October 19, 2011 Construction Progress Report. Construction Progress Report – October 19, 2011 Contract sum to date:$ 162,736,722* Total completed to.

Slides:



Advertisements
Similar presentations
Tam Valley School Modernization - Phase 1 Summer 2011.
Advertisements

PARKVIEW APARTMENTS 20 Unit Rehabilitation & Site Work ISLA VISTA, CA. Joint Cities-County Affordable Housing Task Group October 23, 2008.
CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,
CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.
Hospital of the Future Construction Update as of Dec. 3, 2010.
Carols Project. New foundation (24 x 40) poured in 1990 Old house (24 x 34) moved onto the new foundation Addition added but not tied into house Interior.
Westminster Town Hall 1770 ● 1835 ● 1889 ● 2011 Continuing a Historical Legacy.
Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.
Update on FCPS Construction/Renovation Projects August 2009.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Boren School Preparing an existing wall to receive structural improvements.
Grimsby Secondary School
Johanna Mikitka AE-390 October 13, 2004
Chuck Barry (702)
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
February 1, 2012 Casino Facility Progress Report.
[d] – desk, dining room, door; [b] – bed, bedroom, bathroom; [s] – sofa, poster, sweep; [w] – wall, window, wardrobe.
Site Plans.
Carpentry Basically a person who builds or repairs wooden structures, as houses, scaffolds, or shelving.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
IET 120 CONSTRUCTION PROJECT Name: Clarence Hunt.
Practice House 1. Make a rectangular foundation 2. Put an interior wall in the middle. 3. Add an exterior door, interior door and at least one window on.
Transportation Center Rolling Forward Into Phase 2 October, 2008.
Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.
© OnCourse Learning. All Rights Reserved. Basic House Construction Learning Objectives  List the primary styles of residential architecture  Describe.
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Click here for Game Rules & Instructions: Copyright © 2009, Steve Beutler, All rights.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
Trinity Lutheran Church Major Maintenance Tuesday, February 17, 2015.
Building Plans.
1 NEW FAIRFIELD FREE PUBLIC LIBRARY Renovation Project
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. August 2007 Prepared by:
PHOTO. NO.DATE: 12/20/14 REVISIONS Construction Services 170 Long Lane Middletown, CT WESLEYAN U N I V E R S I T Y P AB HOME AVENUE INTERIOR.
Houston TranStar Building Expansion 2009 Status. Aerial of Existing Building.
Design Development Code analysis Partition types.
Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”
Prof Ralph V. Locurcio, PE CON 2001 CVE Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.
Inspection photo requirements Following this procedure will ensure that you get paid for the work completed. All rights to this document are reserved by.
Floor Plan Sketch on 17” x 22” Graph Paper  Rough Scale Drawing  Room dimensions  Room Names  Basic House Characteristics AutoCAD floor plan including:
Learning, Health, and Safety Capital Project Alternates and Change Order
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Building Your Future with Mountain Peak Homes Corinne T. Moritz Bella Vista Subdivision, Mountain Peak Homes1.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
“Best Improved Residential Property” and “Best Improved Commercial Property” City of Hallandale Beach City of Choice.
Construction Foundations of Technology Construction © 2013 International Technology and Engineering Educators Association STEM  Center for Teaching and.
Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016.
WBS Experiment Infrastructure: LArTF GPP Project Status Dixon Bogert Prepared for the MicroBooNE Collaboration Meeting 11/02/12.
MICROSOFT PROJECT MODULE 2 - BUILD A HOUSE.
Foundations of Technology Construction
Major Steps In Building a SFR
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Upcoming Activities Fun Fact Click here to view the live WEBCAM
Passive Solar Home Design Project
Sneed Property th Ave E, Puyallup Exterior of House
Progress Report 11/10/11.
The Hollies, Ravenshead
New White Lake Township Library
Foundations of Technology Construction
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Concept Features Bus entry, exit and drive are separate from visitor and parent entry and drive Additional area behind building for bus traffic and turn-around;
Minuteman Vocational Technical Regional High School Progress
Value of contract: Length of contract: Contract start date:
Value of contract: Length of contract: Contract start date:
Presentation transcript:

October 19, 2011 Construction Progress Report

Construction Progress Report – October 19, 2011 Contract sum to date:$ 162,736,722* Total completed to date:$ 86,000,000* MBE / WBE awarded to date:$ 32,000,000 Average daily # of construction workers on-site: 310 Note: * - Amounts based on October 2011 pay application; the most recent pay application received to date.

Arial View of Entire Property

Cage / Players’ Services

High Limit Slots

Back of House – Human Resources Training Room

Back of House - Table Games Training Room

Back of House - Office Area

Back of House – Wardrobe Desk

Back of House – Static Flooring Installation in Computer Room

Pouring of Sidewalks / Walkways

Northeast Corner Exit – Forms for Stairs

Loop Road Hardscaping/Landscaping

Construction Progress Report – October 19, 2011 Four Week Look Ahead Casino Interior : – Arrival/installation of permanent chiller units; – Installation of kitchen equipment to begin; – Installation of drywall ceiling and soffits at main promenade; and – Continuation of metal stud walls and interior rough-ins. Casino Exterior : – Installation of landscaping; and – Continuation of exterior finish insulation system on north walls. Parking Garage : – Initialization of electrical distribution; – Installation of masonry stair shafts; and – Demobilization of tower cranes. Road Work : – Continuation of Miami Street widening efforts on south side; and – Installation of infrastructure for new traffic signals.