DEFERRED MAINTENANCE PROGRAM UPDATE REPORT Accomplishments and 2016 Planned Events October 1, 2015 1.

Slides:



Advertisements
Similar presentations
SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL.
Advertisements

Recent Bond Accomplishments. Bordeaux Elementary Remodel.
June 8, 2011 Irvine Unified School District. What is a Modernization? Eligibility Permanent buildings - 25 years old Portable buildings - 20 years old.
Capital Projects Investments Levy Cycle Tom O’Brien – Facilities & Operations Director February 17, 2015.
Cambrian School District 5-year Facilities Maintenance Plan Update 8/25/11.
Measure G Overview March 9, Measure G School Facility Improvement East Side Union High School District To provide greater security and safety, relieve.
Current Project Update October 25th 2012 Good Evening!!!
May 6, 2010 Irvine Unified School District HMC Architects.
Construction Update September 2014 Madison Elementary School District.
1 Capital Budget and Capital Improvement Program Request Public Hearing AGENDA 7:00 - 7:15Presentation of Capital Improvement Program Budget Request 7:15.
Decatur School Board Meeting August 19, Decatur Superintendent’s Report August 19, 2013.
Madison Elementary School District #38 Construction update Bond & Capital 6/5/12.
Facilities Update Site Improvements Encinitas Union School District September 5, 2006.
2014 Bond Issue Projects September 22, On August 5, 2014 the voters of South Lake Schools passed a $25 million bond proposal This PowerPoint will.
Accredited with “Distinction in Performance” St. Clair R-XIII School District.
Facility Construction Project Workplan 2012 A Presentation to the Board of Education Prepared by Facilities and Planning May 15, 2012.
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Torrance Unified School District Bond Measure Y Bond Measure Z Quarterly Construction Update September 30, 2009.
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. August 2007 Prepared by:
2014 construction bond planning Needs assessment- what are we missing Site visits- in and out of district Safety concerns Life cycle evaluations- where.
Construction Report August 18, Projects Site Improvements Track replacement and turf Generators.
Successful Bond Programs (Community Engagement) Cathy Allen, Chief Operations Officer Facilities Support Services September 22,
OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District January 23, 2012 EDUCATE  ENGAGE  EMPOWER 1.
SUMMER 2015 DEFERRED MAINTENANCE
DEFERRED CAPITAL PROJECTS REPORT Facilities Sub-Committee June 11, 2013.
OVERVIEW  Review of completed projects  Update on large construction projects  Update on other miscellaneous projects.
1 Five Year Capital Improvement Schedule Lancaster County School District
OVERVIEW  Review of completed projects  Update on large construction projects  Update on other miscellaneous projects.
Making Our Facilities Better Board of Directors Update – Wednesday, July 24, 2013.
MODERNIZATIONS “The First Five” Golden West Elementary Lathrop Elementary Lincoln Elementary Sequoia Elementary Shasta Elementary December 8, 2015.
DEFERRED MAINTENANCE PROGRAM NORTH DAVIS ELEMENTARY PROJECT DESCRIPTIONS 2015/2016 Planned Events November 19,
MODERNIZATIONS MEASURE G OVERSIGHT COMMITTEE September 8, 2015.
OVERVIEW  Review of completed projects  Update on large construction projects  Update on other miscellaneous projects.
OVERVIEW  Review of completed projects  Update on large construction projects  Update on other miscellaneous projects.
Measure G Bond Projects. Message from the President ….. Monument Refurbishment Project.
HVAC Installation Projects Gym and Locker Rooms Renovation Project DLR Group April 11, 2016.
OVERVIEW  Review of completed projects  Update on large construction projects  Update on miscellaneous projects.
Vision for the Future Spring 2016 Campus Open Forum APRIL 7, 2016 STUDENT CENTER CONFERENCE ROOM.
FY2017-FY2026 GDRSD Capital Plan-June 22, 2016 Jared Stanton, Director of Business and Finance.
HVAC Installation Projects Administration and Multi-purpose Buildings Elementary Schools|1 Dolland 2 Edmondson 3 Moffitt 4 Sanchez Middle School| 5 Waite.
Facilities Focus Group
White Pigeon Community Schools
April 2016 Bond / Facilities Update Presentation
Bond Project Update September 2017
Capital Construction Bond Program
Fall 2017 Update: Physical properties and sinking fund
College Park Elementary School & Turnbull Learning Center
LOMPOC UNIFIED SCHOOL DISTRICT - BOARD UPDATE
Capital Improvements Presentation
Dr. Joseph Meloche Superintendent of Schools Mrs
2012 and 2014 Bond Update Citizens’ Bond Oversight Committee
Troy School District 2013 Bond Program – Series 1 Construction Update September 2016 Barton Malow | TMP.
The summer of 2018 and all the work that has taken place
Local Funding for Capital Improvements
Project S.O.A.R December 10, 2018 Meeting
Troy School District Bond Program – Series 1 Construction Update
Operations Department
Charter Oak Unified School District
Capital Outlay Workshop
Facility Advisory Committee Meeting
Recent Bond Accomplishments
Draft Bond Work Plan A Presentation to the
Troy School District 2013 Bond Program – Series 1 Construction Update June 2016 Barton Malow | TMP.
Deer Valley Unified School District October 11, 2017
Troy School District Bond Program – Series 1 Construction Update
Monterey Peninsula Unified School District
FY Capital Improvement Program Draft
Facilities Update Garden Grove Unified School District
Presentation transcript:

DEFERRED MAINTENANCE PROGRAM UPDATE REPORT Accomplishments and 2016 Planned Events October 1,

STRATEGIC PLAN – Strategy 2 (b-e)  Board Reviewed Deferred Maintenance Project Listing – June 5, 2014  Project Listing Presented – Estimated Value $26M  Board Adopts Resolution for COP’s Financing for Deferred Maintenance Projects  Resolution No – June 19, 2014 (Education Code )  Program Terms and Definitions  Operations – Daily Activities, Custodial & Grounds Services  Routine Maintenance – Minor Repairs, Standard Work Orders, Special Projects  Deferred Maintenance – Building System Replacement (i.e. Roofing, Mechanical, Finishes)  Facilities Modernization – Multiple System Replacement/Life-Cycle Upgrades  Facilities New Construction - Major Capital Outlay, Growth & Program Alignment HISTORY - BACKGROUND 2

 2015 Summer Deferred Maintenance & Facilities Project Descriptions  Relocatable Classroom Replacement – Cesar Chavez Elementary & Holmes Jr. High Schools  Repair Multi-purpose Building – Valley Oak Campus (Da Vinci Charter)  Gym Bleacher Replacement/Modifications – Emerson Jr. High & Harper Jr. High Schools  Restroom Building Replacement – Holmes (In Progress)  Administration Office – DVCA at Emerson Jr. HS  District Wide Projects  Roofing Projects  Fire Alarm Systems  Intercom/Clocks/Bell Systems  Phone Systems  Heating, Ventilation, Air Conditioning Systems  Energy Management Systems (HVAC)  Interior/Exterior Finishes – Paint, Stucco & Window Blinds  DSA Legacy Project Closeouts – 5 of 11 Outstanding Closed  Flooring (Carpet/Vinyl) – District Wide (Rescheduled for Summer 2016)  Playground Equipment Area Repairs Birch Lane ES & Montgomery ES (Rescheduled Summer 2016)  Parking Lot Resurfacing, Seal Coat & Striping – District Wide (Rescheduled for Summer 2016) DEFERRED MAINTENANCE & FACILITIES PROJECT DESCRIPTIONS 3

 Projects Completed to Date $10.5M Intercom/Clocks/Bell 11 Complete, 3 In Progress Fire Alarm System Repaired5 Sites Phone System Upgrades 12 Completed, 3 In Progress Classroom Replacements27,716 Total Square Foot Area) Roof Replacement553,800 Total Square Foot Area) Mechanical System Adds/Replacement7 Split Systems Installed Special Systems Modernization Performed Interior Bleachers Landscape Tree Replacement Projects75 of Trees Planted) Restroom Building Replacement Holmes Jr. High School New Relocatable Office (24’ x 60’) DaVinci Charter Academy DEFERRED MAINTENANCE PROGRAM RECAP OF 2015 PROJECTS COMPLETED 4

 New All Student Center – Davis HS $7.2M ($5.5M Grande Land Sale) In Design Development – Work Group Meetings Being Held  Also at Davis High School Stadium Bleachers (Visitor) $ 500K Student Parking Lot & Tennis Court Repairs $ 1.6M HVAC Controls (LRC) $ 50K Misc. Athletic Field Improvements $ 8K  Relocatable Classroom Replacement (4) – Estimated $1.3M Front Drive ADA Access/Parking and New Waiting Area (Plaza) $ 120K  Roofing Repairs – Estimated $750K Patwin Elementary School Pioneer Elementary School Holmes Jr. High School  Paving Repairs$1.69M Birch Lane ES Cesar Chavez ES Valley Oak (Da Vinci Charter) Emerson Jr. High School Holmes Jr. High School  All Weather Tracks $980K Emerson Jr. High School Harper Jr. High School Holmes Jr High School  Exterior Stucco Replacement $1.6M Marguerite Montgomery Elementary School Fred T. Korematsu Elementary School DEFERRED MAINTENANCE PROGRAM PROPOSED 2016 SUMMER WORK SCHEDULE - $16.25M 5

DEFERRED MAINTENANCE PROJECT LISTING 2015/16 6

QUESTIONS DEFERRED MAINTENANCE PROGRAM & SUMMER WORK PLAN REPORT 7