1 Managing Distribution System Reliability at Southern California Edison Robert Tucker Thach “Nicholas” Duong Roger Lee OIR R.14-12-014 Workshop May 26.

Slides:



Advertisements
Similar presentations
Facilities Capital Planning and Management A program management overview prepared for Ferndale School Districts Facilities Planning Committee.
Advertisements

DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Early Lessons Learned from DOE-EPRI Framework Experience Melissa Chan MA DPU.
Ward 21 Reliability Cedarvale and Surrounding Area Prepared for Councillor Mihevc Toronto Hydro System Planning March 25, 2015.
Vendor Briefing May 26, 2006 AMI Overview & Communications TCM.
Reliability Software1 Reliability Software Minimum requirements & Best practices Frank Macedo - FERC Technical Conference July 14, 2004.
Building A Smarter Grid Through Distribution Automation DOE Projects OE & OE April 2013 Copyright © 2012 Consolidated Edison Company of New.
Pavement Management Program Overview February 10, 2015 Presented By: Christopher J. Ott, E.I.
NCHRP 07-21: Asset Management Guidance for Traffic Control Devices, Barriers, and Lighting 2014 ATSIP Annual Meeting Presented by Nancy Lefler Vanasse.
Mitigating Risk of Out-of-Specification Results During Stability Testing of Biopharmaceutical Products Jeff Gardner Principal Consultant 36 th Annual Midwest.
Nelson Hydro Downtown Conversion July 26, 2010 Project Overview.
Pipeline Replacement Programs Presentation By Frank Radigan Hudson River Energy Group June 26, 2012.
Vegetation Management
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
UK WIR The UK Experience Christopher Royce Anglian Water Services.
© ABB Group June 10, 2015 | Slide 1 1MRS A self healing power system for the accurate fault location and zone concept T&D Smart Grids Europe 2012.
1 March 1, 2007 Report An Overview October 30, 2006 – Staff Workshop.
PAVEMENT MANAGEMENT SYSTEMS OVERVIEW Lecture 2. n Provide a historical perspective of the evolution of PMS over the last 20 years n Describe the basic.
Electric Distribution Reliability OIR R Workshop May , 2015.
Sustainment Management Systems
Naperville’s MUNI Marla Westerhold I n Slide Show mode, the slides and audio should start automatically. If this doesn’t happen.
Presentation to Carillion The Equipment Rental Specialists 9 th June 2010 The Equipment Rental Specialists Vp plc Final Results for the year ended 31 March.
RAM Modelling in the Project Design Phase Friday 30 th April, 2010 Paul Websdane Reliability Modelling for Business Decisions Asset Management Council.
ACTION PROPOSAL FOR FLYWHEEL ENERGY TECHNOLOGY Enhance future grid reliability, interoperability, & extreme event protection In 20 years, the flywheel.
Oncor Electric Delivery Oncor Electric Delivery Restructure An Engineering & Construction Perspective SWEDE Conference May 11, 2007 San Antonio Mark Burt.
Metropolitan Planning Council Roundtable Discussion November 17, 2011 ComEd J. Tyler Anthony Senior Vice President, Distribution Operations.
Rulemaking PacifiCorp Responses to ALJ Ruling May 26, 2015.
…While Investing To Achieve Excellence In Reliability 30% Transmission capital investment 03-06; $ millions Distribution capital investment 03-06; $ millions.
1 Power Quality Mary Santori, P.E. Senior Engineer September 12, 2013.
1 Ministry of Transport, Public Works and Water Management.
Section 3 TRANSMISSION & DISTRIBUTION US Bulk Power Transmission System Transmission & Distribution (T&D) Components New T& D Technologies This product.
Electric Infrastructure Workshop Gulf Power Company January 23, 2006.
SDG&E Electric Reliability Reporting CPUC Workshops May 26-27, 2015.
4/22/2017 WHAT IS THERMOGRAPHY?
EDISON INTERNATIONAL® SM SCE Project Story CIM User Group 10/12/2010 Jim Horstman Southern California Edison.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
Physical Building Audit Physical Building Audit By; Engr.Dr.Attaullah Shah PhD ( Civil) Engg, MSc Engg ( Strs), BSc Engg ( Gold Medalist),), MBA, MA (
GBA IT Project Management Final Project - Establishment of a Project Management Management Office 10 July, 2003.
Technical Conference on Net Metering Load Research Study November 5, 2014.
Planning and Analysis Tools to Evaluate Distribution Automation Implementation and Benefits Anil Pahwa Kansas State University Power Systems Conference.
© ABB PTMV - 1, ABB Overhead Distribution Systems.
hydroAMP asset management framework
1 Presentation By: Mr.O. Aphane Acting Deputy Director General: Electricity, Nuclear and Clean Energy (on behalf of the Director General, Ms N Magubane)
IAEC Reliability Webinar Presented by: Regi Goodale and Ethan Hohenadel December 11,
1 Overview of Reliability Requirements XYZ Cooperative Date: abc.
Frankfurt (Germany), 6-9 June 2011 Louise Jakobsen, Danish Energy Association – Denmark – Session 3 – Paper 0811 Louise Jakobsen, Danish Energy Association.
Prioritizing Booster Pump Station Improvements Tom Peters, P.E. May 2, 2008.
AEE So Cal September 24, 2015 Integrating Renewables and The Distribution Grid of the Future 1.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.
Equipment Life Optimization Program (ELOP) Doug Hilleman February 10, 2011.
FOR OVER 100 YEARS…LIFE. POWERED BY EDISON. Southern California Edison Presentation to City of Palos Verdes Estates December 13, 2011 Marvin Jackmon, Regional.
ACEC National Energy and Environment Challenges in Asset Management? Brian Long Transmission Line Performance Xcel Energy August 15, 2015.
PG&E’s Distribution Resources Planning READ AND DELETE For best results with this template, use PowerPoint 2003 Planning the “Networked Grid“ Integrated.
Distribution systems basic techniques and radial networks.
Grid maintenance expenses Commerce Commission Workshop 2 March 2010.
Identifying drivers of expenditure. Reasons for spending money 2 Effective regulation requires an understanding of why a business spends money Many different.
Resiliency and Reliability
Best Practices Consortium
Maintenance strategies
Overhead Distribution Systems
Predictive-Based Maintenance Strategy
Integrating Distributed Energy Resource into Grid Operations
Transmission Planning in a Modern Market Environment
Presented by: Keith Gray & Julienne Sugarek CenterPoint Energy
Irvine Smart Grid Demonstration Distribution Volt / Var Control
SCE’s 2019 Wildfire Mitigation Plan
Presentation transcript:

1 Managing Distribution System Reliability at Southern California Edison Robert Tucker Thach “Nicholas” Duong Roger Lee OIR R Workshop May 26 & 27, 2015

2 Current Circuit-level Reliability Management Programs Current Distribution System Maintenance Programs Reliability Refresher Discussion of Tools Assessment of Total System Need Allocation of Funding Among 8 SCE Regions Worst Circuit Rehabilitation Program: Identifying the Worst Circuits Identifying Work on Each Circuit Documentation Fast Track WCR Program: Circuit RADAR Challenges: Volatility / Probability Balancing Circuit vs. System Performance Cost-effectiveness Overview

3 Current Circuit-level Reliability Management Programs Southern California Edison's various asset management programs can be divided into three categories based on their drivers and anticipated impacts to system reliability metrics such as SAIDI, SAIFI and MAIFI. The first category of programs is designed to manage system and circuit reliability utilizing rigorous mathematical modeling which can quantitatively predict future reliability as a function of various types and levels of infrastructure replacements and circuit modifications. The primary program in this category is the Worst Circuit Rehabilitation (WCR) program which focuses investments on poorly performing distribution circuits. Programs in the second category are also designed to manage system and circuit reliability but employ less rigorous analytical methods. For many of these programs, reliability benefits are difficult to quantify with precision at this time. Some of these programs have been in place at SCE for years, such as the Substation Infrastructure Replacement program, the Underground Oil Switch Replacement program, the Capacitor Bank replacement program, and the Automatic Recloser Replacement program. Other programs have been initiated by SCE very recently, such as the Cable Testing program, the Cable Injection program, and the Overhead Conductor Program. The third category includes programs which are designed to address problems unrelated to in-service failures of electrical equipment but which may generate reliability benefits. These programs are not explicitly designed for targeted improvements in system reliability metrics, and they are not expected to have a significant impact on system reliability performance. Examples of these programs include the Load Growth program, the 4 kV cutover programs, the deteriorated pole replacement program, and the Deteriorated Vault and Manhole Program.

4 Current Distribution System Maintenance Programs SCE’s Distribution Inspection and Maintenance Program (DIMP) pursues public and worker safety and regulatory compliance by completing scheduled Detailed Inspections and Grid Patrols of the distribution system in conformity with the California Public Utilities Commission's (CPUC) General Order (G.O.) 165, and in accordance with G.O. 95, G.O. 128, SCE standards, and good utility practice. General Order 165 was enacted on March 31, 1997 to establish maximum time intervals of inspection frequency of all electric distribution facilities within the jurisdiction of the CPUC. The basic premise of G.O. 165 is that all distribution assets must be patrolled every year for safety and reliability issues and the identification of significant G.O. 95 and 128 discrepancies. General Order 165 also requires these same assets to have a close up detailed inspection every 5 years (or less) to identify safety and reliability issues as well as all G.O. 95 and 128 discrepancies.

5 Current Circuit-level Reliability Management Programs Current Distribution System Maintenance Programs Reliability Refresher Discussion of Tools Assessment of Total System Need Allocation of Funding Among 8 SCE Regions Worst Circuit Rehabilitation Program: Identifying the Worst Circuits Identifying Work on Each Circuit Documentation Fast Track WCR Program: Circuit RADAR Challenges: Volatility / Probability Balancing Circuit vs. System Performance Cost-effectiveness

6 Reliability Refresher The challenge to SCE’s reliability comes primarily from in-service equipment failures.

7 This challenge will increase because the system is continuing to age…and …

8 … the probability of failure increases, exponentially, with age.

9 The volume of an infrastructure type wearing out each year will increase until the average age of that population plateaus. Whether replacements are effected reactively or preemptively, as well as circuit design and crew response, will affect system and circuit reliability.

10 Current Circuit-level Reliability Management Programs Current Distribution System Maintenance Programs Reliability Refresher Discussion of Tools Assessment of Total System Need Allocation of Funding Among 8 SCE Regions Worst Circuit Rehabilitation Program: Identifying the Worst Circuits Identifying Work on Each Circuit Documentation Fast Track WCR Program: Circuit RADAR Challenges: Volatility / Probability Balancing Circuit vs. System Performance Cost-effectiveness

11 Risk assessment tools (CYME-RAM & in-house tools) can be used to assess circuit SAIDI/SAIFI/MAIFI as a function of design and P(f|age) of circuit elements. Circuit modeling

12 Weibull curves are developed to determine P( f | age)

13 Circuit reliability modeling ( highly labor intensive ) can quantitatively assess benefits Analytical assessments inform SCE’s guidelines which are used to identify remediation work which is both effective and cost-effective.

Circuit modifications such as Branch Line Fusing (BLF) and Fault Indicators (FI) are the most cost-effective investment in system reliability Initial layers of circuit automation are, relatively speaking, the next most cost- effective investment in system reliability  Note: Increasing layers of automation beyond initial layers will yield diminishing returns on investment After FIs, BLFs and automation, replacement of aged cable is the next most cost-effective investment in system reliability  Note: Replacement of younger cable will yield rapidly diminishing returns on investment Compared to the top three categories above, replacement of other distribution infrastructure (i.e. service transformers, poles, underground vaults, secondary services, etc…) is typically less cost-effective as an investment in system reliability  However, such scope elements are often justified for other reasons: safety issues, compliance requirements, operational flexibility, specific customer issues, opportunity work, etc… 14 Analysis-informed guidelines for designing WCR projects

15 Current Circuit-level Reliability Management Programs Current Distribution System Maintenance Programs Reliability Refresher Discussion of Tools Assessment of Total System Need Allocation of Funding Among 8 SCE Regions Worst Circuit Rehabilitation Program: Identifying the Worst Circuits Identifying Work on Each Circuit Documentation Fast Track WCR Program: Circuit RADAR Challenges: Volatility / Probability Balancing Circuit vs. System Performance Cost-effectiveness

16 Conclusion: Without a program to address infrastructure aging, system SAIDI (and SAIFI) would increase significantly. Assessing the consequence of inaction

17 “500 IR” = Program of replacing 500 miles of the most risk-sensitive cable + cost-effective mitigation enhancements on our “worst-performing” circuits Options for various levels of reliability-focused infrastructure investment

18 Having the established the annual system need for investment, the next step is to maximize the return on that investment. Funding to address total system need is allocated among the 8 Regions according to % contribution to System SAIDI and SAIFI Allocation of funding among 8 Regions

19 Within each Region, circuits are prioritized under multiple categories of reliability performance.

20 Specific Example: Octane 16 kV (scoped for 2016 project)

21 Data Source: Outage Data Records Management (ODRM) The outage history is researched on each targeted circuit.

22 Rehabilitation work scopes are developed using risk-informed guidelines, outage histories, and circuit design and component age. Building Remediation Work Scopes

23 In summary, the WCR process is systematic and objective

24 The WCR annual report records the method and results.

25 For each “worst circuit”, an explanation of its selection and its disposition, and a description of its remediation are documented.

26 Current Circuit-level Reliability Management Programs Current Distribution System Maintenance Programs Reliability Refresher Discussion of Tools Assessment of Total System Need Allocation of Funding Among 8 SCE Regions Worst Circuit Rehabilitation Program: Identifying the Worst Circuits Identifying Work on Each Circuit Documentation Fast Track WCR Program: Circuit RADAR Challenges: Volatility / Probability Balancing Circuit vs. System Performance Cost-effectiveness

27 Rolling 12-Month Circuit Performance Report (RADAR) ► Results in awareness of circuit performance and “Fast Track,” (i.e., expedited), WCR projects.

28 Current Circuit-level Reliability Management Programs Current Distribution System Maintenance Programs Reliability Refresher Discussion of Tools Assessment of Total System Need Allocation of Funding Among 8 SCE Regions Worst Circuit Rehabilitation Program: Identifying the Worst Circuits Identifying Work on Each Circuit Documentation Fast Track WCR Program: Circuit RADAR Challenges: Volatility / Probability Balancing Circuit vs. System Performance Cost-effectiveness

29 Circuit performance can be highly volatile and difficult to predict

30

31 30 Year Average CMI (without & with WCR) – Alfredo 16 kV WCR Yearly CMI with WCR (4 simulation results shown) Monte Carlo simulations vs. Calculated Average Forecasts Remediation projects should focus on long term average benefits. The nature of probability tells us that no remediation project on any individual circuit can guaranty short term improvements.

32 “System” ≡ Because remediation work on each circuit varies in benefit/cost, “gold plating” a circuit penalizes the system. The “system” benefits more when remediation resources are distributed across multiple circuits than when resources are focused on one circuit. 123 How much investment to make on any given circuit?

33 Cost-effectiveness

34 Current Circuit-level Reliability Management Programs Current Distribution System Maintenance Programs Reliability Refresher Discussion of Tools Assessment of Total System Need Allocation of Funding Among 8 SCE Regions Worst Circuit Rehabilitation Program: Identifying the Worst Circuits Identifying Work on Each Circuit Documentation Fast Track WCR Program: Circuit RADAR Challenges: Volatility / Probability Balancing Circuit vs. System Performance Cost-effectiveness Summary