1 | Project Briefing Bruce Highway Upgrade Caloundra Road Interchange to Sunshine Motorway NCHD-3074 and NCHD-3075 North Coast District | 03 September.

Slides:



Advertisements
Similar presentations
Newsletter 18 January 2013 Inside this Issue: Building Code 2013 Latest CPI Index Bullying and Harassment Building and Construction Code Improve your Workplace.
Advertisements

Supplier Meeting regarding supply of Low Carbon Vending Services Steph Holmes Head of Procurement Jessica Osowski Category Manager – Business Services.
CEM-512 Value Engineering Highway Project: South Interchange.
TRE ANNUAL MEETING Grant Levi, NDDOT Director November 26,
Capilano Road Improvement Project WELCOME TO THE OPEN HOUSE.
Sheffield Highway Maintenance PFI Project South West Community Assembly Briefing Thursday 13 th January 2011 Michael Platt – Project Director.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION South Cascade Drive/Miller Road (Formerly Route 219)/ Cattaraugus Creek Design-Build Project (PIN ,
JANUARY 9, 2002 SCAJAQUADA CORRIDOR STUDY Grant Street to Parkside Avenue City of Buffalo Fisher Associates Joseph Passonneau & Partners In Association.
Procurement and Tendering Presentation to [NAME OF CLIENT] [YOUR NAME] [DATE]
PUR Miscellaneous Architectural and Engineering Services RFP Mandatory Pre-Proposal Conference July 22, 2013 [ Sample Image: Place a 9.5” x 4.75”
SCDOT’s Strategic Direction Janet Oakley Secretary of Transportation South Carolina Alliance to Fix Our Roads September 22, 2014 Janet Oakley Secretary.
Route 28 South of I-66 Corridor Safety and Operations Study Technical Committee Meeting #2 June 25,
U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.
MTF Rail Development Forum
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Route 110 over Route 27 Design-Build Project (PIN , D900027) Town of Babylon, Suffolk County Request.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Interstate 81 Bridges over Route 80 Design-Build Project (PIN , D900023) Town of Tully, Onondaga County.
1 Collaborative working in action – an employee perspective Adrian Fricker RMT Lead TU H&S Representative Des More TSSA Lead TU H&S Representative.
Transport Investing in Regions SEATS Meeting 17 February 2012.
Constructing West Midlands Martin Merrix Divisional Manager, Urban Design.
Presented to presented by Truck Size and Weight Wisconsin’s Legislative Process AASHTO Subcommittee on Highway Transport 2013 July 10 th Wilmington, NC.
Barrington Road at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study Hoffman Estates Village Hall June 27, 2012.
Alameda Creek Bridge Replacement Scoping Meeting March 4, 2014.
New Decade - New Challenges Annual Conference September 2010 Water Services Training Group 14 th Annual Conference New Decade – New Challenges 9 th September.
The Roads Ahead Leroy D. Alloway, Director Community Development.
Runways – 7 July Paul Harwood
Presentation by Wendy Launder General Manager CRC and Small Business Programs.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
Mid Wales LTP Stakeholder Workshop 3 rd October Presentation by Ann Elias and Janice Hughes.
MnDOT-ACEC Annual Conference March 5,  Capital planning and programming at MnDOT  Major considerations  A more transparent and collaborative.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Asset Management Performance (Structures) Awtar Jandu Safe Roads, Reliable Journeys, Informed Travellers Bridge Owners Forum Cambridge -13 September 2005.
Manage by Measure: Just Do It AASHTO SCOPM Annual Meeting October 23, 2009 Steve Simmons TxDOT Deputy Executive Director.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
Presentation to HAUC (UK) Wednesday 30 May 2012 RINA London.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
3000 Connecticut Avenue, N.W., Suite 208 Washington, DC
Listening to you, working for you Bexley’s Children’s Services Prevention Agenda Thriving Families Service Vision Children do not wait.
PPP Legal & Regulatory Framework. PPP Policy In July 2008 GOK approved the PPP policy directive through which: PPPs are identified as a method for investing.
Meet the Buyer West Yorkshire Transport Fund. WELCOME Mark Roper & Steve Carmody.
D.d. delivers district department of transportation d.d. delivers FAISAL HAMEED RONALDO T. NICHOLSON. P.E. Innovative Project Delivery Processes Innovative.
Utah Research Benefits Value of Research Taskforce July 29, 2015 Cameron Kergaye Utah Department of Transportation.
HORIZON 2020 W ORK PROGRAMME DG Research and Innovation.
JOHNSON STREET BRIDGE PROJECT COUNCIL WORKSHOP MAY 21, 2009.
Work Related to Senate Bill 2202 (effective January 1, 2001)
U.S. 20 Intersection Improvement Project at Waverly Road Porter Town Hall Thursday, August 13, 2015.
I-465 at I-65 Interchange Modification Public Meeting 6:00pm Monday, October 1, 2012 South Grove Intermediate School Beech Grove, Indiana.
1 © 2013 Protiviti Inc. All Rights Reserved. This document has been prepared for use by OOCEA’s management, audit committee, and board of directors. This.
Design-Build in Minnesota Minnesota Department of Transportation.
Simon Amor Asset Development Manager
DECC Framework Contract for Innovation Delivery Support – presentation to potential contractors Thursday 20 October.
Rebuilding our regional centres in the context of the NDRRA Matt Bradbury, Partner Ben Yeoh, Senior Associate 11 October 2012.
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
Industry Briefing 25 May 2016.
Brand Activation Agency
Stage 2 Light Rail Transit Program “In the ground ready”
Four Winds Condominium Association August 2, 2017
Supplier Briefing Capital Works Program
Stakeholder Consultation
(15 minute presentation)
The Oakton Condominium Association September 12, 2017
Presented by: Jim Hefferan Project Director ICB Upgrade Project
Ohio’s Research Initiative for Locals
San Benito County Local Transportation Authority Request for Proposals # Operation of San Benito County Express and Specialized Transportation.
SR 400 Express Lanes: Market Sounding
Manilla Low Level Crossing Project
Building a secure Home Affairs
Suffolk Chamber of Commerce Transport & Infrastructure Group
Information & Market Engagement
Presentation transcript:

1 | Project Briefing Bruce Highway Upgrade Caloundra Road Interchange to Sunshine Motorway NCHD-3074 and NCHD-3075 North Coast District | 03 September 2015

2 | Agenda 1.Welcome- District Director ( Doug Wass) 2.Project Overview- Project Director ( Gavin Soward) 3.Project Scope and Procurement- Director Infrastructure Procurement ( Steve How Lum) 4.Questions

3 | Our values

4 | Diversity and inclusion We have a responsibility to ensure our employee pool reflects and better serves the diverse nature of the Queensland community. Diversity brings different perspectives into the workplace. An inclusive workplace ensures employees feel confident and supported to contribute and participate fully in the workforce. Diverse and inclusive teams: -generate new ideas -challenge the status-quo -introduce fresh ways of looking at problems -offer a wider range of potential solutions.

5 | We connect Queenslanders… We get people and industry moving We plan, we invest We deliver, we manage We regulate We help, we educate

6 |

7 | Project Overview Project Director Gavin Soward

8 | Project location

9 | Project overview Six laning of Bruce Highway (including corridor planning for eight lanes) between the Caloundra Road and Sunshine Motorway interchanges Upgrades to the Caloundra Road and Sunshine Motorway interchanges to replace the existing at-grade ramp intersections Two lane service road on the western side of the Bruce Highway Rationalisation of existing highway access with upgraded ramp arrangements.

10 | Project need AADT AADT AADT

11 | Project benefits Provides a safer highway network Reduction in delays for vehicles and improved travel times Improves capacity for the Bruce Highway Upgrades existing interchanges Provides an alternative route for local traffic and a cycling route between Steve Irwin Way and Tanawha Tourist Drive, by a new western service road Removes the at-grade Sunshine Motorway westbound connection to the Bruce Highway northbound entry ramp Replaces the existing deteriorated concrete pavement on the Bruce Highway. Posted speed returned to 110km/hr.

12 | Funding $1.134 billion Bruce Highway Upgrade Project Caloundra Road to Sunshine Motorway Funded on an 80:20 basis under the Infrastructure Investment Program with the Australian Government contributing $907.2 million and the Queensland Government contributing $226.8 million Estimated construction budget of $500 million (excluding GST).

13 | Environment 21 April Referred the project to the Department of the Environment (DOE) under the Environmental Protection and Biodiversity Conservation (EPBC) Act May 2015 – DOE deemed the project a controlled action and  issued an information request.  requires an additional public consultation phase.  prepared a recommendation for the federal Minister for the Environment post review of the additional information, public comments to approve with conditions or to not approve the action. The Department of Transport and Main Roads will provide further information during this process.

14 | Project Risks Traffic management  Bruce Highway 62,000 (Annual Average Daily Traffic - AADT)  Caloundra Rd 29,000 (AADT)  Sunshine Motorway 39,000 (AADT)  Service roads and commercial vehicles. Design and construction management  Staging  Environment  New bridges and demolition of existing bridges  Geotechnical  Flooding. Stakeholder management.

15 | Challenges for proponents Minimising impact on vegetation in the South West corner of Caloundra Road Interchange (CRI) through Beerwah State Forest Traffic management during construction Improved access for the tourist precinct.

16 | Caloundra Road Interchange

17 | Director (Infrastructure Procurement) Steve How Lum

18 | Probity A Probity Advisor has been appointed to oversee the tender and procurement process. Mr Greg Edmonds Project Procure 144 Edward Street Brisbane Qld 4001 Tel:

19 | Key Dates 3 September 2015 Release RFP 1 October 2015 Close RFP 30 October 2015 Notify shortlisted tenderers for Stage 1 2 November 2015 Stage 1 commences 14 March 2016 Stage 1 closes July 2016 Contract Award Mid 2020 Construction completed

20 | Procurement methodology Benefits of an Early Contractor Involvement (ECI) process: Contribution for Stage One work to unsuccessful tenderer Interactive process Develop innovative solutions Knowledge of risks and the project Competition Early engagement.

21 | Tendering Prequalification levels ̶ Constructors R5 / B4 / F-Open ̶ Designers BD3, HE3, HD3, TE3, GE3. Joint Venture (JV) requirements ̶ only undertake work for which they are appropriately prequalified ̶ Three varieties of unincorporated JVs ̶ Prequalification applications ̶ Roles of each of the venturers must be defined.

22 | Early contractor involvement Project Briefing Stage One Contracts Stage Two Contract Shortlisting Period Request for Proposal Period Phases 1 and 2Stage 1Stage 2

23 | Selection criteria – Stage One Mandatory criteria highlights Prequalification requirements Joint Ventures Code compliance: Building Code 2013 Queensland Code of Practice for the Building and Construction Industry (July 2013) Accredited under the Australian Government Building and Construction WHS accreditation scheme Receipt of notice to tenderers Page limits.

24 | Phase One evaluation criteria Written responses Evaluation criteria Proposal format.

25 | Phase Two Presentations to the project team Shortlisting to two tenderers.

26 | Stage One Two tenderers invited to enter into a Stage One contract Tenderers prepare Stage Two offer The Department will embed senior designers 16 weeks duration.

27 | Stage One Weekly design meetings with project team Risk analysis and risk apportionment workshops Variation benchmarking workshops Cost planning workshops Mid-term presentation Final presentation Commercial meetings.

28 | Stage Two Workplace Relations Management Plan (WRWP)

29 | Procedural matters Queries during the tendering stage directed to Recommend register two addresses for receipt of Notice to Tenderers (NTT).

30 | Summary Issue Request For Proposal (RFP): 3 September 2015 Prequalification levels  Contractor R4/ B4 / F-Open  Designer BD3, GE3, HE3, HD3, TE3 RFP Closing Date: 1:00pm, 1 October 2015 Award two ECI Stage one contracts: 2 November 2015 Award Stage Two contract: July 2016.

31 | Questions?

32 | Thank you