PROJECT REPORT On REPLACEMENT OF BED BLOCKS ON

Slides:



Advertisements
Similar presentations
Safety Absolutes Green Lake
Advertisements

ODOT Structure Project Manager Training
SEMINAR ON SEGMENTAL CONSTRUCTION OF BRIDGE
Safe Lashing / Securing of Loads
Actions and Retrofit of Post Earthquake-Damaged Bridges
Erecting steel structures Setting up or dismantling cranes or hoists
BOX PUSHING TECHNOLOGY
Breaking and Breaching. Tools Used Sledge hammers –Long and short handled Chisels Pinch point pry bar –“Crow bar” Hacksaw Handsaw Bolt cutter Flat head.
BLR’s Safety Training Presentations
Copyright  Business & Legal Reports, Inc.
Chapter 34 Bridge Construction.
OSHA Subpart Q Concrete and Masonry Construction.
Reconstruction of the Eads Bridge Highway Deck
Copyright  Business & Legal Reports, Inc. BLR’s Safety Training Presentations Cranes and Slings 29 CFR and 184.
Gas Transmission Pipelines
CASE STUDY of Cantilever Method of Erection RUB spanning mtr. NH-5 (Chennai-Kolkata) PREPARED BY: Srinibas Sahoo, AXEN/C/E.Co.Rly/Cuttack P. Choudhary,
 Project Delivery  Design Considerations  Lessons Learned.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
UNIT-I STANDARD SPECIFICATION FOR ROAD BRIDGE
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
BHEL Haridwar. BHEL – A Glance Indian integrated power plant equipment manufacturer, established in Products and services available for Power, Transmission,
Street and Local Roads Inspection and Acceptance of Alternative Pavements.
PRE-FABRICATED STRUCTURES
Public Information Meeting Rehabilitation of Bridge No Flat Rock Hill Road over I-95 Old Lyme, Connecticut Rehabilitation of Bridge No Flat.
Other Construction Projects
BRIDGE BUILDING.
Fire and Emergency Services Company Officer — Lesson 17 Fire and Emergency Services Company Officer, 4 th Edition Chapter 17 — Preincident Planning.
Authorization and Inspection of Cyclotron Facilities Inspections.
Election Commission of India
SFOBB East Span Seismic Safety Project Steve Margaris, Specifications Engineer, Caltrans.
Bridge Engineering (5) Substructure – Abutments and Piers
BOX JACKING. EXPLANATION It is the process in which a pre-cast R.C.C box or a rigid box is pushed into the soil with the help of hydraulic jacks It is.
Maintenance of LWR/CWR
Dedicated Freight Corridor By CHAHATEY RAM CBE/ER.
Cranes and Slings 29 CFR and 184
CAISSON FOUNDATION.
. v related related.
1. 2 Civil Engineering Practice Introduction Instructor: Dr. Attaullah Shah Lecture # 1 Department of Civil Engineering Swedish College of Engineering.
Outline of the Execution Manual for Seismic Retrofitting of Existing Pile Foundations with High Capacity Micropiles Masashi ITANI Takeshi OSHITA Seiichi.
FALL PROTECTION. Duty To Have Fall Protection Protection at or above 6’ level Walking/working surfaces inspected before work begins Employees can only.
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
IENG 301 FUNDAMENTALS OF WORK STUDY AND ERGONOMICS
Joints for Diaphragm Walls
USFD BZA USFD BOOKLET.
MH...CH LECT-021 SYSTEMS CONCEPT Adopting a materials handling systems from overall optimization point of view. Adopting a materials handling systems.
CRS SANCTIONS Chetan Bakshi, CRS/Central. WHY CRS SANCTION IS REQUIRED ? Section 21 & 22 of Railway Act 1989 stipulates that “ No Railway should be opened.
Bulb Piles –Franki Piles or pressure injected footings –Special form of cast in place pile with an enlarged base for increased load bearing F 10-4 Minipiles,
WELCOME ALL FACULTY MEMBERS & ALL PARTICIPANTS OF
Timing (minutes) Learning ObjectiveMain tasks / ProcessResources / tools 5TitleStandard Operating Procedures for Power Press Machine Slide 1 5Index 
. Client: City of Pittsburgh, Brighton Heights Community Objectives : Develop a pedestrian/bicycle bridge reconnecting Brighton Heights to Riverview park.
SANKALCHAND PATEL COLLEGE OF ENGINEERING,
PRESENTATION ON FOUR WEEK SUMMER TRAINING AT PWD GORAKHPUR
Modernization of Track for High Speeds. Modernization Transport more passengers/goods at high speed, safe, economic.
CAISSON FOUNDATION.
FOUNDATIONS.
Load carrying capacity based on load testing Joan R. Casas Technical University of Catalunya (UPC) Barcelona, Spain.
Timing (minutes) Learning ObjectiveMain tasks / ProcessResources / tools 5TitleStandard Operating Procedures for Power Press Machine Slide 1 5Index 
Concrete Repair presented by: Amirhossein Jodeiri Mapua Institute Of Tecnology.
土木工程概论 Introduction to Civil Engineering 第五、六、七章 交通、桥梁与港口工程 Chapter 5 Transportation, Bridge and harbor Engineering.
Concrete Repair.
Temporary Works – P8 Project Practice.
BOX JACKING.
The Final Decision in the Environmental Impact Assessment Procedure in Ukraine as a Multilateral Agreement Tretiak Taras Associate Professor of National.
BUILDING CONSTRUCTION 1
SeminAR ON LINTELS --SANTHOSHKUMAR.M..,.
By T.G.N.C.VAMSI KRISHNA. 171FB M.tech – Civil.
Concrete and Masonry Construction 29 CFR 1926, Subpart Q
CONSTRUCTION METHODS & TECHNOLOGY
Suryoday Technologies ISO 9001:2015 Co.
R.G.G.P (NARWANA) Power point presentation of Building construction
Presentation transcript:

PROJECT REPORT On REPLACEMENT OF BED BLOCKS ON BRIDGE NO. 23 ( BANAS BRIDGE) ON JAIPUR – SAWAI MADHOPUR SECTION (NWRAILWAY) (30x18.29 meters SPANS)

OUR HEARTEST THANKS To Project Guide: SHRI AJAY GOYAL Sr. Prof OUR HEARTEST THANKS To Project Guide: SHRI AJAY GOYAL Sr.Prof.Bridges, IRICEN, PUNE & SHRI V.B. SOOD, Professor Bridge, IRICEN, PUNE PRESENTED BY R. C. MEENA ADEN LINE JP NWR MOHAN RAO ADEN/SW.SC/SCR RAJU SOLANKY AXEN/CON./NWR

HIGH LIGHT OF THE PRESENTATION IMPORTANT DETAILS OF BANAS BRIDGE BRIEF HISTORY OF BRIDGE Derails of the defects observed REASON FOR REPLACEMENT OF BED BLOCK SCOPE OF WORK INVOLVED LIST OF THE TOOLS PLANTS & man power PRELIMINARY ARRANGEMENTS BEFORE EXICUTION OF WORK PLANNING FOR THE REBABILITION REQUIREMENT OF MAN POWER SAFETY MEASURES TAKEN DURING EXECUTION OF WORK ACTIVITIES INVOLVED IN THE WORK CONCULUSION

BRIDGE NO.23 (BANAS RIVER)

IMPOTANT DETAILS OF THE BANAS BRIDGE Name of the River :- BANAS RIVER No.of Spans : :- 30 X 18.29 Section :- Jaipur – Sawaimadhopur Between Station :- Chothkabarwara- Isarda Location km from 33/8 to 34/4 Year of construction:1905 Type of sub structure: Stone Masonry. Type of super structure: Plate Girders.

BRIDGE No.23 ON BANAS RIVER BETWEEN JAIPUR – SWAI –MADHOPUR SECTION

BRIEF HISTORY OF THE BRIDGE Bridge No. 23 (BANAS) is about 100 years old and stone bed block in 14 pieces were laid during construction of the bridge cracks developed in the bed block. This bridge was declared distressed Permanent SR of 50 kmph speed imposed on the bridge.

DETAILS OF THE DEFECTS OBSERVED Initially stone bed block provided in 14 pieces on MG track & Gauge conversion done in 1992-93 without changing the bed blocks. Strengthening of sub structure has been completed during GC & after long life in service vertical & diagonal cracks observed in bed blocks during detailed inspection.

REASON FOR REPLACEMENT OF BED BLOCK Inadequacies of design of existing bed block to carry heavier axle load & higher speed. Speed restriction of 50 kmph had to be removed which was already imposed on the bridge. Replacement of bed blocks was necessary for safety of bridge and increasing the speed up to 110 kmph.

SCOPE OF WORK All deficiencies in sub-structure removed before replacement of bed block. (Jacketing of piers other sub structure works). Casting of new RCC bed block done in advance on each pier with SR of 20 kmph & stop dead if required. Removed old stone bed block in phases under traffic block. Insertion of RCC bed blocks (which were casted on piers/abutments) including bearings.

LIST OF THE MACHINARY, TOOLS & PLANTS Road vehicle for transportation of man & material Surveying equipment such as thodolite, Leveling instrument, tape etc. Air compressor

Contd.. Pneumatic tools, Drilling machine, chiseling machine & breakers Gas cutting equipment Generator Jacks Hydraulic & Mechanical Capacity 30 Tons 8 Nos. ( 4 in working & 4 stand by) & 50 Tons 4 nos. (2 in working & 2 stand by ) Wire rope Ordinary pulley block Manila rope Crow bars. Steel brackets of cantilever type for creating extra working space. wooden planks & blocks for packing .

Cont.---- Other men & material required Labour : staff deputed to do heavy nature of work. Skilled labour has been arrange & deputed at site for safely execution of work in timely. Highly skilled artisan and supervisor staff have been deputed at site. Timely Supply of Gas for cutting, Fuel & other consumables.

PRELIMINARY ARRANGEMENT BEFORE EXECUTION OF WORK Traffic work order (TWO) for Speed restriction 20 kmph & stop dead if required for 60 days & 2 nos traffic block of 1 hour each for 15 days daily sanctioned from Division with consultation of operating Deptt. RCC bed block (in two pieces) already cast on each pier as per approved drawing. (CE/C/JP/221) Arrangement for curing has been done on each pier by providing of pipe line. Arranged highly skilled staff who has already executed such type of works. Procured all necessary tools & plants including all consumables as required for the work. Meticulous planning is paramount importance for completion of any task.

Protection during replacement of bed block

Protection during replacement of bed block

WORK DURING BLOCK LIFTING OF GIRDERS WITH JACKS. DISMANTALING OF CRACKED BED BLOCKS PIECES IN DIFFERENT PHASES. INSERTION OF CASTED BED BLOCKS AND BEARINGS. LOWERING OF GIRDERS. PROVIDING EPOXY FOR THE COLD JOINT FOR ALL SIDES OF NEW PRECASTED BED BLOCKS IN PIECES. BINDING OF REINFORCEMENT WITH NEW RCC BED BLOCK. FOR CASTING BALANCE PORTION TO MAKE COMPOSITE BED BLOCK.

EXISTING STONE BD BLOCK TO BE DISMANTLED

DISMENTLING OF EXISTING STONE BED BLOCK OF STONE AT ENDS.

rCC BED BLOCK CASTED AT BOTH SIDE IN PIERS IN ADVANCE

DISMANTALING OF Intermediate PIECE OF BED BLOCK FOR JACKING PURPOSE.

PROVIDING FOUR JACKS 50 TONS CAPACITY FOR LIFTING OF GIRDER

LIFTING OF GIRDER TO REQUIRED HIGHT BY JACKS FOR REMOVAL OF BED BLOCKS UNDER THE GIRDER.

REMOVING OF BEARING & DISTMENTLING OF EXISTING BED BLOCK STONE TO CREATING OF SPACE FOR FIXING OF CENTER JACK CAPACITY OF 50 TONS

Planning, IN CASE BLOCK NOT permitted due to heavy traffic, WORK HAS BEEN DONE IN MARGINE AFTER PASSING OF TRAIN “MINIMUM TIME” 20”

JACKS RELEASED, LOAD TAKEN ON WOODEN BLOCKS & TRAFFIC PASSED WITH EXITING SR 20 KMPH

AFTER PASSING THE TRAIN ,TAKING THE LOAD ON CENTER JACK FOR RELEASING THE SIDE JACKS

LEVELING OF SPACE BY PROVIDING MORTAR & SLEWING OF PRECASTED RCC BED BLOCK FROM BOTH SIDE WITH OR WITHOUT BLOCK

SLEWING OF PRECAST RCC BLOCK UNDER GIRDER MANUALY

INSERTING OF PER-CAST RCC BED BLOCK BELOW THE GIRDER & FIXING BEARING

LOWERING THE JACK FOR RESTING THE GIRDER ON NEW RCC BED BLOCK

BINDING OF REINFORCEMENT & APPLYING APOXY FOR COLD JOINTS

CONCRETING OF IN SITU BED BLOCK & CURING

THE SAME PROCEDURE HAS BEEN ADOPTED FOR BALANCE PIERS (P-2 TO P-29) AND ABUTMENTS(A-1& A2)

AFTER CASTING LAST BALANCE PORTION BED ON ABUTEMENT A-2 & CURING UP TO 28 DAYS . RELAXED SPEED RESTRICTION (IN STAGES) FOR 45 KMPH, 75 KMPH & NORMAL SECTION SPEED (110 KMPH)

TIME TAKEN IN VARIOUS ACTIVITIES AFTER IMPOSITION SPEED RESTRICTION 20 KMPH & STOP DEAD IF REQUIRED (day = D) TILL COMPLETE JOB Sr.No ACTIVITIES PERIOD DAYS remarks 1 Casting of rcc bed blocks both side on each pier. D1 to d8 8 days   2 Curing of rcc bed blocks D2 to d29 28 days Curing started from d2 3 Replacement of rcc bed blocks from piers p1 to p29 & abutment a1to a2 D29 TO D44 15 days Curing started from d30 to d45 after casting of balance portion of bed block on p1 further simultaneously up to p29 & a1,a2 4 Casting of balance portion of bed blocks D30 to d45 5 Curing of balance portion of bed block D31 to d60 15 days (after casted last portion of bed block) 6 Speed relaxed to normal ( 110 kmph) On d61 60 days Note: - work completed with in 60 days including casting, replacement of bed block & curing rcc bed blocks.

ACTIVIES AFTER BLOCK REMOVING OF TEMPORARY STEEL BRACKETS. REMOVING OF WATER PIPE CONNECTIONS REMOVING OF WOODEN PLANKS & BLOCKS. CHECKING OF TRACK PARAMETER ON THE BRIDGE. 22 No. SPANS PRECAST BED BLOCKS HAS INSERTED WHEN BLOCK WAS NOT PERMITTED BY OPERATING DEPT.

AFTER CASTING LAST BALANCE PORTION BED ON ABUTEMENT A-2 & CURING UP TO 28 DAYS . RELAXED SPEED RESTRICTION (IN STAGES) FOR 45 KMPH, 75 KMPH & NORMAL WORKING OF TRATRAIN (SECTION SPEED 110KMPH).

SAFETY MEASURES TAKEN IN EXECUTION OF WORK CHECKING OF TEMPORARY ARRANGEMENTS CHECKING UP OF ALL TOOLS & PLANTS. PROTECTION OF TRACK PROVISION OF SAFETY BELTS PROVISION OF FIRST AID FACILITY AT SITE PROVISION OF ROAD VEHICLE AT SITE PROVISION OF ADEQUATE COMMUNICATION

CONCLUSION THIS WORK IS VERY SPECILISED NATURE IN TRACK WITH HEAVY TRAFFIC DENSITY PROVIDING BED BLOCKS FOR 30 SPANS UNDER TRAFFIC WITHOUT ANY UNUSAL OCCURANCES. THE WORK HAS BEEN COMPLETETD WELL BEFORE THE TARGATED TIME WITH LEAST TRAFFIC BLOCKS.