11 CPIT 456 by Dr. M. Rizwan Jameel Qureshi Chapter 3 Risk Management.

Slides:



Advertisements
Similar presentations
Chapter 7 Managing Risk.
Advertisements

Managing Risk CHAPTER SEVEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Risk Analysis and Management M Taimoor Khan
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
Risk Management Planning for Problems. Characteristics of Risk Risk has two principle characteristics Uncertainty – It may or may not happen Loss – If.
In the name of God Sharif University of Technology, International Branch, Kish Island Dr. Mohsen Sadighi Moshkenani Chapter 6.
Chapter 7: Managing Risk
Software Process Improvement in Small Organizations A Case Study.
Risk Analysis and Management
Types of Risks 1.Project risks –Impact schedule and cost –Includes budgetary, schedule, personnel, resource, customer, requirement problems 2.Technical.
Software Project Risk Management
CIS 375 Bruce R. Maxim UM-Dearborn
8 Managing Risk Teaching Strategies
Risk Management. What is risk? You have some expected outcome –Of some event in the future Risk is the deviation of the actual future outcome from the.
Chapter 25 Risk Management
Software Project Management Lecture # 8. Outline Chapter 25 – Risk Management  What is Risk Management  Risk Management Strategies  Software Risks.
1 These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 5/e and are provided with permission by.
Chapter 11: Project Risk Management
Risk management in Software Engineering T erm Paper By By Praveenkumar Sammita Praveenkumar Sammita CSC532 CSC532.
Software Project Management Lecture # 8. Outline Earned Value Analysis (Chapter 24) Topics from Chapter 25.
Managing Risk. Objectives  To Describe Risk Management concepts and techniques  To calculate and analyze a project using Probability of completion 
Risk management process
Information System Design IT60105 Lecture 21 Staff Organization, Risk Management and Software Configuration Management.
Managing Risks in Projects. Risk Concepts The Likelihood that some Problematical Event will Occur The Likelihood that some Problematical Event will Occur.
1 Chapter 5 Project management. 2 Project management : Is Organizing, planning and scheduling software projects.
Risk Analysis and Management. Reactive Risk Management Project team reacts to risks when they occur. More commonly, the software team does nothing about.
Risk Analysis & Management
1 Risk Management. Risk concerns future happenings For today and yesterday, we are reaping what we sowed by our past actions/inactions Can we change today.
What is it? A risk is a potential problem — it might happen, it might not. But, regardless of the outcome, it’s a really good idea to identify it. Assess.
Object-Oriented Software Engineering
Robotics & Engineering Design Projective Management Chin-Sung Lin Eleanor Roosevelt High School.
Chapter 22 – Risk Management 1Chapter 22 Project management.
Advanced Project Management Project Risk Management Ghazala Amin.
1 The Concept of Risk A risk is defined as a variable that can take a value that endangers or eliminates success for a project. In plain terms, a risk.
Chapter 17 Risk Management. RISK MANAGEMENT RISK MANAGEMENT FOCUSES ON THE FUTURE RISK MANAGEMENT FOCUSES ON THE FUTURE RISK AND INFORMATION ARE INVERSELY.
Lecture # 17 PRM 702 Project Risk Management Ghazala Amin
Pre-Project Components
Formulating a Simulation Project Proposal Chapter3.
Managing Risk CHAPTER SEVEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Software Engineering B.Tech IT/II Sem-II Term: Unit-7 PPT SLIDES Text Books:1.Software Engineering, A practitioner’s approach Roger s. Pressman.
Software Development Risk Assessment for Clouds National Technical University of Ukraine “Kiev Polytechnic Institute” Heat and energy design faculty Department.
Software Engineering Lecture 6: Risk Analysis & Management.
Project & Risk Management
R ISK A NALYSIS & M ANAGEMENT. Risk – possibility that an undesirable event (called the risk event) could happen – Involve uncertainty and loss – Events.
Information Technology Project Management Managing IT Project Risk.
1 Chapter 3: Project Management Chapter 22 & 23 in Software Engineering Book.
Introduction to Project Management Chapter 9 Managing Project Risk
Dr. Rob Hasker. Avoiding failure  Standish Report, 2014 Standish Report 31% projects cancelled before completion 53% projects ~190% of original estimate.
Risk12a 1 Risk Management Proactive strategies for minimizing the effects of bad things.
Software Project Management Lecture # 9. Outline Chapter 25 – Risk Management  What is Risk Management  Risk Management Strategies  Software Risks.
1 Project Management C53PM Session 4 Russell Taylor Staff Work-base – 1 st Floor
11 CPIT 456 by Dr. M. Rizwan Jameel Qureshi Chapter 2.
R i s k If you don’t attack risks, they will attack you.
Failure Modes and Effects Analysis (FMEA)
Ashima Wadhwa.  Probably the most time-consuming project management activity.  Continuous activity from initial concept through to system delivery.
Project management Chapter 5. Objectives To explain the main tasks undertaken by project managers To introduce software project management and to describe.
8 Managing Risk (Premium).
Software Engineering B.Tech Ii csE Sem-II
Risk Analysis.
Recognization and management of RISK in educational projects
Risk Management SOS ch 6.
Management. Management What is a risk? A risk is simply a probability that some adverse circumstance will actually occur.
Assessing Risk Impact Factors affecting the consequences Nature Scope
SE 3800 Note 10 Project Management
Cyber security Policy development and implementation
Chapter 28 – Modified by Fleck
Chapter 25 Risk Management
Presented To: Sir Ali Raza Presented By: Kainat(06)Riffat(024)Asqsa(034) Group#06.
Risk Management.
Software Risk Management
Presentation transcript:

11 CPIT 456 by Dr. M. Rizwan Jameel Qureshi Chapter 3 Risk Management

2 What is a Risk?

3 Risk Is Anything that can go wrong against the project to fail it.

4 What is Risk Management?

5 Risk Management Risk management is composed of: – estimating all possible risks that can effect a project; – preparing a plan to manage all estimated risks; – monitoring the estimated risks; – implementing the risk avoidance plan to manage them.

6 What are Main Categories of Project Risks?

7 Main Categories There are two main categories of risks. – Predictable or Certain – Non predictable or Uncertain

8 Predictable or Certain Risks Certain risks are sure risks that they will definitely happen such as budget and schedule risks.

9 Non predictable or Uncertain Risks uncertain risks are those that may or may not happen such as any incident in terms of accident or people may leave the project during development including the project director or management may change their policy in terms of stop financing the project. Stop financing of a project means to finish the project.

10 What are Main Types of Project Risks?

11 Main Types of Project Risks Project Technical Business

12 Project Risks Project risks include budget, schedule, people, resources and customer requirements problems. – Project may not exceed the estimated budget and schedule. – People may not leave the project during completion. Resources may not lack short. – Customer Requirements verification and it may not change after observing the working version.

13 Technical Risks Technical risks include the quality, identifying the potential design, implementation, interfaces, verification & maintenance problems, requirements ambiguity and obsolete technology. – Identifying the potential design means selection of best solution may not be wrong. – SW may not be implement-able after completion. – SW verification problems could be approval of main functionalities and understanding of vague customer requirements. – The technology in terms of HW and SW selected to implement and develop the project may not become obsolete.

14 Business Risks Business risks cover the market trend, scope of SW and management support. – The SW project will meet the customer requirements and market trend at the completion or not. – Will the scope of the SW meet the organizational mission statements or not? – The SW may not lose the support of the top management.

15 Main Strategies to Manage Risks There are two main strategies to handle or manage the risks. – Reactive – Proactive

16 Reactive Strategy Reactive strategy is used when you take some action when some incident or accident happens such as budget, schedule and people risks. Budget and schedule risks are raised when initial actions are not being taken when indications start appearing that project is going out of tolerance level in terms of estimated budget and schedule. – The extra budget and schedule is needed to complete the project. – People risk is raised when some members of the project staff suddenly left the project because they got better offer from any of your competitor and you have no backup to fill their positions. It is also called fire-fighting mode.

17 Proactive Strategy Proactive strategy is the planned strategy to handle the risks. We estimate all possible risks and develop a plan to handle and reduce them and try to reduce the loss if it not possible to avoid the all risks 100%. Proactive strategy is also called intelligent strategy.

18 Assessment Method to Measure Risks Risk Exposure method is used to measure or assess the risks for any software project. The analyst measure the average probability of risk occurrence based on the cost, schedule and support. The constant value for the risks is between 0.7 and 1.0. Risk exposure is calculated by multiplying the probability (P) of risk occurrence and cost impact (C). – Risk Exposure = P * C

19 Example Calculate the risk exposure for a project if 70 % of the SW components will be reused from the 60 selected components. The average code for each new component is 100 LOC at the cost of $ 14/LOC. The risk probability is 80%.

20 solution Risk Exposure = P * C Probability = 80 % SW components reused = 70 % Total components needed to develop = 60 SW components reused = 0.7 * 60 = 42 New SW components needed = 60 – 42 = 18 SW cost needs to develop each new component = $ 14 / LOC Total cost needed to develop 18 components having 100 lines of code = 18 * 14 * 100 = $ Risk Exposure = 0.8 * = $ 20200

Calculate the Risk Exposure Calculate the risk exposure for a project if 70 % of the SW components will be reused from the 60 selected components. The average code for each new component is 100 LOC at the cost of $15/LOC. The risk probability is 50%. 21

Solution Risk Exposure = P * C Probability = 50 % SW components reused = 70 % Total components needed to develop = 60 SW components reused = 0.7 * 60 = 42 New SW components needed = 60 – 42 = 18 SW cost needs to develop each new component = $15 / LOC Total cost needed to develop 18 components having 100 lines of code = 18 * 15 * 100 = $ Risk Exposure = 0.5 * = $