Details on the Accelerator Installation Plan E. Sargsyan & L. Lari www.europeanspallationsource.se 20 April 2016.

Slides:



Advertisements
Similar presentations
Requirements Structure and Status for NCFE
Advertisements

Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Construction and Installation of the CLIC Experimental Area
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Global Design Effort - CFS LCWS CONVENTIONAL FACILITIES AND SITING GROUP Parallel Session Overview A. Enomoto, V. Kuchler, J. Osborne.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Anders Sunesson RF Group ESS Accelerator Division
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
Comparison of Fermilab Proton Driver to Suggested Energy Amplifier Linac Bob Webber April 13, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
MEF - Machines & Experimental Facilities March 2013 Project meeting Activities in Linac4 tunnel and building in 2013 March 2013 Project meeting 14/03/2013J.Coupard1.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
ESS Vacuum Systems TAC 6 November 2012 Peter Ladd Senior Vacuum Expert.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Installation plans for RFQ and Superconducting linac Dave McGinnis Chief Engineer Eugene Tanke Systems Engineer March 20,
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
ESS Cooling System - Interface with DTL 1 John Jurns Cooling System Engineer.
WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Steps towards beam commissioning: RF system group Paolo Craievich :: RF Section :: Paul Scherrer Institut SwissFEL.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Accelerator Systems Integration Stephen Molloy Section Leader for Accelerator Integration April, 2016.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Accelerator Installation Plan: Graphical representation E. Sargsyan & L. Lari DRAFT - March March 2016.
Chapter Editor: John Weisend TDR Chapter 6 Cryogenic System, Vacuum System & Test Stands.
Integration of HWR, SSR1, and Cryo in the PXIE enclosure Curt Baffes PIP-II Collaboration Meeting 09 November 2015.
Introduction to the Accelerator layout February 2016 Nick Gazis Mechanical Integration Lead Engineer.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Status of Primavera (P6) Accelerator Plan & an Introduction to the Accelerator Installation Plan Luisella Lari Head planner for Accelerator & Senior Scientist.
RF cell Anders Sunesson RF group leader
Cryomodule test stand at ESS site
Preparation for DESY Meeting
Updated with comments 22 may 2017 Updated again 29 June 2017
Update on HW commissioning
Hollow e- lens, Cryogenic aspects
XFEL Vacuum System Commissioning
Cryogenic C&C Scope of work
Proton Source and LEBT Luigi Celona & Lorenzo Neri
WP Coordinaten XFEL RF Operation
RF Distribution for Warm Linac
Beam Commissioning at ESS
RF systems introduction
Ciprian Plostinar Workshop on Testing and Commissioning
Infrastructure Project and Component Installation Accelerator Project
Introduction CDR Normal Conducting Linac LLRF
Testing Coordination at ESS
European Spallation Source ERIC
WP16 Water cooling systems
High Level Readiness Reviews
Lessons from the 1st Safety Readiness Review
Accelerator NCFE Liaison Officer
Status of the ESS High Power RF Systems
Plan for early Operation
RF introduction Anders Sunesson RF group leader
Status & Schedule for ESS TS2
Charge and Agenda of the 18th TAC meeting
Acc Collaboration board Trieste
Accelerator Installation Schedule
Overview of the TARGET Monolith Rough Vacuum
Polarized 3He target installation
General Overview of WP 12 ESS Vacuum System
Project Support Meeting January 9, 2019
Presentation transcript:

Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016

Introduction High Level Milestone – Beam on Target in June 2019 Partial and full access dates from CF Project 11 in P6 for deliverables from different IKC/WPs Time-area-activity relations – Understand better the sequence of main activities – Highlight parallel activities and cohabitation issues – Define required teams/resources – Overview and consistency check Logistics considerations needed Only one shift is considered so far 2

Gallery to Tunnel Mapping 3

Visualization (tunnel example) 4 ACCELERATOR SECTIONS ACCELERATOR SECTIONS ACCELERATOR COMPONENT S ACCELERATOR COMPONENT S TIME Activity A Activity B Activity A AREA Duration or time window Activity B Parallel activity of the same type – two or more teams Sequential activity of the same type – one team in cascade

Stubs installation 5 Two stubs in parallel Cable ducts 2 teams (4 persons) Total 1 week RF distribution 2 teams (4 persons) Total 2 weeks Cables pulling 2 teams (12 persons) Total 3 weeks Water cooling 1 team (2-3 persons) Total 2 weeks From teams are needed for CNPW

Tunnel installation – main stages 6 General Services Installation Cryo-Distribution System Installation & Tests Cryo-Modules & LWUs Installation NCFE Installation & Commissioning

Tunnel installation – general services 7 Drilling for supports 4 persons in parallel Total 6 weeks Floor markings 2 persons Work in cascade Total 4 weeks Water cooling install. 1 team (6 persons) Work in cascade Cable trays install. 2 teams (4 persons) Work in cascade Full access to Tunnel & FEB90 2 May 2017 Phase reference line installation 1 team (2 persons) Work in cascade Hardware commissioning in FEB90 Total 5 weeks Racks installation 2 teams (4 persons) Work in parallel Total 2 weeks Cable termination & test 4 persons in parallel Total 3 weeks Filling of racks WP technicians Total 9 weeks Cables pulling 1 team (6 persons) Total 3 weeks

Tunnel installation - NCFE 8 Shielding wall is installed in place of the DTL-5 to allow parallel work in SC Linac section ISRC & LEBT – Installation/assembly in the tunnel 2 weeks – Beam commissioning 13 weeks – LEBT dismantling 1 m upstream the RFQ (for bead-pull); need to re-assemble before the RFQ beam commissioning! RFQ – Assembly & tuning 2 weeks – RF conditioning 15 weeks MEBT – Installation/assembly in tunnel 4 weeks during the RFQ conditioning window – need to interrupt the RFQ conditioning – Pre-assemble MEBT sections to minimize time spent in tunnel! ISRC to MEBT beam commissioning 12 weeks DTL – Tanks 3&4 installation 2 weeks in parallel to LEBT partial dismantling – Tanks 3&4 RF conditioning 2 weeks in parallel with the RFQ conditioning – Tank 1 installation 2 weeks – Tank 1 RF conditioning 2 weeks ISRC to DTL-1 beam commissioning 5 weeks DTL – Tank 2 installation 2 weeks – Tank 2 RF conditioning 2 weeks ISRC to DTL-4 beam commissioning 5 weeks Shielding wall dismantling 1-2 weeks DTL – Tank 5 installation 2 weeks – Tank 5 RF conditioning 2 weeks The rest of the accelerator is already installed and cooled down Cold hardware commissioning ISRC to Dump beam commissioning Beam to target

Tunnel installation – CDS 9 Window of 6 months for CDS installation & testing for both spoke and elliptical sections CDS cooldown & commissioning (including warmup at the end) Total 4 weeks CDS install. & process pipe leak test 1 team for SPK (IKC) in cascade 1 team for MBL+HBL (IKC) in cascade Number of people TBD CDS pressure test (no access to tunnel) Total 1 week CDS final leak test & connection to Cryoplant 1 team for SPK (IKC) 1 team for MBL+HBL (IKC) Number of people TBD Total 1 week CDS final interconnections 1 team for SPK (IKC) in cascade 1 team for MBL+HBL (IKC) in cascade Number of people TBD

Tunnel installation – CM & LWUs 10 LWU installation 2 teams (6 persons) in parallel 2 week/LWU CM cooling & cable connections Cooling 1 team (1-2 persons) in cascade Cables 1 team (1-2 persons) in cascade 1 week/CM RF waveguide connections 1 team (2-3 persons) in cascade 1 week/CM CDS connections 1 team (persons TBD) in cascade 1 week/CM Cryomodule installation 1 team (3-4 persons) in cascade 1 week/CM LWU installation 3 teams (9 persons) in parallel 2 week/LWU CDS & CM cooldown Total 2 weeks Beam commissioning 6 weeks ISRC to DUMP 1 week ISRC to TARGET

Gallery installation - preview 11 Constrained by: Partial access dates Beam commissioning (June 2019 MS) Several parallel activities: General services (cabling, cooling) Installation & testing of RF equipment

Gallery installation – RF Cell example 12 Electrical - 2 RF cells/stubs in parallel – Cable trays, 2 teams (4 persons/1 week) Electrical – 2 rack rows in parallel – Cable terminations (4 persons/3 weeks) Electrical - 2 RF cells/stubs in parallel – Rack install. 2 teams (4 persons/2-3 weeks) Electrical - 2 RF cells/stubs in parallel – Cable trays install., 2 teams (4 persons/1 week) RFDS waveguides on walls –2 RF cells in parallel – 2 teams (4 persons/1 week) Electrical - 2 RF cells/stubs in parallel – Cable pulling 2 teams (12 persons/3 weeks) RFDS supports - 1 cell in cascade – 1 team (3 persons/2 weeks) Water cooling for RF – 1 cell in cascade – 1 team (6 persons/1 week) RFDS WG, circulators & loads – 1 cell in cascade – 1 team (3 persons/2weeks) Electrical - 1 RF cell in cascade – Cable trays to RF, 2 teams (4 persons/1 week) Klystrons – 2 RF cells in parallel (some exceptions) – 2 teams (4 persons, 1 week/klystron) Modulators – 2 RF cells in parallel (some exceptions) – 2 teams (4 persons, 1 week/modulator) Hardware commissioning of 6-8 weeks per RF cell at different stages

Summary High Level Milestone – Beam on Target in June 2019 – Constrain driving the developed strategy – Resource loaded plan requiring parallel activities and area consideration (cohabitation) Further details on sequences, durations & personnel – Installation procedures – Hardware commissioning/test procedures – Safety procedures – Benchmarking & tests (e.g. experience from other facilities, Integration Test Stand, stub mockup) Synchronization & coordination – Installation – Tests – Commissioning 13

Acknowledgements Thanks to all AD colleagues for discussions and inputs, in particular to E. Tanke for the first version of the installation sequence! 14