PXIE Ion Source and LEBT Installation Status L. Prost, B. Hanna, R. Andrews Project X Technical Meeting October 29 th, 2013.

Slides:



Advertisements
Similar presentations
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
Advertisements

9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
HYBRIS: R. Keller Page 1 A Hybrid Ion Source Concept for a Proton Driver Front-End R. Keller, P. Luft, M. Regis, J. Wallig M. Monroy, A. Ratti, and.
FETS Ion Source Installation progress UKNF Meeting Trinity College, September Dan Faircloth, Scott Lawrie, Alan Letchford, Christoph Gabor,
LINAC4 STATUS Alessandra M. Lombardi for the LINAC4 team 1.Motivation and goals 2.Status of Linac4 2 years after official start of the project ( )
Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
Compressor status AWAKE Technical Board meeting 19 August 2015.
J. Alessi Implementation Plan EBIS Project Technical Review 1/28/05 Implementation Plan WBS exists Working on a “bottoms up” cost estimate The following.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Overview of Electron Cooling Activities at FNAL Thomas Kroc Fermilab – Electron Cooling EIC 2004 March 15-17, 2004 Jefferson Lab.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Project X Injector Experiment (PXIE) Sergei Nagaitsev Dec 19, 2011.
Ion Sources – Hardware and Operation MACS Week Friday 8th October 2010 PP a-LPE, 8 th October 2010, MACS Week 2 Liviu Penescu, „Ion Sources.
ECOOL Meeting 03/26/10 1 Low-E cooler baseline decisions: 1.FNAL’s cooling section “as is” – with weak solenoids, correctors, etc. (to prevent over focusing.
Status and schedule for the H - source upgrade at HINS beam line HINS Meson meeting January 5 th, 2012 L. Prost (most inputs from Steve Hays & Alex Chen)
22AUG07 Gun System Update1 Rich Andrews. 22AUG07 Gun System Update2 Gun System Coaxial coupler Gun Cavity Solenoid Magnet Compensator Magnet.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Yousef I. Makdisi DIS03 St. Petersburg April 24,2003 Polarized Jet target status The overall view The Dissociator stage The Atomic Beam stage The RF transitions.
ASTA Accelerator Directorate Review Project Plan and ES&H Carsten Hast May 20, 2014.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
PHIN Fabrication of a photo-injector for the CTF3 accelerator and for the NEPAL test stand WP 4 of the JRA2 PHIN 1.Status of the construction of RF guns.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Developments of the FETS Ion Source Scott Lawrie.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
LINAC3 UPGRADE Source and LEBT modifications for YETS and recommissioning timetable 28/10/2015 Ville Toivanen.
PXIE Beam Instrumentation Status Update – Preparing for MEBT 1.1 Beam Vic Scarpine Feb. 9, 2016.
PXIE LEBT Status Update Lionel Prost PIP-II “Friday” Meeting January 16 th, 2015.
PIP-II R&D Program PXIE Ion source and LEBT Lionel Prost PIP-II Machine Advisory Committee Meeting March 2016.
PXIE Layout and Infrastructure Building, Cryogenics, Utilities… Rich Stanek On behalf of the CMTF Team PXIE Collaboration Meeting November 28, 2012.
H - ion source at the pre-acc R&D lab Update HINS Meson meeting January 20 th, 2011 L. Prost, C. Schmidt, D. Bollinger, R. Tomlin.
PXIE absorber test bench A. Shemyakin, C. Baffes, K. Carlson, B. Hanna, L. Prost, J. Walton November 6, 2012 Project X meeting Test bench description Difficulties:
PXIE warm front end status A. Shemyakin PIP-II technical meeting 3 May 2016.
Linac4 BCC 14/10/2010 Linac4 Measurement and Dump Lines BCC on the Linac4 Transfer Line Status.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
Warm Front End Concept A. Shemyakin PIP-II Machine Advisory Committee 9-11 March 2015.
PIP-II Beam Instrumentation Vic Scarpine PIP-II Machine Advisory Committee Meeting March 2016.
D. Li, Project X Collaboration Meeting, Fermilab (October 25-27, 2011) Overview of Project X Frond-End R&D at LBNL Derun Li Project X Collaboration Meeting.
Mini MAC II PEP-II hardware M. Sullivan Apr 23-24, 2009Page 1 PEP-II Hardware Status M. Sullivan SLAC National Accelerator Laboratory Mini-MAC II Frascati,
PXIE Ion Source & LEBT Commissioning Update Lionel Prost on behalf of A. Shemyakin, R. Andrews, B. Brooker, K. Carlson, J. Czajkowski, R. D’Arcy, B. Hanna,
Status of Mechanical Design of LEBT Rich Andrews, Matt Alvarez, Tim Hamerla, Danny Snee.
Ion Source and LEBT Statuses L. Prost (with many contributions from others) Project X Technical Meeting July 3, 2012.
Report Technical Director Storage-Ring-Installation Completed
ELENA installation and commissioning status
XFEL Vacuum System Commissioning
Proton Source and LEBT Luigi Celona & Lorenzo Neri
Injector Performance Requirements Conventional Facilities Update
Advanced Research Electron Accelerator Laboratory
Ion Source and LEBT control system topology, Interlock strategy
ISRC and LEBT Vacuum System Design
Ion Source and LEBT Beam Diagnostics
(Beam) Commissioning Plan
Safety Readiness Review (SRR) Thomas Hansson, ESH
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Presentation transcript:

PXIE Ion Source and LEBT Installation Status L. Prost, B. Hanna, R. Andrews Project X Technical Meeting October 29 th, 2013

Ion Source Installation 2

Page 3 Layout (reminder) Note: In light green, distances dictated by optics solution(s); have been set for ~ 2 years.

3D model (partial) 4 Emittance scanners (only one at first but can be used for both directions) Gate valve DCCT Turbo pumps Chopper

First set-up 5 Faraday Cup (protective ‘cover’ not shown) Emittance scanner drive assembly (probably not ready for first beam) IS body Turbo pump

Ion Source Assembly at CMTF Page 6 Ion Source moved to the cave (10/15) and aligned with respect to the reference beam line –Includes Faraday cup –Vacuum: ~1  Torr Faraday cup (inside) Isolated cable tray (from HV cabinet to IS) IS vacuum chamber IS body Water distribution system

IS Electrical Page 7 Two cabinets (HV and LV) in the cave: –One ‘floating’ at HV (-30 kV) and connected to the source body Racks complete –Safety document written and reviewed by AD EE Support for HV cabinet One more walkthrough needed for ‘unattended‘ operation approval Does not include the source itself at this time –Isolation transformers test may be done this week Check that they don’t overheat while in the cabinet –They were tested upon delivery but not in an enclosed volume Isolation transformers Bias PS LV rack HV rack (at elevated potential, -30 kV)

Infrastructure Page 8 Electrical distribution system almost complete –Most cable pulls finished yesterday Includes fibers optics for controls –Various ‘small’ jobs remain E.g.: cable terminations Water system almost complete –Hoses to be hooked up to the source this week Source body, back-plate, filament, extraction and control electrodes, and Faraday cup –Instrumentation (flow meters, pressure gauges…) are being wired (today) Hydrogen distribution system installation in progress –Scheme/routing agreed upon with Safety –Will need formal review from the Hydrogen Safety Committee

Controls Page 9 PLC for H 2 flow control valve installed (has been for a while) –Programming remains to be done Same clock system as for NML –All hardware in place Fiber optics ran into the enclosure yesterday –For control of PSs in the IS HV rack Controls rack Enclosure for H 2 bottle Mass flow controller

Instrumentation Page 10 Emittance scanner –Parts for emittance scanner ordered (SNS) –Assembly and testing at Oak Ridge before being shipped to Fermilab January ’14? –Stand alone control system But data output accessible through ACNET Hardware being procured Coding in progress Faraday cup (designed and built in-house) –Attached to IS vacuum chamber with protective cover (personnel safety) –Thermo-couples and signal output cable remain to be installed

Safety documentation Page 11 LOTO procedure for IS electrical cabinets has been written –Reviewed (and approved) by Dan Wolf Draft (advanced) of the H 2 safety document –Will need to be updated after final installation of the H 2 distribution system –Will be the main document for Hydrogen Safety Committee review Draft write-up for rad and electrical safety has been sent to Safety dpt. –Safety officers have been assigned to review and guide us on what else needs to be done or corrected What has been submitted should be relatively close to a final version John Anderson requested that we go through a formal ORC –i.e. Need Roger’s approval before firing up !

Timeline Page 12 Installation complete: First week of November Safety review(s): Second week of November Commissioning starts: Third week of November First measurable beam: First week of December (?)

LEBT 13

Solenoids Page 14 First solenoid delivered ~2 weeks ago QC in progress –Several magnetic field measurements have been completed (but not all… yet) Dipole correctors have a relatively big ‘roll’ (~6°) Not specified to vendor but will have to be corrected for the other 3 solenoids –Magnetic center line has been referenced Have all the parts (and PSs) to build controls rack… –… but no manpower (EE Support)

Magnetic field linearity (with respect to current) Page 15 Longitudinal field strength measurement at the center of the solenoid as a function of the solenoid current Ratio of the longitudinal magnetic field to the solenoid current as a function of the beam current, normalized to the average value of this ratio Longitudinal magnetic field vs solenoid current relationship linear to within <1% from 50 A to 300 A Nominal range of operation

First prototype has been fabricated –Can be installed on the solenoid when appropriate There may be a possibility of testing it with beam without the solenoid Isolated diaphragm Page 16 Cooling channel Diaphragm (electrically isolated) Cooling channel Flange (welded after installation inside solenoid bore)

Chopper (and Toroid) Page 17 Mechanical design –Remains conceptual at this point –Beam line geometry needs to take into account the space needed for the toroid ‘De-scoped’ (e.g.: Project X-Document #1219) –Slower pulsing frequency (nominal 60 Hz)  Re-use ecool modulator –Work on driver started this month (G. Saewert) Sol. #2 Sol. #3 Isolated diaphragm assembly Chopper assemblyToroid Isolated diaphragm assembly

LEBT installation outlook Page 18 First solenoid installed in January –Emittance scanner mid-January ? Last 3 solenoids delivered in February Chopper prototype complete in April

Setup with one solenoid (I) Page 19 Diagnostics box (former IS vacuum chamber) Emittance scanner Biased aperture (maybe) DCCT Faraday cup Ion Source

Setup with one solenoid (II) Page 20 Diagnostics box (former IS vacuum chamber) Emittance scanner Faraday cup Ion Source

Summary Page 21 Installation of the IS infrastructure and IS assembly proper has progressed very well over the past couple of months –It is realistic to expect beam (10 mA?) before Christmas ! While all components of the LEBT have not been designed in detail, there has been good discussions on various concepts and we are converging –Expects preliminary drawings of the entire beam line with all components before the end of CY’13

Additional/backup slides 22

Nominal beam envelope Page 23 Beam envelope (calculated with VACO) – Gaussian distribution, 10 mA Z [m] Beam size, 2.5  [cm] X in red, y in blue Beam size, ±2.5  [cm] Outermost particle Normalized, rms emittance [mm mrad] Emittance growth Neutralization factor Kicker electrodes Aperture restriction (e.g.: ‘collimator’, ceramic break…) An important constraint for the beam envelope is the capabilities of the chopper. On the other hand, the larger the beam size near the chopper, the least emittance growth. < 0.25 mm mrad