Mike Andrews May 10, 2013. Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.

Slides:



Advertisements
Similar presentations
Target chase, decay and absorber cooling for LBNE A. Marchionni, Fermilab 8th International Workshop on Neutrino Beams & Instrumentation CERN, November.
Advertisements

Neutrinos from Stored Muons STORM Target Station Conceptual Design 15-April-2013 Kris Anderson Fermilab/Accelerator Division/Mechanical Support Department.
9/17/07 ILC Detectors 1 Conventional Utilities Tom Lackowski.
NuMI Target Pile Fan Repair Michael Andrews 3/15/10.
NuMI Radiation and Environmental Protection NBI th International workshop on Neutrino Beams and Instrumentation September 5-9, 2006 Mike Martens.
ANU Cooling Systems Karl Williams Fermilab Accelerator Division CD-2/3a DOE Review of NO A October 23-25, 2007.
NOvA Near Water and Dryer System Design and Status
Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
NUMI NuMI Hot Handling Jim Hylen (FNAL) NBI02 March 13, 2002 Page 1 NuMI Target Hall Radioactive Component Handling NuMI Target Hall Utilizes Three Basic.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
We are Here! Gluex Collaboration Meeting May Engineering Status - Presented by Tim Whitlatch1.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
Preparation for May-2013 Review of UCN Beamline March 27, Date: May 2-3, 2013 Review Committee finalized Scope – Overall concept, focusing on 2014.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
31, May 2007 ILC DESY 07 1 Surface Building Design Development Tom Lackowski GDE.
CFD team supports CERN development 19 May M.Battistin CERN May 19 th 2011 C omputational F luid D ynamics team C omputational F luid D ynamics team.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
NuMI Run II meeting Nov. 4, 2004 NuMI Target Hall Jim Hylen Page 1 NuMI Target Hall Status / Plan 8 slide introduction to target hall 9 slide list of status.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
NuMI NBI2006 September 9, 2006 NuMI Repairs for Hot Components Jim Hylen / FNAL Page 1 NuMI Repairs for Hot Components (1 sievert = 100 rem) Problem On.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
NUMI NuMI Internal Review July 12, 2001 Infrastructure: Radiation Safety Page 1 Technical Components NuMI Beamline Radiation Safety Issues Radiation Safety.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
NuMI NuMI Target Hall Air System Review Introduction July 30, 2003 Jim Hylen / FNAL Page 1 NuMI Target Hall Air System Review Introduction Air system for.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
F NuMI Beamline Accelerator Advisory Committee Presentation May 10, 2006 Mike Martens Fermilab Beams Division.
J T Volk Fermilab April 2008 Ground Motion Studies at Fermi National Accelerator Laboratory James T Volk Applications Physicist II Vladimir Shiltsev, Shavkat.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
All Exp Mtg July 7, 2008 NuMI-MINOS Status Report – Laura Loiacono FAR DETECTOR: FD live time was 95.7% for cosmics last week (ROP7 problems reported at.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
Global Design Effort Working Group C Conventional Facilities Parallel Session IRENG07 V. Kuchler, A. Enomoto, J. Osborne September 19, 2007.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
Booster L12/Noker-L13/Absorber Update PIP Update Talk August 15, 2012 Salah Chaurize.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
Iouri Ivaniouchenkov RAL Specifying the needs for MICE July 8, RAL MICE Collaboration Meeting 1.
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
Mike Andrews August 30, Weeks 1-5 Activities Rad survey open to supervised access & re-core Install crane electronics & remove shield wall Retrieve.
This talk is not a summary of costs for conventional facilities This talk is Review of conventional facilities used by CDF Discussion of status of systems.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
LBNE Reconfiguration Engineering/Cost Working Group Report Jim Strait Fermilab LBNE Project Manager Deputy Chair, Cost and Engineering Working Group Fermilab.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
Mike Andrews August 17, Week 16 NuMI Activities Leak testing of DI bottles & Casks Complete all bottles & casks RAW Impulse line upgrade Finished.
1 CFS Utilities – What’s included in RDR for IR July CFS Utilities – IRENG WG C WATER COOLING: none. Unknown loads on IR. Only have water plants.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
S A Griffiths CM42 June 2015 Electrical & Control.
ILC Utility Design Study for Kitakami-site
CBETA Technical Review
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Francois and Lau EATM 17 July 2012
1.3-GHz Cavity Vacuum Furnace at IB4
Experimental hall design in Japanese site
Part II: Integrated Design of Infrastructures
News and brief overview of Beamline plans for the next few months
NuMI - Shutdown – Week 9 Horn 2 Repair – Successfully Tested the Repaired RAW Leak Drained and Refilled Horn 1 and 2 RAW Systems Changed Horn 2 DI Bottle.
Detector Hall Tom Lackowski ILD Workshop 2011 LAL, Paris
Undulator System Installation
Presentation transcript:

Mike Andrews May 10, 2013

Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange skid system Complete Target elevation survey Target in chase with shielding platform in place (Monday) Move shielding platform sections to surface storage Connect & QA all water/gas/instrumentation lines Install spool pieces in beamline & place under vacuum Connect water to MI quad magnets & install Q117 cooling plates Clean Support Rooms, Pre Target, Target Hall drain system, drip ceilings, floors, & magnets Install electrical support for LBNE Muon Monitor prototype infrastructure in Absorber Passageway Install electrical support for AH air compressor adjacent to shaft Hook up & test the Multiwires in the Pre Target

NuMI Target RAW Lines

NuMI Beamline

Next Weeks Activities Controls & instrumentation testing MI65 exchange skid system controls Commission Target RAW system Install data racks for Muon Monitor in Alcove 4 Install electrical support for PPD Muon Monitor prototype infrastructure in Alcove 4 Clean NuMI Decay Pipe & Absorber Hall drainage system Complete PM’s on Target Hall & chase dehumidification system Order two new pumps for Target RAW skid & new pressure transmitter for Horn 2 spray lines Install new chase humidity & temperature sensor

NoVA Detector Hall Project Kiewit Construction site activities Status of work 97% of the Project is complete Completed water mist fire protection system testing Demobilization of the yard & office areas Fabrication of Detector Hall rails & work deck Continue with installation of block wall at Hall entrances Estimated end date week of May 27

NoVA Hall Construction

NoVA Far Detector Ash River, MN