Long-Baseline Neutrino Facility LBNF Far Site Conventional Facilities (FSCF) Scope and Interface Overview Tracy Lundin as borrowed from Headley & Willhite.

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
Advertisements

Comments about Extrapolation to LBN(E) Barry Norris September 25, 2014 Barry Norris, Cryogenic Meeting at CERN September 2014.
SNOLAB Facility Status Fraser Duncan SNOLAB Workshop 27 August 2009.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Towards a Future Long-Baseline Neutrino Experiment Bob Wilson Colorado State University CERN Prototype/Beam Test Meeting CERN, 20 October 2014.
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
LBNE Reconfiguration Workshop – April 2012 FD Assumptions and Cost Estimate 1 Bruce Baller.
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP Status and Overview.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
Status of SNOLAB Development Fraser Duncan SNOLAB Workshop 4 Oct 2008.
Long-Baseline Neutrino Facility LBNF Summary of FSCF Final Design Parameters Meeting at SURF, 10 Aug 2015 Elaine McCluskey, LBNF Project Manager EFIG 19.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Fraser Duncan Queen’s University Synergies in Low Background Techniques 26 July 2005 Underground Facilities at SNOLAB.
LINEAR COLLIDER COLLABORATION Designing the world’s next great particle accelerator Detector Hall Configuration Overview New baseline (Hybrid A’) proposed.
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015.
LBNF status. Process to chose 2 SPs Candidates who accepted (vote starts the 27 th ) : Milind Diwan Chang Kee Jung Sanjib Mishra Andre Rubbia Jim Strait.
Cost and Engineering Working Group Introduction Jim Strait Fermilab LBNE Project Manager Deputy Chair, Cost and Engineering Working Group LBNE Reconfiguration.
The 2009 Sr Design Project (for Coal). What is Covered Mine Plan and Layout –Methods –Equipment –Manning –Production Rate –Sequence Rock Mechanics –Orientation.
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
Long-Baseline Neutrino Facility LBNF Integration - Interfaces, Config Mgmt and Requirements Jeffrey Dolph LBNF/DUNE DOE/SC CD-1 Refresh Review July 14-16,
Progress on Remote Handling Systems TAC 12 Magnus Göhran – WPM 15 th October 2015.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
LAr1 Plans at FNAL Bruce Baller - Fermilab. Outline LAGUNA Meeting - Mar  LBNE LAr detector overview  Prototyping plan  1 kton prototype.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
March 22, –  Design Concept & Hall Layout  Access Tunnel  Top heading Tunnel  Displacement of detector hall by push-pull operation.
Long-Baseline Neutrino Facility LBNF Cryostats Systems Requirements on FSCF Marzio Nessi LBNF/DUNE DOE/SC CD-3a Director’s Review October 27-29, 2015.
Conventional Facilities for the Far Detector Options Assumptions and Cost Estimates T. Lundin April 25, 2012 LBNE Reconfiguration Workshop - 25, 26 - April-2012.
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Project 29 September 2015.
News from LBNF C. J. Mossey, LBNF Project Director DUNE Collaboration Meeting - South Dakota School of Mines and Technology 19 May 2016.
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Status N. S. Lockyer
Long-Baseline Neutrino Facility LBNF Far Site CF Scope Joshua Willhite Logistics Workshops August 11-13, 2015.
Long-Baseline Neutrino Facility LBNF Update: LBNF EVMS Implementation for CD-3a Elaine McCluskey, LBNF Project Manager Bob O’Sullivan, Project Controls.
Long-Baseline Neutrino Facility LBNF LBNF Project C. J. Mossey, LBNF Project Director 49 th Annual Fermilab Users Meeting 16 June 2016.
The DUNE 35ton Prototype at Fermilab. DUNE FD ND 1300 km We have learned much about neutrinos in the last 70 years, but there is still much we don’t understand.
LBNE Reconfiguration Engineering/Cost Working Group Report Jim Strait Fermilab LBNE Project Manager Deputy Chair, Cost and Engineering Working Group Fermilab.
Long-Baseline Neutrino Facility LBNF LBNC: Far Site Update and Planning Mike Headley LBNF Far Site Facilities Project Manager January 11, 2016.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Long-Baseline Neutrino Facility LBNF Update on LBNF to Long-Baseline Neutrino Committee Elaine McCluskey, LBNF Project Manager 13 June 2016.
DUNE-UK Mark Thomson University of Cambridge DUNE-UK Meeting, UCL May 15, 2015.
Challenges to get LBNF ready for Far Detector installation ASAP Elaine McCluskey ELBNF Proto-Collaboration Meeting 22 Jan 2015.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
LBNF 1 LBNF/DUNE – Construction Summary. LBNF Far Site Facilities Scope and Requirements LNG Membrane cryostat is an European technology. CERN has now.
Long-Baseline Neutrino Facility LBNF Far Site CF Scope Joshua Willhite Interface and Logistics Workshops August 10-12, 2015.
Siting/Conventional Facilities Jonathan Hunt PIP-II Machine Advisory Committee 9 March 2015.
1 DOE Independent Project Review Critical Decision-3a Long-Baseline Neutrino Facility/ Deep Underground Neutrino Experiment (LBNF/DUNE) Project DOE Executive.
IEFIG update Joe Lykken | iEFIG Chair ELBNF IB phone meeting | 6 March 2015.
Long-Baseline Neutrino Facility LBNF Elaine McCluskey, LBNF Project Manager Fermilab PAC Meeting 23 June 2015.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Experimental Hall in Mountain Regions
LBNF/DUNE Update Public Meeting Sanford Lab Update
Overview of the Long-Baseline Neutrino Facility Cryogenic System
Detector Hall Design and Cost Information CONVENTIONAL FACILITIES
IT-4189 Supply and installation of a cryogenic distribution system
Risk Identification HL-LHC Detector Upgrades Project
October 2004 Through September 2005
News and brief overview of Beamline plans for the next few months
LBNF Excavation Alternatives
Warm structure requirements :
Meeting of the LCLS Facilities Advisory Committee
Scope, Requirements Deliverables & Schedule
Far Experimental Hall - Hutches
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Long-Baseline Neutrino Facility LBNF Far Site Conventional Facilities (FSCF) Scope and Interface Overview Tracy Lundin as borrowed from Headley & Willhite LBNF/DUNE Far Site CD-3A Risk Management Workshop Planning Meeting August 26, 2015

LBNF Outline Lundin | LBNF Far Site Conventional Facilities and Interfaces2 FSCF Scope Other FSCF Scope – Early Work Interfaces with CF Organization and Staffing Schedule Summary Planning for LBNF Construction

LBNF FSCF Scope Introduction Lundin | LBNF Far Site Conventional Facilities and Interfaces3 Overall CF scope: Design, procurement, construction, and installation of conventional facility improvements. Interfaces with cryogenic systems, and cryostats to support the DUNE Far Detector at the Far Site. Major scope elements for the Far Site Overall: CF Scope Interfaces with CF Scope ElementFunding Source Excavation of 4850L detector and utility caverns and drifts DOE Surface buildings, utility infrastructure, and cavern outfitting DOE LN2 cryogenic systemsDOE Four 10kt fiducial cryostatsNon-DOE LAr cryogenic systemsNon-DOE LAr and LN2 cryogenic fluids procurementDOE and Non-DOE

LBNF Lundin | LBNF Far Site Conventional Facilities and Interfaces4 FSCF Scope – Site Overall Sanford Underground Research Facility Ross Complex Yates Complex Property Summary 186 acres (surface) 7700 acres (underground)

LBNF Lundin | LBNF Far Site Conventional Facilities and Interfaces5 ControlRoom 12kV PowerFeed 12kV Power Feed CryogenicCompressorBuildingand Cryogenic Systems (LAr and LN2) RossHoistBldg Ross Headframe and Crusher Bldg Waste Rock Handling System from 4850L to Kirk Road Ross Dry RossSubstation

LBNF Completion of Ross Shaft rehabilitation, skips, loading pocket Utilities in the Ross Shaft  Electrical power  Fiber optics for experiment data & control and fire alarm  Pipes in Ross Shaft for nitrogen and argon transport  Fire water pipe from 4100L sump to 4850L  Concrete slick line for construction FSCF Scope – Ross Shaft Lundin | LBNF Far Site Conventional Facilities and Interfaces6

LBNF LZ (future) LUX-ZEPLIN Second generation dark matter Lundin | LBNF Far Site Conventional Facilities and Interfaces7 FSCF Scope – 4850L Facilities Four 10kt detector pits, central utility cavern, and connecting drifts

LBNF FSCF Scope – 4850L Excavations Excavated material ~800,000 tons Lundin | LBNF Far Site Conventional Facilities and Interfaces8

LBNF Phasing of Excavation – Logistics and Ventilation Challenges Lundin | LBNF Far Site Conventional Facilities and Interfaces9 Phasing focuses on separating “clean” cryo/experiment work and “dirty” CF work.

LBNF Other FSCF Scope – Early Work at the Surface SURF has identified several surface projects that pose risks to the facility and should be addressed prior to LBNF construction; Examples include: Near-surface adit repairs (Tramway, 300L) Crusher building roofs at both shafts Hoist upgrades (motor rebuilds) Headframe reinforcement at both shafts Administrative Building Parking lot/roadway Oro Hondo fan replacement Lundin | LBNF Far Site Conventional Facilities and Interfaces10

LBNF Other FSCF Scope - Early Work Surface & Underground Lundin | LBNF Far Site Conventional Facilities and Interfaces11 Waste Rock Handling System

LBNF Interfaces with CF – Cryostat / Cryogenic Systems Layout Lundin | LBNF Far Site Conventional Facilities and Interfaces12 Cryostat 1 Cryostat 4 Cryostat 3 Cryostat 2 Central utility cavern Each Cryostat holds 17.1kt LAr Central Utility Cavern holds Cold boxes, LN2 dewars, booster compressors, LAr/GAr filters Note: 2nd Cryostat must be complete before operations begin in Cryostat 1

LBNF Lundin | LBNF Far Site Conventional Facilities and Interfaces13 External (Internal) Dimensions 19.1m (16.9m) W x 18.0m (15.8m) H x 66.0m (63.8m) L Interfaces with CF – Free-Standing Steel Cryostat People for Scale

LBNF Interfaces with CF – Membrane Cryostat Lundin | LBNF Far Site Conventional Facilities and Interfaces14

LBNF Far Site Facilities Organization & Staffing Lundin | LBNF Far Site Conventional Facilities and Interfaces15 L3 PM (B Norris) CF Scope Interfaces with CF

LBNF LBNF at the Far Site - Schedule Summary Overview Lundin | LBNF Far Site Conventional Facilities and Interfaces16 Approval to Operate Cryostat #2 FY27 FY26FY25FY24FY23FY22FY21FY20FY19FY18FY17 FY16 Excavation and UGI Cavern #1 FY15 Cryostat #1 Construction Surface Facilities Excavation and UGI Cavern #2 Cryostat #2 Construction Excavation and UGI Cavern #3 Cryostat #3 Construction SURF Operations Projects Waste Rock Handling Cryogenics Preliminary & Final Design Approval to Operate Cryostat #1 Conventional Facilities Complete Excavation and UGI Cavern #4 Utilities in the Shaft Cryostat #4 Construction Dec-19 CD-2/3c Project Baseline/ Construction Approval Oct-15 CD-1 Refresh Approval Nov-21 CD-4a (early completion) Jan-16 CD-3a Approval Cryogenics Construction Complete Feb-27 CD-4b (early completion) Cryogenics Activity (DOE) Conventional Facilities Activity Cryogenics Equipment Cryogenics Fluid FY28 Cryogenics Activity (Non-DOE) Conventional Facilities Preliminary & Final Design Cryogenics Activity (DOE & Non-DOE)

LBNF Planning for LBNF Construction – CM/GC Lundin | LBNF Far Site Conventional Facilities and Interfaces17 Developing RFP for Construction Manager/General Contractor (CM/GC) scope of work. CM/GC will help LBNF plan for and execute conventional facilities construction Will be available for cryostat, cryogenic systems, and DUNE detector installation, coordination and management Expect to have CM/GC under contract to Fermilab before the end of calendar 2015

LBNF Planning for LBNF Construction – Logistics Lundin | LBNF Far Site Conventional Facilities and Interfaces18 LBNF and DUNE are working on understanding the logistics issues associated with sharing limited space at the Far Site. Space is limited on the surface, in the shaft (the conveyances) and at the 4850L. Fermilab has engaged Arup to carry out a Construction Logistics Study for proposed work at three functional areas at SURF: - Construction of LBNF conventional facilities - Installation of LBNF cryostat and cryogenic systems - Installation of LBNF neutrino detectors A draft study was delivered August 3, All stakeholders participated in a logistics workshop held August 11-13, Final report due in early September.

LBNF Planning for LBNF Construction – Issues Lundin | LBNF Far Site Conventional Facilities and Interfaces19 Must get the CM/GC on board early enough to participate during final design. FSCF funding is too low for FY16-FY19. This will slow the rate of design and construction progress. Delivery of cryostat exoskeleton to 4850L is challenging – options under consideration. Experiencing some scope creep since CD-1R: ventilation borehole, rehabilitation of Ross Dry space, substation transformer upgrade to 30MW.

LBNF Lundin | LBNF Far Site Conventional Facilities and Interfaces20 Questions?