Lau Gatignon, Catania, 30-09-2014.  Introduction  COMPASS  NA62  SHIP L.Gatignon, 30-09-20141SPS fixed target physics at CERN.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Lau Gatignon, EATM, 7 October  The T9 and T10 lines have been running smoothly from mid July and the T11 beam started up very smoothly for CLOUD.
RAL 27 April 2006The beta-beam task, EURISOL1 Status of the beta-beam study Mats Lindroos on behalf of the EURISOL beta-beam task.
Summary of the Design Report and Next Steps Edda Gschwendtner for the CERN AWAKE Project Team Edda Gschwendtner, CERN1.
CERN First Considerations to implement nuSTORM on the CERN site “North Area Neutrino Hub” E.Wildner, CERN Wednesday, March 27, 2013Elena Wildner,
Lau Gatignon / EN-MEF, IEFC Workshop, 8 March 2012.
The MERIT experiment at the CERN PS Leo Jenner MOPC087 WEPP169 WEPP170.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
The ISIS strong focusing synchrotron also at the Rutherford Appleton Laboratory. Note that ISIS occupies the same hall as NIMROD used to and re- uses some.
J.-P. Riunaud PS/AE PSMB 16/09/2002 Report from 59 th SPSC meeting 03/09/2002 OPEN SESSION on Tuesday, 3 September 2002 at 09:00, Main Auditorium 1. Proposal.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
12/10/05NuPAC – CERN 2005M. Benedikt 1 Potential future proton beam performance at CERN for HIE ISOLDE, n_TOF phase 2 and EURISOL Michael Benedikt AB Department,
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
1 Target Station Design for Neutrino Superbeams Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory NBI 2012, CERN.
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
NA61 11 October 2010Light Ion for NA61/ S. Maury1 Light Ion in SPS Foreseen to have primary Ar beam physics in 2012 Nothing runs in 2012 NA61 duty cycle.
COMPASS polarized target for Drell-Yan Michael Pesek Charles University in Prague On behalf of COMPASS PT group PSPT, Charlottesville, Virginia
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
General Information New members in ABP (RTL): –M. Samson Restructuring should be finalized by the end of the year to be effective for beginning of the.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CERN Test Beam Update and Schedule
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
CNGS Operation Summary Edda Gschwendtner, CERN. Outline Introduction CNGS Performance Highlights since last NBI 2010 in Japan Issues Summary 2E. Gschwendtner,
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
Dec7,2007 ie-FP7 Test Beams for detector R&D at CERN The PS East Area The SPS North Area Irradiation facilities.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Status of facility design Activities of the IPNS Nuclear/Particle Physics group Basic information for the working sessions Activities of Nuclear and Particle.
Application of FLUKA to fixed- target programs at CERN: a short, not exhaustive selection M. Calviani (CERN) With contributions from: M. Brugger, F. Cerutti,
Lau Gatignon, EATM,  The construction of the CHARM and IRRAD zones is completed and operation at nominal intensity started yesterday.
Extraction and beamline progress B.Goddard TE/ABT.
Lau Gatignon. The open session of this meeting was fully dedicated to the AD program with 6 presentations by AEGIS, ACE, GBAR, ASACUSA, ATRAP and ALPHA.
Radiation Protection Considerations for the CDR Helmut Vincke DGS-RP.
Mixed field irradiation -- Who answered ?  In total 36 forms filled / 34 persons answered: 38% 62% CERN: mainly LHC related topics CERF: beside LHC topics.
EU accelerator contributions to the IDS … R. Garoby ISS meeting RAL 28/04/2006.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
LIEBE Target Design Review. Schedule This comment is no longer valid as the schedule has been postponed and the beam permit will be requested for Q
HiRadMat status report Adrian Fabich HiRadMat EAM, 4. March 2016 EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th.
RF separated beam and other beam issues Lau Gatignon, COMPASS workshop, 22 March 2016.
PRESENT AND FUTURE TEST FACILITIES FOR HIGH- INTENSITY TARGETRY CERN I.Efthymiopoulos, CERN with input from Jacques Lettry & Rende Steerenberg.
CERN accelerator chain (operating and approved projects)
Proton and neutron irradiation facilities in the CERN-PS East Hall Maurice Glaser and Michael Moll CERN- PH-DT2 - Geneva - Switzerland 6 th LHC Radiation.
SPSC114 summary for EATM Lau Gatignon / EN EATM, 15 July 2014 Open Session:OPERA, ICARUS, NA63, COMPASS, CLOUD, P349 (pbar polarization) Closed Session:Neutrinos.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
EXPERIMENTAL AREAS CONSOLIDATION EACONS part – early draft from comments.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
SPS Beam Dump Facility M. Calviani (CERN) on behalf of G. Arduini, K. Cornelis, M. Fraser, L. Gatignon, B. Goddard, R. Jacobsson, M. Lamont, M. Manfredi,
Mandate Priorities Other tasks Membership Forthcoming reports to CTC
The SHiP Facility Lau Gatignon / EN-MEF
CONVENTIONAL BEAMS WG Lau Gatignon, Markus Brugger, CERN/EN/EA
News and brief overview of Beamline plans for the next few months
SPSC123 Summary Lau Gatignon/EN-EA IEFC, 4 November 2016.
Accelerator and Experiment Interface Session: LS2, LS3
Status of the beta-beam study
of secondary light ion beams
Acknowledgments: LIU-PT members and deputies, H. Bartosik
M. Calviani, A. Ferrari (EN/STI), P. Sala (INFN)
BG - SPS BDF - PBC WS March 2017
nuSTORM and the Physics Beyond Colliders workshop
Beam Dump outline work plan (UK perspective)
2003 test beam with 25 ns bunched muons
Fassò, N. Nakao, H. Vincke Aug. 2, 2005
Present and Future test facilities for High-intensity Targetry CERN
Drell-Yan measurements with COMPASS
Presentation transcript:

Lau Gatignon, Catania,

 Introduction  COMPASS  NA62  SHIP L.Gatignon, SPS fixed target physics at CERN

L.Gatignon, SPS fixed target physics at CERN SHIP NA62 COMPASS

L.Gatignon, SPS fixed target physics at CERN

 All running fixed target experiments at the SPS want highest statistics with minimal pile-up. In practice the figure of merit is the time on flat top per year, i.e. the total time over which protons are extracted to the production targets of the beam lines.  The time on flat top is the product of  number of physics days scheduled  machine efficiency  duty cycle  The machine efficiency degrades if one pushes the intensity to the limits  The duty cycle for the North Area fixed target program depends on the other physics users at CERN and on the primary beam momentum (due to heating of the SPS and North Area magnets). It is the ratio of the length of the flat top(s) and the length of the super-cycle. L.Gatignon, SPS fixed target physics at CERN4

E.g:  Supercycle 14.4 (16.8) sec  Flat top 4.8 sec  Duty cycle 33.3 (28.6)% The longer super cycle (i.e s) served for machine studies in parallel with physics. In those days (before CNGS) no LHC filling! L.Gatignon, SPS fixed target physics at CERN5 Intensity in SPS Magnet current

L.Gatignon, SPS fixed target physics at CERN6 E.g:  Supercycle 46.8 sec  Flat top 9.6 sec  Duty cycle 20.5%  But high number of protons on target delivered for CNGS (~ pot over the CNGS years)

L.Gatignon, SPS fixed target physics at CERN7

 COMPASS has been running for many years with high-energy high-intensity muon beam for studies of the spin structure of the proton. Up to muons per spill at 160 GeV/c.  It has also operated with negative hadron beams for measurements of the Primakoff effect and for spectroscopy experiments. The intensity of the hadron beam was about 5 MHz.  The secondary hadron beam was of ‘modest intensity’ and required modest primary proton intensity on the T6 primary target. The (tertiary) muon beam requires the maximum incident proton flux that could reliably be delivered on the T6 target within the limits of equipment survival and radiation protection constraints. The latter are mostly related to the fact that the COMPASS experiment is located in a surface hall.  Most of the time COMPASS has been running (successfully) in parallel with the CNGS program, which has come to an end in L.Gatignon, SPS fixed target physics at CERN8

L.Gatignon, SPS fixed target physics at CERN9

COMPASS has been formally approved for running until LS2 for the following physics programme: L.Gatignon, SPS fixed target physics at CERN10  In 2014 and 2015 transversity studies with a secondary  - beam at 190 GeV/c onto a polarised target followed by an hadron absorber. This allows to increase the intensity up to 10 8 per second.  From 2016 onward high-intensity positive and negative muon beams for spin-dependent Generalised Parton Distributions. This requires again the highest proton fluxes on T6, namely ppp for a 4.8 sec flat top or ppp for a 9.6 sec flat top  These fluxes are limited by the PS and SPS radiation levels, the proton beam extraction and transport through TT20, the splitters, the T6 target and TAX beam dump-collimators, as well as radiation levels on the surface.

There are ideas, but nothing is officially proposed or approved yet. Among the ideas discussed (and presented to the European Strategy Group) we could mention  More Drell-Yan running with  - beam (as in 2014/15),  An extension of the previous muon physics program with the existing polarised target,  GPD physics with high-intensity muon beam on a polarised target (the latter needs further study),  A polarised RF-separated anti-proton beam (not yet studied),  A hyperon beam, produced in the end of the beam tunnel (not yet studied). These projects would require at some stage a consolidation of the infrastructure in the experimental hall and the last two a re-design and rebuild of the secondary beam line. L.Gatignon, SPS fixed target physics at CERN11

L.Gatignon, SPS fixed target physics at CERN12 From Andrea Bressan:

 The NA62 experiment construction is approaching completion and commissioning of the almost full detector is scheduled to start next week.  The beam line has been commissioned in a Technical Run in fall 2012 (along with part of the detector). The beam line itself was complete, but the infrastructure did not yet allow running at high intensity for extended periods.  Following the 2012 experience some minor details have been further improved, the T10 target and its instrumentation have been consolidated and the vacuum system for the decay volume is being completed and finalised. However, the final ventilation system in ECN3 and TCC8 will only be installed in  The main objective of the 2014 run is commissioning of beam line and apparatus, combined with some first physics studies, e.g. K + ➝  + at the level of the SM sensitivity. L.Gatignon, SPS fixed target physics at CERN13

L.Gatignon, SPS fixed target physics at CERN14 ~10 12 / s protons from SPS (400 GeV/c) on Be target (~1  750 MHz secondary beam: Positive Kaon fraction ~6%  p/p ~ 1%

L.Gatignon, SPS fixed target physics at CERN15 Very preliminary projection A.Ceccucci,

L.Gatignon, SPS fixed target physics at CERN16

 The NA62 requirements are similar to those of NA48 in terms of intensity. However, due to more stringent RP restrictions these conditions imply a redesign of the ventilation system and a strict air separation between the T10 target area and the experiment itself. The present layout is ok for NA62 but has no large safety margins.  In the case of a 4.8 sec flat top the combined proton requests from NA62, COMPASS and the T2 users can be satisfied: T2 + T4 (NA62) + T6 (COMPASS) = ( ) = ppp  IF one has to run with a long flat top and IF COMPASS requires maximum proton flux (?), these rates have to be increased to maintain competitive instantaneous rates: T2 + T4 (NA62) + T6 (COMPASS) = ( ) = ppp  In the latter case one must either reduce one or more of the target intensities or find ways to improve the transmission. Some ideas exist. L.Gatignon, SPS fixed target physics at CERN17

 A search for K L ➝  o  which is being studied under a PRIN grant. As the SM branching is smaller than for K + ➝  +  and as it is important to have a narrow ‘pencil beam’ to constrain the decay kinematics, such an experiment requires substantially higher proton fluxes on the K o production target than NA62. The PRIN studies used a flux of ppp on this target, assuming a long flat top.  Such requirements may need very substantial modifications to the tunnel, infrastructure (ventilation!), beam transport and beam protection and radiation protection if such an experiment were to be housed in the present NA62 location. However, in a facility similar to the one proposed by SHIP this could become more realistic.  PRIN has also looked at the possibility to look for Dark Matter candidates with a sensitivity which is limited by the presently available proton flux. L.Gatignon, SPS fixed target physics at CERN18

 An Expression of Interest was submitted to the SPSC in October 2013, proposing a search for neutral heavy leptons in a proton beam dump at the CERN SPS.  The SPSC recognises the interesting physics potential of searching for heavy neutral leptons and investigating the properties of neutrinos. Considering the large cost and complexity of the required beam infrastructure as well as the significant associated beam intensity, such a project should be designed as a general purpose beam dump facility with the broadest possible physics programme, including maximum reach in the investigation of the hidden sector  To further review the project the Committee would need an extended proposal with further developed physics goals, a more detailed technical design and a stronger collaboration.  In the mean time the collaboration has progressed along these lines, with two recent workshops, and the CERN management has mandated a taskforce to study the consequences for CERN if this project were approved. L.Gatignon, SPS fixed target physics at CERN19

 A taskforce was established by R.Saban with members G.Arduini, M.Calviani, K.Cornelis, LG, B.Goddard, A.Golutvin, R.Jacobsson, J.Osborne, S.Roesler, T.Ruf, H.Vincke, H.Vincke.  The task force report (81 pages) has been released and delivered to the CERN management. It is available on EDMS as document V1.0.  While the collaboration is working towards its Technical Proposal, some exchange of information with the Task Force members will be organised in the form of a few meetings.

 Location and civil engineering layout have been defined.  Slow extraction onto TT20 (NA channel) and replace splitter 1 by a laminated splitter/switch magnet. Then exit through Jura side wall of TDC2 into >200 m long tunnel onto the target. Flat top about 1 sec.  The target is dense (tungsten) and segmented for survival. RMS power 400 kW, 2.9 MW during the spills. This is in fact a spallation target!  The muon filter baseline is passive, but magnetised shielding is under investigation. Aim: < 10 5  per spill. This 70 m long muon filter Is followed by the detector hall (120x20 m 2 ), which is ‘underground’.  Main issues needing more work: activation at extraction ZS and target survival and manipulation.  A preliminary schedule has been prepared. Tight planning in LS2. May need some cool-down time before (ion run?).  Protons must be shared with the other fixed target users in the NA, CNGS-like.

But shortage of protons for NA62+COMPASS?

B.Goddard

The production target is installed inside an underground FE shielded bunker, accessible from the top

 Fully remote handling / manipulation of the target and shielding from the target hall - High residual dose rate (tens of Sv/hr!)  Helium environment enclosing the target and the shielding - Reduction of air activation and corrosion  Ventilation system according to ISO The idea is to have a pressure dynamic → confinement L.Gatignon, SPS fixed target physics at CERN27

 The target must be segmented to reduce temperatures and compressive stresses  Very high flow rate required (cavitation, erosion/corrosion…) - Need to check “water hammer” effect on target/cooling circuits  Full control of water chemistry (à la nTOF)  Vigorous R&D should be launched on material properties and their evolution with radiation and temperature - Ta-cladded W, Wre alloys, K-doped W alloys, etc L.Gatignon, SPS fixed target physics at CERN28

Th. Ruf

 Building a muon shield with 70 m length fulfilling the experimental requirements is feasible.  Much more work is needed to optimise the cost.  Passive shielding: -requires ~100 t of W and ~2500 t of Pb, -a large part of the W/Pb could be resold after the experiment completion, -additional material (e.g. building walls) ideally as far as possible to minimise backsplash, or filling up the space between shield and walls with iron.  Active shielding:.a combination of a magnetic field (~30 Tm) and a passive iron shoeld comes close to the experimental requirements, living with the return field is the key issue -new ideas of magnetic field configuration should be actively pursued.  In parallel, need to study (full simulation) the background caused by surviving  ’s L.Gatignon, SPS fixed target physics at CERN31

L.Gatignon, SPS fixed target physics at CERN36 ItemCost (MCHF)FTE Extraction and proton beam line Target station Muon filter (passive shield)11.0 Civil Engineering Infrastructure Total

 Beam losses will cause 1. Air activation 2. Residual dose rate increase 3. Dose to equipment (magnets, cables, etc)  “Estimated beam losses from high intensity beam (7x1013 protons per extraction) are about a factor 7 higher than for CNGS beams”, (Quotation from collimator LIU review minutes)  Already at nominal beam intensity the dose levels will be a factor 3-6 higher than in previous years. Without mitigation, this could lead to dose levels of 12 mSv/hr after a month of cool-down.  Ways to reduce beam losses have to be investigated. L.Gatignon, SPS fixed target physics at CERN37

2x

 Compared to the version discussed in the Task Force report, progress has been made. An important possible modification concerns the muon filter, which may become a magnetic shield. This allows, according to first studies, a cleaner environment for the detectors with a shorter length. This may have an impact on the civil engineering layout.  The impact on e.g. NA62 and COMPASS is similar to the one of CNGS, with probably again a longer flat top for the North Area users.  A facility of this type may be of interest for other experiments, e.g. after SHIP. It may be wise to take such aspects into account when optimising the final layout.