Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.

Slides:



Advertisements
Similar presentations
Report from MICE project teams Proposed MICE organogram: revised Revised request for resources for financial year 2003/04 Review of iMICE schedules – status.
Advertisements

TurnKey Project Management Services Capabilities Briefing.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Mu2e WGM 4/21/2010 R. Ray Mu2e Project manager. Project Team We have a L2 manager for the tracker!  Aseet Mukherjee has assumed this role  Experience.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Auger Project Management H. Glass Director’s Review15-Dec-2011 Fermilab (Technical Division) has hosted Auger Project Management office since collaboration.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
Release & Deployment ITIL Version 3
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
CERN LBNE Test Experiment. Plan view of Bat
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
Requirements Review – July 21, Requirements for CMS Patricia McBride July 21, 2005.
Control & Monitoring System Update Contributors: Brian Martlew - Daresbury Laboratory - STFC James Leaver - Imperial College Pierrick Hanlet - Fermilab.
Telescope Integration and Tests Tuesday Afternoon.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Challenges & Issues for SBNE Nigel S. Lockyer 4/4/14.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Conventional Construction Working Group Meeting Tom Lackowski L2 Conventional Facilities Mu2e Working Group.
Consultant Advance Research Team. Outline UNDERSTANDING M&E DATA NEEDS PEOPLE, PARTNERSHIP AND PLANNING 1.Organizational structures with HIV M&E functions.
P. Shanahan Nov 15, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since May review Near Detector Electronics production.
K.Gadow CALICE technical review 1 Move to FNL ECAL/HCAL-Movable Table Setup test beam integration to Fermilab MT6-B3/B4.
Summary of the WA104, T600 overhauling programme C. Montanari – INFN-PV, Italy M. Nessi – CERN, Switzerland weekly meeting, December 18,
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
Linda Bagby - SBN Program Electrical Coordinator ICARUS Electronics Meeting 27 January 2016 SBN Program Operational Readiness Clearance.
Installation of the T600 at Fermilab CSN2, September 22,
Remote Monitoring for Hardware & Beam Commissioning E. Harms/FNAL 7 April 2005 Port Jefferson, New York bnl - fnal- lbnl - slac US LHC Accelerator Research.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Long-Baseline Neutrino Facility LBNF Cryostats Systems Requirements on FSCF Marzio Nessi LBNF/DUNE DOE/SC CD-3a Director’s Review October 27-29, 2015.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
TE-CRG Activities D. Delikaris, TE-CRG.
MicroBooNE Working Group Meeting March 08, :00– 2:00 PM Black Hole (WH2NW)
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
O. Kester, NuSTAR annual meeting, 27/02/2013
Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
CERN Neutrino platform 24 th July, 2014 S. Bertolucci CERN.
LBNF Cryo + Detector schedule Filling scenarios (Cryostats #1 and #2) Mohammed Elrafih, Elaine McCluskey, David Montanari, Marzio Nessi, Bob O’Sullivan.
Challenges to get LBNF ready for Far Detector installation ASAP Elaine McCluskey ELBNF Proto-Collaboration Meeting 22 Jan 2015.
CERN Steve Kettell DUNE Collaboration Meeting January 12, 2016.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
T600 Detector FNAL Fernanda G. Garcia Fermi National Accelerator Laboratory.
Warm Vessel Leveling Islands (Piers)
Installation of the T600 at Fermilab
Completion and Pre-Exploitation Costs for the Initial ATLAS Detector
SBN Far Detector Installation & Integration
News about the WA104 Programme
SBN Far Detector integration model overview
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
(Procurement, testing of magnets)
Warm Vessel South Wall Installation, Sub-assembly Option
Status of the PANDA Magnet
Far Detector Activities Late 2017 – Early 2018
Status of CO2 Cooling tests at CERN for Pixel phase 1
NSS integrated installation plan workshop Introduction
Preliminary Project Execution Plan
Presentation transcript:

Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration

SBN 12/16/201A. Stefanik | SBN Director's Review Dec

SBN The SBN Far Detector Installation and Integration (SBN FD I&I) work package aims to develop and implement the plan for installation and integration of the ICARUS detector at FNAL over the next two years and be ready for beam data taking in CY2017 The recently formed SBN FD I&I team has been active getting information and establishing the strategy –Level 2 manager took up her post in Nov 2015 Visited CERN and met CERN and INFN collaborators –Experienced skill personnel identified - Nov 2015 –Majority of the team is not at full-time capacity on the project Nevertheless the group is motivated and committed to the task –At this point we have focused on T600 detector installation plan Integration CAD model Grounding plan Far Detector Installation & Integration Overview 12/16/201A. Stefanik | SBN Director's Review Dec

SBN Resources 12/16/201A. Stefanik | SBN Director's Review Dec Collaboration with CERN and INFN colleagues is imperative throughout this process WBS Fernanda G. Garcia WBS 4 Cat James Mechanical Support - Andy Stefanik Justin Tilman, John Voirin Jim Kilmer Electrical Support - Linda Bagby Baghda Baiboussinov Cryogenic - Mike Geynisman Mike Zuckerbrot Alignment - Babatunde OShinowo Cosmic Ray Tagger - Bob Wilson David Warner

SBN The SBN far detector installation and integration work package scope includes the following major points: –Assembly of one warm cryostat –Installation of T600 detector (more later on this presentation) –Overseeing / joint coordination of cryogenic system installation assembly and testing cooperation between CERN and FNAL –T600 commissioning & cool-down –Detector support systems readout support requirements grounding requirements (more later after this presentation) –Installation of cosmic ray tracker (Detector breakout) –Installation of overburden (Facility Infrastructure breakout) Firming up the high-level integration between the different subsystems is key to maintain schedule Far Detector Installation & Integration Scope 12/16/201A. Stefanik | SBN Director's Review Dec

SBN WBS 40 SBN/4.1.1 – FD Installation and Integration –Identify a responsible manager for each subsystem  –Develop a schedule Provisional schedule in progress  “Living document” as our understanding matures –Identify budget needs First top-down (presented in this review)  Updating to a bottom-up approach --> system managers define their budget in agreement with project leader –Account for dependences on or links with other subsystems, schedule and budget Level of granularity will depend on complexity of task –Define the type and number of documents required for the project –Define management and communication structure Weekly meetings with managers  Increase personnel recruitment in the next months Structuring the SBN Far Detector I&I task 12/16/201A. Stefanik | SBN Director's Review Dec

SBN 12/16/201A. Stefanik | SBN Director's Review Dec SBN Far Detector Installation Timeline – Provisional Plan FD Building Construction 2Q Q Q Q Q Q Q Q Q Q 2016 Ship Overburden Ship Warm Vessel Parts Ship Two Cold Vessels with ICARUS Detectors Assemble Warm Vessel in FD Building Install Warm Vessel Insulation (Vendor) Install Two Cold Vessels into Warm Vessel Install Cryogenics Install Detector Readout Systems Install CRT, integrated with Warm Vessel and Readout installation – details TBD Pump down, Cool, Fill, Commission

SBN Active communication and close cooperation with CERN and INFN colleagues is essential –Maintain consensus and keep the collaboration informed –We will seek advice on alternatives to consider during the planning process –We are assuming some installation tasks will be collaborative with our colleagues We will rely on Claudio Montanari (ICARUS Technical Coordinator) and Marzio Nessi (Head of CERN Neutrino Platform) for our primary point of contact and anticipate a close collaboration with the entire team Cooperation among institutions 12/16/201A. Stefanik | SBN Director's Review Dec

SBN 12/16/201A. Stefanik | SBN Director's Review Dec Current thoughts on Detector Grounding (presented later) Installation of the T300 modules

SBN The current installation proposal is based on the following: Each unfilled T300 detector weights 52 metric tons (57 US short tons). There are two building cranes; each crane has a capacity of 27.2 metric tons (30 US short tons). We assume we will need a lifting fixture. Fermilab personnel will install the T300s if no rigging contractors are required. We have two other possibilities that depend on the equipment that Fermilab owns: Use a rigging contractor for specific tasks. Use a rigging contractor for the entire installation task. We will work with Fermilab rigging and safety personnel as the installation plan develops. We have already started discussions with rigging personnel. Installation will be in accordance with Fermilab Standards. Installation of the two T300 cold detectors 12/16/201A. Stefanik | SBN Director's Review Dec

SBN Each T300 will arrive at Fermilab on a low-boy trailer Installation of the two T300 cold detectors 12/16/201A. Stefanik | SBN Director's Review Dec

SBN Use rigging contractor to lift the T300 off the trailer and to place it on track rollers so it can be rolled into the building. Fermilab personnel does the rest of the installation work. Installation of the two T300 cold detectors 12/16/201A. Stefanik | SBN Director's Review Dec m (90”) clearance between the hook and the top of the T300.

SBN ICARUS lifting fixture. T300 Lifting Fixture 12/16/201A. Stefanik | SBN Director's Review Dec

SBN T300 Installation Route 12/16/201A. Stefanik | SBN Director's Review Dec #1 #2 North

SBN Next stage on the process is to work with CERN to Obtain 3D models and drawings in a workable electronic format. Verify weights and lift points on all the components that will reside in the far detector service building Especially lift points for the T300 which will allow the lifting fixture to be designed Determine which institution will provide the T300 lifting fixture for installation Verify support points under the T300 modules so we know where to place the rollers … Installation of the two T300 cold detectors 12/16/201A. Stefanik | SBN Director's Review Dec

SBN SBN Far Detector installation and integration plans have started –Team recently formed to develop the plan Personnel will increase as we continue working on this –Preliminary structure on management and communication is in place –Provisional schedule exists Accumulating and updating information on tasks, schedule, and manpower as the team learn more about installation –Effort focus on the most urgent needs Ongoing development of a plan for T600 detector installation Preliminary thoughts on detector grounding Conclusions 12/16/201A. Stefanik | SBN Director's Review Dec