ESS Vacuum Systems TAC 6 November 2012 Peter Ladd Senior Vacuum Expert.

Slides:



Advertisements
Similar presentations
4-1 Chapter 4 Overview b The DCM is very complex Mechanical, electrical, hydraulic and safety systems all work together Mechanical, electrical, hydraulic.
Advertisements

Progress and Plan for Superconducting RF Cavity RF Group.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
ORNL is managed by UT-Battelle for the US Department of Energy Commissioning and Operation of the Horizontal Test Apparatus at SNS Presented at: CEC/ICMC.
ESS Cryogenic System Process Design Philipp Arnold Section Leader Cryogenics CEC – ICMC 2015 June 29, 2015.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
Front End Test Stand Klystron Commissioning Alan Letchford UKNF Plenary Meeting 22 nd April 2009.
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.
Utilities 14 October 2008 Martin Nordby, Gordon Bowden.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
CM1 Thermal Cycle CM1 Warmup –1/4/12 (Wed.) to 1/6/12 (Fri.) (~50 hours) –Verified turbo interlock system works CM1 Cooldown –Began 1/9/12 (Monday) –At.
G5 Beam Line Vacuum System. G5 Beamline Vacuum System Design  Bakeable and Particulate free to Class 100 Clean Room quality Require Clean room QA and.
Alexander Aleksandrov Oak Ridge National Laboratory
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
Safety Concept and Tests Fakultaet Maschinenwesen, Institut fuer Energietechnik, Bitzer-Stiftungsprofessur für Kaelte-, Kryo- und Kompressorentechnik Jülich,
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
Thomas Jefferson National Accelerator Facility Page 1 SPL Cryogenic and vacuum sectorisations 9-10 November, 2009 Joe Preble Workshop on cryogenic and.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
1 ESS Warm End Linac Cooling Water 5-6 May 2014 John Jurns.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Reliability of SNS Superconducting Linac April 12, 2011 Jeff Saunders SNS/ORNL.
ESS Vacuum Standardization
Cooling Water and Heat Recovery system Thomas Hjern Harald Bäck Design Leader Process systems Conventional Facilities Accelerator Review November 3-4,
ESS Cooling System - Interface with DTL 1 John Jurns Cooling System Engineer.
ESS Cooling System - Interface with RFQ 1 John Jurns Cooling System Engineer.
Machine Protection Systems (MPS) Arden Warner, and Jim Steimel Project X Machine Advisory Committee March 18-19, 2013.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Treatment Machines for External Beam Radiotherapy
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Overview of elliptical cryomodules vacuum system Vacuum Equipment Standardization meeting February 2014 P. Bosland – C. Darve – N. Elias.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
Accelerator Installation Plan: Graphical representation E. Sargsyan & L. Lari DRAFT - March March 2016.
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
Vacuum Related Procedures and Tools of IHEP ILC Test Cryomodule Assembly Jiyuan Zhai (IHEP) TTC Topical Workshop on SRF Cryomodule Clean Room Assembly.
Chapter Editor: John Weisend TDR Chapter 6 Cryogenic System, Vacuum System & Test Stands.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Primary Design Parameters July 13,2001 S. Childress Page 1 NuMI Besides design specifications driven by physics and Main Injector beam parameters, significant.
Slides for TAC meeting Oct/2015 Marcelo juni Ferreira Vacuum section leader October,
Field Emission Minimization for LCLS-II
Cryomodule test stand at ESS site
at STFC Daresbury laboratory
T5.2: Harmonization - Material and Component Reference
HIE-ISOLDE HEBT vacuum system
Leak Detection Tutorial Work
LINAC4 Vacuum Control System Review
XFEL Vacuum System Commissioning
Martin Dommach TDR ART Review, Hamburg, September 14, 2012
UK RFD Pre-Series cryomodule
Cryomodule Assembly Plan
ISRC and LEBT Vacuum System Design
LEBT water cooling system
(Beam) Commissioning Plan
High Level Readiness Reviews
RF introduction Anders Sunesson RF group leader
Charge and Agenda of the 18th TAC meeting
Vacuum System Design for the Target Monolith System
Overview of the TARGET Monolith Rough Vacuum
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Burst Disc Review Closeout 21 May 2019 J.G. Weisend II, Chairman.
General Overview of WP 12 ESS Vacuum System
Presentation transcript:

ESS Vacuum Systems TAC 6 November 2012 Peter Ladd Senior Vacuum Expert

Scope The vacuum team has overall responsibility for all ESS technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and Neutron Guides Providing guidance and on going support to ensure the implementation of compatible vacuum designs for e.g. vacuum chambers, components and other equipment exposed to a technical vacuum environment.

Vacuum Requirements Vacuum requirements are dictated by physics and individual system requirements. Accelerator – Levels required for the various areas of the accelerator are summarized in the ESS Parameter List together with the gas flow rate and gas species required for the Ion Source. – Typically vacuum levels will be in the mbar range. Target – The requirements for target system are not currently defined. Neutron Scattering Instruments and Neutron Guides – Vacuum levels required for the various Neutron Scattering Instruments will vary depending on the science to be performed. – Vacuum levels will typically range from the to mbar. – Neutron guides will operate in the – range.

An Integrated Approach As previously noted the vacuum team is responsibly for all ESS technical vacuum systems across the project. Working closely with our partners across the project one of the primary goals is commonality of equipment and to meet this goal a Vacuum Equipment Standardization Task Force will be established. This Task Force will be led by the ESS vacuum team with representatives from the various ESS partners involved in the use of vacuum equipment for the various accelerator vacuum subsystems. The mandate of the task force will be to develop a list of standard vacuum equipment that will be used for the various subsystems in order to minimize project costs, spares holding, training and achieve other benefits to be gained from standardization.

Accelerator Systems This activity encompasses the design, selection of equipment and integration of the vacuum systems into various accelerator systems: – Warm linac, comprising the front end systems (FES) and drift tube linac – Cold linac, comprising the spoke cavities and medium  and high  cryomodules – High Energy Beam to Target (HEBT), the beam line that delivers beam from the cold linac to the target and tuning beam dump

Front End Systems (FES) The front-end systems comprise: – the Ion Source (IS) » high hydrogen gas loads need to be handled » turbomolecular pumps (TMP’s) selected to meet requirement » TMP exhaust handled appropriately to eliminate potential for formation of explosive mixtures in the exhaust gas stream – Low Energy Beam Transport (LEBT), » similar pumping system to IS, same requirement to handle explosive mixtures in the exhaust stream – Radio Frequency Quadrupole (RFQ) » TMP’s are selected for commonality with the IS and LEBT and distributed along RFQ – Medium Energy Beam Transport (MEBT) » ion pumps selected since gas load primarily outgassing

Drift Tube Linac (DTL) Gas loads associated with the DTL tanks will be primarily outgassing Ion pumps selected for pumping and mounted directly to the DTL tanks. RF screens incorporated at inlet of each pump to prevent the regurgitation of gas due to RF power. Getter pumps used for maximum pumping speed between the RF window and iris within limited space available. Pump provided with isolation gate valve to allow reactivation of getter when heated. TMP backed scroll pump used to pump out the gas released from the getter during reactivation. The DTL tanks initially pumped down using mobile pump carts before the ion pumps are started.

Spoke Cavities, Medium  and High  Cryomodules The accelerating cavities of the spoke, medium and high β cryomodules cooled with liquid helium and are self-pumping. The cavities conditioned prior to installation in the tunnel where connections to warm sections are made. Connections made under clean room conditions using portable cleanrooms to minimize particulate contamination of cavities. Following connection warm section evacuated and interconnecting valves adjacent to each cavity and cryomodule opened. The vacuum jacket (insulating jacket) evacuated prior to cool down of cryomodule. Vacuum jacket is self pumping following cool down.

LEDP and HEDP Pumping Sections The LEDP (Low Energy Differential Pumping) section – Provides pressure reduction between last DTL tank and first spoke cavity to limit flow of gas from warm to cold section of machine. – Uses distributed ion pumps and beam pipe providing minimum conductance possible to maximum pressure reduction. – Includes beam instrumentation and fast closing valve to protect the first spoke cavity in case of loss of vacuum event occurring in warm section of the machine. The HEDP (High Energy Differential Pumping) section – Provides controlled pressure rise between last cryomodule and HEBT to limit flow of gas from HEBT into cold section of machine. – Configured in similar manner to the LEDP including fast valve to protect last cryomodule from loss of vacuum event occurring in the HEBT.

LEDP Installed at SNS

LWU’s (Warm Sections) LWU’s provide beam line connections between individual spoke cavity modules and individual medium  and high  cryomodules. LWU’s have centrally located ion pump, beam instrumentation, vacuum gauging and manual vent valve with micron filter to allow LWU’s to be vented. LWU’s isolated from cavities and cryomodules during installation by isolation gate valves located on end of each cavity or cryomodule. connections between LWU’s and spoke cavities and cryomodules made under clean room conditions, as previously noted, using portable cleanrooms to minimize particulate contamination of the cavities.

Warm Section Prep at SNS DI Water TankUltrasonic Tank Assembly/Bake AreaFinal Assembly

Warm Section Prep at SNS

LWU Clean Connection Clean room set up Clean connection equipment

Warm Section Installation at SNS

High Energy Beam to Target (HEBT) Beam line expands rapidly in vicinity of collimator leading to target window and tuning beam dump window. Areas potentially activated requiring special precautions for maintenance, i.e. the use of shielding, long handled tools and/ or remote handling techniques. Larger beam line and maintenance requirements provide challenges in selection of appropriate metal seal design for beam line flanges and providing remote leak testing capability. During hands on maintenance upstream of the collimator a gamma blocker is rotated into the beam line to block back streaming radiation from target, tuning beam dump and collimator. Radiation hard components with high reliability used where possible. Local shielding and a strategy to utilize redundant components in activated areas. Ion pumps used for pumping having no onboard electronics and controllers that can be located remotely.

HEBT A2T and Tuning Beam Dump

Target Systems The vacuum group will assist in developing the design of the vacuum interface and design of the proton beam window, target safety valve and interconnecting beam line between these components. Area activated and design will need to be compatible with replacement of components using long handled tools and/ or remote handling techniques. Forming part of the beam line helium leak testing required and with monolith filled with helium, testing with He 3 may need to be considered. HEBT operates at relatively high pressure ~10 -6 mbar therefore a reasonable level of leak tightness needed following component change out to minimize the gas load to ion pumps and maximize operational life due to saturation. The vacuum team will also assist in design of embedded vacuum system within the He Target cooling and the He monolith circuits.

Instruments and Neutron Beam Lines Overview of Vacuum Teams Support Activities – provides guidelines for design of vacuum chambers and selection of vacuum components and equipment, – performs materials testing, e.g. outgassing studies on materials installed in vacuum environment, – advises on and reviews designs of instrument chambers and components from a vacuum prospective e.g. weld design and material selection etc., – Inspects fabricated components and chambers for vacuum compatibility and witnesses vacuum testing at vendor premises, – performs testing and start up of vacuum systems following installation.

Neutron Scattering Instruments and Neutron Guides approximately 2900 m of neutron guide installed to support the full suite of instruments. vacuum pumping required about every 20 m along the neutron guides and need to provide an operating pressure in – range. assists in vacuum design of neutron guides and interfacing components e.g. choppers and designs, procures, fabricates and installs vacuum pumping equipment. neutron guides pumped with mobile pumping units allowing ready exchange of units for servicing. Approximately units required to support initial instruments suite.

Vacuum Facilities Vacuum facilities provided to support both construction and pre operational activities, including: – outgassing test chamber for material and component investigations, – general purposes bake out and drying ovens for preparation of equipment prior to installation, – support equipment including pump carts, leak detectors etc., – ISO Standard 209 Class 4/5 (Fed Standard 209D Class 10/ 100) cleaning and washing area for preparation of warm sections and other critical components prior for installation, – pump carts, leak detectors, portable cleanrooms and other equipment dedicated to “clean” cryomodule beam line connections, – provision of limited spares to support vacuum operations through the pre operational phase, – provision of pump carts, leak detectors, cold traps and other equipment to support maintenance of activated and/or contaminated equipment.

Material Outgassing Studies at SNS Outgassing decay RGA Scan

WP11 Vacuum Schedule

Accelerator Cost Distribution

Vacuum Systems Cost Distribution

Thank you for your attention to the preceding presentation where nothing really is a sign of a job well done…………