24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 1/23 24 th IAEA Fusion Energy Conference San Diego, USA, 8-13 October 2012 24 th.

Slides:



Advertisements
Similar presentations
ITER Organization, Cadarache, France
Advertisements

Fusion Power Associates Meeting, 5 December 2012 Slide 1/16 ITER Achieve 500 MW of fusion power. Demonstrate the scientific and technological feasibility.
Report from US ITER Fusion Power Associates December 15, 2011 Ned Sauthoff Project Manager.
TORE SUPRA Association EURATOM-CEA 1 TORE SUPRA Association EURATOM-CEA Julien WAGREZ EFDA GOTP - ITER PPE WP2 1 juin 2009 EFDA ITER - Goal Oriented Training.
Extension of IEA Implementing Agreement on Large Tokamak Facilities Presented to Committee on Energy Research Technologies October 18-19, 2005 Paris, France.
Office of Central Integration and Engineering
July 28, 2011 ITER Thomas J. Vanek Senior Policy Advisor Fusion Energy Sciences.
Stuart East, 22 nd May 2012 Delivering industrial solutions for the fusion research community Stuart East.
ASIPP Zhongwei Wang for CFETR Design Team Japan-US Workshop on Fusion Power Plants and Related Advanced Technologies February 26-28, 2013 at Kyoto University.
EPICS Collaboration Meeting – Aix-en-Provence June 2010 Page 1 ITER welcomes EPICS WD Klotz ITER int. Organiztion That’s me.
Physics of fusion power Lecture 14: Anomalous transport / ITER.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
Summary and Closing Remarks Farrokh Najmabadi University of California San Diego Presentation to: ARIES Program Peer Review August 18, 2000 UC San Diego.
The shield block is a modular system made up of austenitic steel SS316 LN-IG whose main function is to provide thermal and nuclear shielding of outer components.
DCal Meeting
Overview of Advanced Design White Paper Farrokh Najmabadi Virtual Laboratory for Technology Meeting June 23, 1998 OFES Headquarters, Germantown.
The main function of the divertor is minimizing the helium and impurity content in the plasma as well as exhausting part of the plasma thermal power. The.
Role of ITER in Fusion Development Farrokh Najmabadi University of California, San Diego, La Jolla, CA FPA Annual Meeting September 27-28, 2006 Washington,
The current overall EU policy framework: Europe 2020 strategy, Innovation Union and Energy 2020 Strategy On March 2010, the Commission presented a Communication.
Introduction to Computer Technology
ITER International Team 16th ANS Topical Meeting on Fusion Technology
Power Extraction Research Using a Full Fusion Nuclear Environment G. L. Yoder, Jr. Y. K. M. Peng Oak Ridge National Laboratory Oak Ridge, TN Presentation.
3 Dec 2003Market Operations Standing Committee1 Market Rule and Change Management Consultation Process John MacKenzie / Darren Finkbeiner / Ella Kokotsis,
Broader Approach Activities toward Fusion DEMO Reactors IT/E-2 IAEA 21 st Fusion Energy Conference (Chengdu 17 th October, 2006 ) Shinzaburo Matsuda Japan.
Norbert Holtkamp, October Status of the ITER Project Norbert Holtkamp Status of the ITER Project Norbert Holtkamp Principal Deputy Director General.
General Overview of the Korean Domestic Agency Procurement Activities K. J. Jung ITER Korea (KODA) National Fusion Research Institute.
Kaname Ikeda, October Status of the ITER Project Status of the ITER Project Kaname Ikeda ITER Nominee Director-General October 2006.
Tom MAZOUR IAEA, Division of Nuclear Power
Page 1 of 11 An approach for the analysis of R&D needs and facilities for fusion energy ARIES “Next Step” Planning Meeting 3 April 2007 M. S. Tillack ?
08 October 2015 M. Ammar Mehdi Introduction to Human Resource Management & SSG-16 Actions 4 th Steering Committee on Competence of Human.
Managed by UT-Battelle for the Department of Energy Stan Milora, ORNL Director Virtual Laboratory for Technology 20 th ANS Topical Meeting on the Technology.
US ITER UFA Meeting APS-DPP Savannah, GA Ned Sauthoff (presented by Dale Meade) November 15, 2004 US In-kind Contributions and Starting Burning Plasma.
EFDA EUROPEAN FUSION DEVELOPMENT AGREEMENT 16th TOFE Madison, Sept , EUROPEAN TECHNOLOGICAL EFFORT IN PREPARATION OF ITER CONSTRUCTION ROBERTO.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
1 1 by Dr. John Parmentola Senior Vice President Energy and Advanced Concepts Presented at the American Security Project Fusion Event June 5, 2012 The.
Norbert Holtkamp, October The Engineering Challenges of ITER The Engineering Challenges of ITER Norbert Holtkamp PDDG Nominee October 16th, 2006.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Programmatic issues to be studied in advance for the DEMO planning Date: February 2013 Place:Uji-campus, Kyoto Univ. Shinzaburo MATSUDA Kyoto Univ.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
ITPA12 Diagnostics - PPPL - 3/26-30/07 1 US ITER Project Plans David Johnson Diagnostics Team Leader March 26, 2007 ITPA12 Design Basis US Scope Port Plugs.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
IAEA International Atomic Energy Agency Methodology and Responsibilities for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
Request for Service (RFS) Process and Metrics Update June 24, 2008.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 2: Project Management 1.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board Of Directors – August 15, 2006 TPTF Meeting August.
ITER-China Project Huo YuPing PT Leader, ITER-China Chief scientist.
Managing Challenging Projects Presented to the class of: Dr. Jane Mackay M.J. Neely School of Business.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
Tata McGraw CHAPTER 4 Product and Service Design.
© The Delos Partnership 2005 Dairygold Workshop Strategic Sourcing Process.
DEVELOPMENT OF THE NATIONAL INFRASTRUCTURE FOR NUCLEAR POWER IN VIETNAM DEVELOPMENT OF THE NATIONAL INFRASTRUCTURE FOR NUCLEAR POWER IN VIETNAM Vuong Huu.
1 Preparation and Positioning of Korea for the ITER Project 2004 KSTAR US-Korea Workshop May 19-20, General Atomics.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
ITER Liquid Helium Plants Status and Test Protocol ICEC June 29th, 2015 / Grenoble / FranceY. FABRE.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
In-Kind Contributions Workshop – IKCW ITER Status of In-Kind Procurement Helium (3,5 MeV) Neutron (14,1 MeV) Deuterium Tritium Ken Blackler Construction.
Boundary Physics Breakout Session was a Good Start Breadth of topics: many issues pointed out in three plenary talks: pedestal, SOL/div/PFC, and technology,
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
Camera PDR/CD1 Planning 19 September 2008
CSP 25th November 2010 Technical agreement number 3: overview
ITER & Expectations for Fusion Research in the Next Quarter Century
The Engineering Challenges of ITER Norbert Holtkamp PDDG Nominee October 16th, 2006 Norbert Holtkamp, October 2006.
Annual Report on the IA for Co-operation on Tokamak Programmes
Annual Report on the IA for Co-operation on Tokamak Programmes
Stellarator Program Update: Status of NCSX & QPS
Presentation transcript:

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 1/23 24 th IAEA Fusion Energy Conference San Diego, USA, 8-13 October th IAEA Fusion Energy Conference San Diego, USA, 8-13 October 2012 Osamu Motojima Director-General of the ITER Organization St. Paul-lez-Durance Osamu Motojima Director-General of the ITER Organization St. Paul-lez-Durance

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 2/23 Introduction The 24th Fusion Energy conference marks the 5 th anniversary of the establishment of the ITER Project; Over the last two years, the ITER project has made the transition from building up the infrastructure of IO and 7 DAs; Design completion is leading a real construction of in-kind components; Our aim and responsibility are to show the progress of ITER construction keeping the project risk for ITER scope, cost, and schedule to an acceptable level. A new IO management structure was introduced in 2010; Decision making processes were streamlined and procedures simplified; Establish several new communication channels with 7 DAs; Unique ITER Team Faster decision making and a better performance of the combined Unique ITER Team (IO + DAs);

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 3/23 Contents to Report you Introduction/General ITER Project Status Schedule Structure and Management ITER Research Plan and Physics Operations Disruption Mitigation/ELM Mitigation The Key Technical Challenges Vacuum Vessel/Cryostat/Coils/In-Vessel Components Site Construction and Logistics Summary R=6.2 m, a=2.0 m, I p =15 MA, B T =5.3 T, 23,000 tons Unique ITER Team

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 4/23 Machine completion and First Plasma November 2020 D-T Operation 2027 Level 0 Reference Schedule within Baseline Boundaries We are addressing some potential schedule delays (Building, VV, PF Coils etc.) and working with the DAs on resolving them. IO and DAs as UIT are working hard to maintain this schedule. IO proposes to install a W-divertor from the beginning (first priority) IO proposes phased installation of heating : 67MW at non-nuclear phase full 73 MW at pre-nuclear shutdown) IO proposes to defer installation of some component and system from the construction to the operation phase (potential items, Heating systems, T-Plant, Hot Cell Tools, ELM/VS coil & PS, and TBM) IO is investigating the simplified assembly scenario Schedule ITER Level 0 Reference Schedule

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 5/23 Level 0 Overall Project Schedule (OPS): ~ 50 Activities……………..…………………………. Level 1 Strategic Management Plan (SMP): ~ 3000 Activities …………………………… Level 2 Detailed Working Schedules (DWS): ~ 150k Activities………….... (Including IO and DAs) Achievement of Schedule Structure and Management Completion of DWS DWS has been completed on 28 th June and reviewed Milestones are monitored and become controlled.

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 6/23 New SMP Lifecycle Forecast Using the new SMP post 2012 IO and DAs Implementing strong schedule recovery action Previous New

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 7/23 Procurement Arrangements (PA) are important milestones Total number of signed PA is now 80 out of a total of 137 The achieved value to date is kIUA out of a total In-Kind project value of kIUA; 81.2 % of value achieved US KO JA EU CN INRF

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 8/23 Significant progress in modelling of physics processes underlying ELMs and ELM control Disruption Mitigation System Conceptual Design Full revision of predicted heat loads on PFCs in support of First Wall and Tungsten Divertor design Conceptual design of Plasma Control System moving towards completion Extensive experimental and modelling R&D continuing in support of development of ITER disruption/ runaway electron mitigation systems Challenges of Plasma Physics

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 9/23 Non-linear Simulation of ELM Energy Deposition Conductive ELM in ITER Q=10 plasma ELM simulations in ITER Q=10 plasma scenario (JOREK code) Conductive ELMs : –large magnetic perturbation leads to ergodic edge with homoclinic tangles –parallel conduction on perturbed magnetic field lines –broadening of energy deposition scales with magnetic perturbation Convective ELMs: –filament formation, energy density losses in parallel direction –broadening energy deposition due to radial distance travelled relative to parallel transport

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 10/23 Disruption Mitigation System Conceptual Design Preliminary drawing Disruption Mitigation System is planned to consist of two subsystems: 3 Upper Ports primarily for Disruption Mitigation probably a single injection system in each port 1 Equatorial Port for Disruption Mitigation and RE Mitigation multiple injection systems

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 11/23 Challenges A technology qualification and prototyping programme is being executed in EU, JA, RF responsible for procurement of the W plasma-facing components; Target value are 1000 cycles at 10 MW/m 2 (Normal & Steady), 500 cycles at 20 MW/m 2 (Off-Normal); Within the Physics R&D Community and ITPA, efforts are underway to provide an assessment of the risks faced by ITER; From the physics point of view, the main risk elements are well recognized; Work remains to try and quantify them sufficiently well to inform a decision by the IO with regard to a full-W divertor start; IO is expecting a lot of important JET results with the ITER-like Wall and AUG etc; All-Tungsten Divertor Status The design of an all-tungsten divertor is currently under development at the IO. Low fuel retention and low dust inventory Significant contribution to schedule saving and cost containment for ITER Project Experience gained in operation with W-divertor in non-active phase The final design phase is planned to be completed by the end of 2013.

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 12/23 Port Cell Structures Interspace Port Plug Port Plug 9 incorporates: -TIP, VIR, and ECE -Detailed optical layout is being performed Diagnostic System ITER has approximately 45 plasma diagnostic systems. More than 70% of the diagnostic systems have been through the Conceptual Design Review process At least one PAs with all the DAs Concept of shared catalogue being developed to reduce overall costs

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 13/23 Key Technical Challenges of ITER Vaccum Vessel Challenges The vacuum vessel is the SIC (Safety Important Component) component The first boundary of the nuclear safety; Status The design of VV and ports by IO was complete and the manufacturing stage has already started; The VV manufacturing design is under preparation by the contracted suppliers of the main vessel, ports and IWS in the EU, Korea and India; Mock-up fabrication and testing programs are underway in EU, IN, KO and RF. The material manufacturing already started after the ANB approval; All the VV materials, including the main material 316 L(N) IG and bolt materials XM-19 and Inconel 625, were already qualified by the ANB. Contract of VV field Joint will be made soon by IO. Evaluation committee made a report;

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 14/23 Cryostat Status One of the most important and critical systems in the ITER project, and has very large number of complex interfaces; The cryostat manufacturing contract was signed in August 2012; Challenges The site workshop will be ready for the cryostat assembly in 2014; The first deliveries of components for assembly in the tokamak pit will occur in September 2015; Pre-manufacturing activities such as the Manufacturing and Inspection Plan, manufacturing CAD design and drawings and quality plan are being initiated between the ITER organization, INDA and their industrial partners. 3D View of Cryostat OD: m, HT: m Mass: ~3500T

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 15/23 Toroidal Field Coils Status The production of the TF coils is split into 3 main production areas: The TF conductors; The TF structures; and the TF windings and coils; The TF conductors, which comprise 450t of Nb3Sn, are supplied by EU, RF, JA, KO, CN and US. Over 70% of required 450t of Nb3Sn strand has already been produced; It is anticipated that the rest will be completed in two years; JADA has signed a series production contracts with Japanese and Korean suppliers to build a first of series for TF winding and for the fabrication of the TF structural section; Challenges Both China and Korea have fabricated dummy conductor, which has been supplied to Europe for TF winding trials; The TF structures are to be assembled by welding in Japan and Korea. The manufacturing feasibility of these large components has already been undertaken by the Japanese Domestic Agency and its industrial partners. Manufacturability study of large TF coil components by Toshiba and its sub- contractor KHI

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 16/23 Poloidal Field Coils The ITER Poloidal Field (PF) magnet system consists of six PF coils procured by EU (PF2~6) and RF (PF1); The two PAs between IO and each domestic agency have been signed; Contract with industry by EU will soon made; Central Solenoid US is responsible for the supply of the Central Solenoid for which JA supplies the conductors; The CS consists of six identical coils and is 13.6m tall, has a diameter of 4.2 m and weighs approximately 1000t; The contract for CS module fabrication was placed by the UA in July 2011; This was followed by a successful Preliminary Design Review in September Manufacturing input to structures design is being provided by US industry. The assembly tooling is on track for Preliminary Design Review in September Conductor test is at its final stage. We will complete several additional tests soon, but we have already one conductor satisfying necessary condition. PF1 winding equipment in place in the Efremov Institute.

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 17/23 Challenges The ITER Members are in charge of the design, manufacturing and delivery of the TBSs to the ITER site. IO is developing all required interfaces with the other ITER systems and buildings based on input data given by the Members; IO is performing all the design work necessary for the TBSs integration into ITER facility; The six TBMs are in three dedicated ITER equatorial ports; Test Blanket Module (TBM) Program Status TBM program provides the first experimental data on the performance of the breeding blankets in the integrated fusion nuclear environment; Detailed desing studies of TBM integration into ITER facility and related maintenance strategy performed; Agreement on generic TBM Arrangement achieved; right of intellectual properties, nuclear/non-nuclear liability, post irradiation test View of TBM Port Cell Area

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 18/23 Buildings and Site Infrastructure 50 Hectare level platform finished All infrastructure needed to support construction is complete 400kV electrical substation constructed Poloidal field coils winding building constructed Tokamak Excavation, foundation slab and anti-seismic plinths completed All 493 anti-seismic bearings fabricated and installed New Headquarters building completed and occupied from 8 October km “Special Itinerary” to allow the transport of large components from Marseille port to ITER is complete Status Challenges Building is the biggest critical path of schedule control Improvements to “robustness” of some structural elements is being implemented Engagement with industry is required to mitigate schedule challenges Innovative technical solutions need to be investigated to minimize risks to cost and schedule

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 19/23 Site Construction Progresses (1) Inside PF Coil Building Lower Basemat and Anti-seismic isolators View of the On-site Construction PF Coil Winding Building

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 20/23 Site Construction Progresses (2) Future ITER Council Room ITER New HQ Building Inside HQ Building ITER New Amphitheatre

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 21/23 ITER Itinerary Local Communities Provided Road Upgrades TF Coil ~360 t 16 m Tall x 9 m Wide Heavy Component on Road (TF Coils, VV Sectors, and PF1 Coil) VV Sector ~400 t 12 m Tall x 9 m Wide PF1 Coil ~200 t 9.4 m Dia FRANCE Itinerary: March 2013 Test Convey Beginning of 2014 Real Component will arrive at ITER

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 22/23 Representatives of the French nuclear regulator (ASN) make regular inspections of ITER. Here they inspect the civil works (April 2012). ITER files (DAC) submitted in March 2010 ~ 5000 pages > 700 questions asked by regulator ~ 10,000 questions during public enquiry ~ 180 recommendations and commitments now to be answered in next 2 years Safety and Licensing The ITER is a nuclear facility The ITER facility is being licensed in France as a Basic Nuclear Installation (INB) In November-December 2011, meetings of the Groupe Permanent, a standing committee of experts convened by ASN In parallel, in July-August 2011, Public Enquiry held in towns surrounding ITER In July 2012, ASN announced its decision to grant the decree to authorize the creation of the ITER facility decree now in draft and being discussed - hopeful for signing before end of 2012

24 th IAEA Fusion Energy Conference, San Diego, 8-13 October 2012 Slide 23/23 In Summary ITER is well and truly off the starting blocks. ITER is presently well into the construction phase and is facing the problems to be expected in such phases. The large size and unique requirements of ITER have presented many technical challenges for the design and manufacturing. ITER designs, R&D and manufacturing mock-ups are addressing these challenges. ITER will develop key components necessary for the development of fusion. We are learning a great deal from ITER. The achievements over the last 2 years have shown that an international cooperation such as ITER can work successfully SMP/DWS completed Effort to create Unique ITER Team to deal with the usual problems which arise in large and technically ambitious construction projects. ITER has a more complex organization and procurement scheme than other large science projects IO and DAs Implementing strong schedule recovery action. I am very glad to ask you watch and listen to our presentations this week.