LCLS-II Cryomodule Interconnect Camille M Ginsburg (FNAL) FNAL LCLS-II Deputy Team Lead – Cryomodules Cryomodule Control Account Manager 29 July 2015 Project.

Slides:



Advertisements
Similar presentations
1 PROJECT MANAGEMENT ROLE OF KEY PERSONNEL Bernd Madauss International Space University Strasbourg February, 2011
Advertisements

Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
EMIS Chapter 6. EMIS Chapter 6 EMIS Chapter 6 Fig 6.2 shows where the SEMP fits into the earliest program stages. Fig 6.5 has an.
Systems Engineering Management
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
Release & Deployment ITIL Version 3
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
From Research Prototype to Production
Fermilab Cryomodule QA/QC Model Jamie Blowers LCLS-II EDM/PLM Applications 31-Mar-2014.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Project Life Cycle.
普 华 永 道 Phase 1: Project Preparation Phase 1: Project Preparation Phase Overview Phase Overview.
Vertical Test Stand in IB1 C.M. Ginsburg (Fermilab) for the IB1 VTS Group SRF R&D Meeting 6.July 2006.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
IAEA International Atomic Energy Agency Methodology and Responsibilities for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden Design, Manufacture, Transport and Integration in Chile of ALMA Antennas Page.
Industrial Participation & SRF Infrastructure at Fermilab Phil Pfund with input from Harry Carter, Rich Stanek, Mike Foley, Dan Olis, and others.
Team-Based Development ISYS321 Managing the Information Systems Project.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
LCLS-II Button-type BPM (Review) Nikolay Solyak Review, FNAL, Dec. 12, 2014.
Final Design Review (90-100%) Production 1.3 GHz CryoModule Marc Ross, Systems Manager for Cryogenic Systems, LCLS-II May 2015 Fermilab ICB.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Fermilab LCLS-II Cryomodule QA/QC Model and Software Tools ESS Cryomodule Workshop, 16-Oct-2014 Jamie Blowers Head of Machine Shop and Quality & Materials.
Production CM QA/QC Plans and Systems Production Cryomodule Final Design Review Jamie Blowers 12-May-2015.
LCLS-II Prototype Cryomodule FDR J. Blowers, C.M. Ginsburg, T. Peterson, R. Stanek, J. Theilacker (FNAL) 21 – 22 January 2015 Homework Responses.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan May 22, 2015.
SRF Collaboration Shekhar Mishra Fermilab. Overview Charge: Does the laboratory make effective use of collaboration and existing SRF capabilities at other.
LCLS-II Cryomodule Design
LCLS II FNAL Niobium Pre- Procurement Review - Overview Camille M. Ginsburg, FNAL April 17, 2014.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Cryomodule Safety Approvals Jay Theilacker LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
LCLS-II Prototype Cryomodule Darryl Orris 21 January 2015 Final Design Review: Instrumentation.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
Camera PDR/CD1 Planning 19 September 2008
Cryoplant Controls Installation
Accelerator Readiness Review October 31, 2006
Dana Arenius LCLS-II 4.5K Cold Box Director’s Review November 16, 2016
Software Project Configuration Management
2K Cold Box FDR Introduction
2K Cold Box PDR Introduction
Crab Cavities Contribution from the U.S.
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
MLC Schedule Plan Proven in-house expertise and infrastructure for fabrication, assembly, and testing cryomodules Confident in our technical expertise.
LCLS-II Cryoplant Controls Readiness to Procure
Spoke CDS PDR Closeout J. G. Weisend II June 10, 2016.
2K CB FDR Overview:  Agenda, Charge, Review Process
JEFFERSON LAB LCLSII CRYOPLANT INSTALLATION PACKAGE DIRECTOR’S PROGRESS REVIEW Welcome and Introduction Stuart Henderson June 1, 2017.
EMIS 7307 Chapter 6.
Electron Beam Systems ETC and Methodology
DOE Review of the LCLS Project October 2006
Preliminary Project Execution Plan
DOE Review of the LCLS Project 7-9 February 2006
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

LCLS-II Cryomodule Interconnect Camille M Ginsburg (FNAL) FNAL LCLS-II Deputy Team Lead – Cryomodules Cryomodule Control Account Manager 29 July 2015 Project Management

2 Outline Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015 Cryomodule Project Overview Scope of work Procurement methodology Integration with partner labs Organization and staffing CM interconnect characteristics CM interconnect schedule CM interconnect risks and prior reviews This review

Fermilab cryomodules: lead-in to LCLS-II Use existing designs to extent possible to optimize cost and schedule -LCLS-II SRF linac closely based on EuXFEL / ILC / TESLA design -Similar designs have been under development ~ 20 years 100 cryomodules to be built for XFEL FNAL has been working with these designs for ~10 years in ILC context -Two 1.3 GHz cryomodules built and tested (singly): CM1 and CM2 -One 3.9 GHz cryomodule was built for DESY/FLASH; in operation FNAL responsible for the CM design, in collab with JLab & SLAC Procurement/fabrication/assembly/test shared by FNAL and JLab  Cooperation and assistance from DESY/XFEL and CEA Saclay extremely beneficial Ginsburg - LCLS-II CM Interconnect FDR, 29 July

LCLS-II cryomodule production model 1.3 GHz cryomodules (35) Produce two streams of identical 1.3 GHz production CM at FNAL&JLab -Tightly coordinated activity among partner labs -Common procedures, common test performance database, common travelers, etc. (within infrastructure limits) -Split procurements between the two labs Assemble two prototypes in advance of 33 production cryomodules -Prototype designs optimized to use existing components to confirm as many design concepts as possible, on a rapid schedule -Design, engineering development, R&D, core staff training, and infrastructure updates are completed with the prototypes Test cryomodules prior to delivery to SLAC, including prototypes 3.9 GHz cryomodules (2) Designed, produced and tested at FNAL, following 1.3 GHz for efficiency Ginsburg - LCLS-II CM Interconnect FDR, 29 July

5 LCLS-II 1.3 GHz cryomodule procurement model Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015 Procurements distributed JLab/FNAL Deliveries split between JLab/FNAL Documented LCLSII-4.1-PM-229-R0 6/12/2014 Using JLab SOTR framework One assigned at each lab Direct communication

6 Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015 Sub-Contracting Officer’s Technical Representative (SOTR) Important Role / Responsibility “Glue” between design, prototyping, procurement and assembly phases Technical expertise for sub-system components Design Phase Develops technical specifications from higher level requirements Prepares drawings and supporting technical documents Prototyping Phase Works with Acquisition/Procurement to procure prototypes from industry/partner labs Participates in prototype development and testing Feeds forward experience into production process Production Procurement Phase Provides technical leadership and point of contact with suppliers Inspection/Assembly/Integration Provides sustaining engineering during receiving inspection & manufacturing Technical judgment to resolve non-conformances Daly

7 QA/QC Summary Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015 Quality systems are in place at both Labs, and have proven effective in numerous past projects SLAC-specific requirements have been incorporated Completed QA Cross-Walk exercises in Nov/Dec 2014 On-going regular QA discussions between JLab and FermiLab on project QA. Both Labs are using electronic travelers, and will be collecting a common set of parameters Designs are controlled through Teamcenter Both SLAC and JLab have access Our quality systems are in use now for the pre-production Cryomodule work Thanks to Anne McEwen, Johnny Leung and Valerie Bookwalter for their help Blowers

LCLS-II cryomodule project integration Regular teleconferences JLab & SLAC personnel work closely with FNAL for design, procurement, fabrication and test of the 1.3 GHz cryomodules Documentation Physics Requirements Documents Functional Requirements Specification Engineering Specification Documents Interface Controls Documents Reviews All include safety in the charge Safety and quality assurance are incorporated into all procurements and assembly travelers Ginsburg - LCLS-II CM Interconnect FDR, 29 July

FNAL LCLS-II 1.3 GHz cryomodule team Cryomodule CAM Camille Ginsburg Test Facilities VTS - Melnychuk HTS - Hanna/Ozelis CMTS - Leibfritz pCM Technical Coordination – Genfa Wu Managers & Support Solyak – Accelerator Science Grassellino – High Q0 Theilacker – Project Engineer Hoffer – Controls/Schedule Trimby – Budget Cibic – Procurement Blowers – QA/QC Design Verification Nikolay Solyak CM Design Tom Peterson Cavity Prep/Test Allan Rowe CM Ass’y Tug Arkan CM Test Elvin Harms FNAL Senior Team Lead Rich Stanek Ginsburg - LCLS-II CM Interconnect FDR, 29 July

10 CM Interconnect Overview Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015  A bellows interconnect installed between two modules  Outer shell of the inter-connect unit can slide over the vacuum vessel to allow space for welding of six cryogenic pipes in-situ  Mechanically decouples adjacent CM’s and allows for thermal contraction or expansion during thermal cycling  33 interconnects are needed for the 37 CM’s in the LCLS-II configuration Yun He

CM interconnect parts list Ginsburg - LCLS-II CM Interconnect FDR, 29 July Upstream module Downstream module Inter-module kit Vacuum vessel inter-module bellows unit, F Thermal shield, F & F HGRP, F Bellows spools for cryogenic pipes (Qty. 5), F HOM absorber, F MLI blankets (10 layers to 5 K, 30 layers to 50 K) Gaskets, fasteners Yun He

12 CM Interconnect Responsibilities Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015  JLab and FNAL are jointly responsible for procurement of the parts  SOTR for absorber  H.K. Park (JLab, primary), N. Solyak (FNAL, secondary)  SOTR for remaining interconnect parts  T. Peterson (FNAL, primary), N. Huque (JLab, secondary)  The interconnect kit comprised of these parts is delivered to SLAC  SLAC is responsible for installation in the LCLS-II tunnel  DESY/XFEL providing installation guidance  JLab and FNAL also provide installation guidance

Cryogenic Systems Schedule Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015 FNAL CM Assembly / Test JLAB CM Assembly / Test Cryoplant CDS install CM work FY16-Q2 to FY18-Q1 CM / CDS FDR FNAL FY15-Q2/3 Ross, DOE CD3B, Apr

CM Interconnect Schedule Highlights A full P6 schedule has been developed Takes into account the CD milestones, facility throughput, lead time on procurements Working Schedule for interconnect parts (H.K. Park for HOM’s): -Today is the gating review for procurements -Award contract Nov Receive and inspect components: May 2016 – Jan Deliver to SLAC Jan 2017 – Feb The interconnect parts have a lot of schedule float Some schedule modifications will be made prior to CD-2 baselining Ginsburg - LCLS-II CM Interconnect FDR, 29 July

Past Reviews Related to the CM Interconnect LCLS-II Director’s CD-1 Review – 9-11.Dec LCLS-II DOE CD-1 Review – 4-6.Feb  Prototype 1.3 GHz Cryomodule – 6.Jun CM cryomechanical issues LCLS-II Cryogenic System Preliminary Design Review Aug LCLS-II DOE Status Review – Aug.2014  Prototype 1.3 GHz cryomodule Jan – Final Design LCLS-II FAC Review at SLAC 5-6.Feb.2015 LCLS-II Director’s CD3B Review at SLAC Feb.2015 LCLS-II DOE CD3B Review at SLAC 6-9.Apr GHz Production CM Final Design Review May  No recommendations of relevance to this review Ginsburg - LCLS-II CM Interconnect FDR, 29 July

FNAL CM Interconnect Risks (in Risk Registry) 16 Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015  None

17 LCLS-II CM Interconnect FDR Committee Charge Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015 Evaluate CM interconnect design readiness to approve implementation, procurement, fabrication & installation activities. 1.Technical Scope a)Are the design, conceptual procedures and intended fixtures technically sound and mature enough to satisfy design requirements and installation concepts ?TP, YH, NS, KF b)Is the design likely to meet performance expectations? TP, YH, NS c)Have installation issues been sufficiently addressed to ensure that interconnect procurements may proceed and that there are no show stoppers? KF d)Have all the major interfaces been identified and incorporated into the design as appropriate? TP e)Are all design specs, reqts, performance, & interface documents sufficiently identified and prepared? TP 2.Design Management a)Is the design team organized and staffed to successfully complete the project? CMG b)Have all of the major risks been identified and managed? CMG c)Are procurements appropriately identified? CMG, JP d)Is the development of the 3D model sufficiently mature? TP 3.Schedule: Is interconnect design & procurement schedule reasonable to meet project requirements? CMG 4.ES&H: Are all related ES&H aspects being properly addressed? TP 5.Miscellaneous:. Are there any other issues that have been identified that need to be addressed? CMG(b) 6.Overall Readiness: Is the design sufficiently mature so as to allow Final Design Review (i.e. ~90-100% design maturity) approval? All

Design Review Definitions (LCLSII-1.1-QA-0009-R0) Preliminary Design Review [~30-50% Design Maturity] Documented technical and interface requirements Mechanical/structural/thermal design and analyses Preliminary layouts, drawings Reliability, maintainability Assessment of risk areas Plan for obtaining safety approval Final Design Review [~90-100% Design Maturity] Requirements of PDR plus… Final detailed design Final implementation plans including engineering models, prototypes and spares Engineering model test results and design margins Readiness Review Needed for authorization prior to construction activities Objectives, documentation, QA, safety, residual risk 18 Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015

19 Review agenda Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015 Welcome and introductions – Ross/Ginsburg Cryomodule (CM) interconnect design project management – Ginsburg/Preble CM Design Overview and Interconnect Requirements - Peterson Cryomodule interconnect design –Yun He HOM Absorber Design – Solyak HOM Absorber Procurement – HyeKyoung Park Installation Guidance from DESY/XFEL – Karen Fant Any accumulated issues – Ginsburg (for the Team)

Conclusions CM interconnect design is mature Heavily based on existing designs [Peterson, He, Solyak] Staff available and working Project plan derived from experience  Thanks in advance for your help; we anticipate a productive review Ginsburg - LCLS-II CM Interconnect FDR, 29 July

21 Backup Slides Ginsburg - LCLS-II CM Interconnect FDR, 29 July 2015

22 The Cryogenic System Production Cryomodule Final Design Review, 12 May 2015 Figure from LCLS-II-4.9-EN-0300 (ED ) LCLS-II CDS Relief System Analysis