17.01.05Commissioning Strategy - Chamonix 20051 LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Injection test? Mike Lamont For initial discussion.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
1 Luminosity monitor and LHC operation H. Burkhardt AB/ABP, TAN integration workshop, 10/3/2006 Thanks for discussions and input from Enrico Bravin, Ralph.
Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April.
LHC Application Software1 Beam Commissioning: Required Applications 23 / 01 / 2006 Mike Lamont.
LHC Utilities & Facilities WAO Daejeong 12/04 – 16/04/2010 Markus Albert on behalf of LHC Operations.
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
1 Beam Plans for Accelerator Systems: The Machine Protection System Jan Uythoven On behalf of the MPWG and the MPS Commissioning WG Special thanks to R.Schmidt,
LHC progress Report LHCC Wednesday 23 rd March 2011.
R.Bailey, March 2008 Beam plans for Accelerator Systems R.Bailey, F.Zimmermann eLTC Summary March 2008.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
Ramping & Snapback Andy Butterworth AB/RF Chamonix XIV 17 January 2005.
LHC Sector Test 1 Roger Bailey, Helmut Burkhardt, Paul Collier, Brennan Goddard, Stephen Jackson, Lars Jensen, Rhodri Jones, Verena Kain, Alex.
Schedule IT General Schedule 9 th, September 09 Today.
LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
LHC Commissioning Phases Phase A GeV, Increasing the Beam Intensity presented by Jan Uythoven on behalf of the LHCCWG Particular thanks to Laurette.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
1 Machine Checkout and Setup Periods Jan Uythoven Thanks to: O.Aberle, R.Bailey, F.Bordry, O.Brunner, L.Bottura, E.Carlier, P.Charrue, E.Ciapala, S.Claudet,
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
R.Bailey, Chamonix XV, February 2006 Staged commissioning plan for protons Hardware commissioning Machine checkout Beam commissioning 43 bunch operation.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
HiRadMat Summary of Phase-I and plans for Phase-II commissioning J. Blanco, N. Conan, V. Kain, K. Cornelis, B. Goddard, C. Hessler, M. Meddahi, C. Theis,
LHC commissioning and interaction with the experiments
LHC Commissioning with Beam
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
LHC schedule.
The LHC - Status Is COLD Is almost fully commissioned
Mike Lamont on behalf of the LSA team
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Machine plans - Alignment workshop
Initial Experience with the Machine Protection System for LHC
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
LHC Commissioning Phases
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Lost at 12:05 to power converter (RTQX2.R1) problem
Wire almost entirely through beam before BLM triggers dump
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
Summary Thursday h21: Stable beams fill #1303.
Machine plans - CMS startup workshop
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
The LHC Beam Interlock System
Summary for LPC (March 7th, Ralph Assmann)
Summary Tuesday h23: Machine closed. Precycle started.
Another Immortal Fill….
Beam commissioning plans, 2007 and 2008
Review of hardware commissioning
Feedbacks & Stabilization Getting them going
HI2011 Commissioning Status
Presentation transcript:

Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.

Commissioning Strategy - Chamonix – LEP commissioning 14th July: First beam14th July: First beam 23rd July: Circulating beam23rd July: Circulating beam 4th August: 45 GeV4th August: 45 GeV 13th August:Colliding beams13th August:Colliding beams

Commissioning Strategy - Chamonix 20053

Commissioning Strategy - Chamonix Motivation - TI8 Beam down – first shot.Beam down – first shot. Full set of measurementsFull set of measurements optics, aperture etc. What does this tell us? Lionel Mestre Yu-Chiu Chao

Commissioning Strategy - Chamonix TI8 INSTALLATIONINSTALLATION HARDWARE COMMISSIONINGHARDWARE COMMISSIONING Survey Technical services Vacuum Equipment MACHINE CHECKOUTMACHINE CHECKOUT Preparation of incoming beam Controls Beam Optics/Energy Instrumentation Settings Interlocks & Machine protection Access Radiation monitoring Tells us that quite a few things were done right Volker Mertens and team

Commissioning Strategy - Chamonix TI8 OBJECTIVESOBJECTIVES PREPARATIONPREPARATION PLANNINGPLANNING STAGINGSTAGING BEAM: extraction tests 2003 PRACTICEPRACTICE Dry runs BEAM: CNGS extraction 2004 Important for debugging Important as milestones

Commissioning Strategy - Chamonix LHC Beam Commissioning OBJECTIVESOBJECTIVES PREPARATIONPREPARATION PLANNINGPLANNING KEEP IT SIMPLEKEEP IT SIMPLE PHASE ITPHASE IT KEEP IT SAFEKEEP IT SAFE

Commissioning Strategy - Chamonix Objectives Establish colliding beams as quickly as possibleEstablish colliding beams as quickly as possible SafelySafely Without compromising further progressWithout compromising further progress Commissioning the LHC with beam - Stage One Take two moderate intensity multi-bunch beams to high energy and collide them.

Commissioning Strategy - Chamonix More Specifically No parasitic encountersNo parasitic encounters No crossing angle No long range beam Larger aperture InstrumentationInstrumentation Good beam for RF, Vacuum…Good beam for RF, Vacuum… Lower energy densitiesLower energy densities Reduced demands on beam dump system Collimation Machine protection LuminosityLuminosity cm -2 s -1 at 18 m 2 x cm -2 s -1 at 1 m 43 on 43 with 3 to 4 x ppb to 7 TeV

Commissioning Strategy - Chamonix and in the process CommissionCommission the Equipment the Instrumentation the Machine protection system to the levels required. Looking for an efficient commissioning path to get us to the above objectives Stage two definition to follow

Commissioning Strategy - Chamonix Clear aim to commission/fix/test everything that can be: before beam. Preparation

Commissioning Strategy - Chamonix EXIT HWC LHC ? EXIT CHECKOUT EXIT TI8/TI2

Commissioning Strategy - Chamonix Exit HWC - 1 Implicitly:Implicitly: Beam Vacuum [warm & cold] Cooling and Ventilation Cryogenics Plant Cryostat Instrumentation Electrical Network Insulation Vacuum Powering Interlock QRL Instrumentation QRL Vacuum Radiation Monitors Software Interlock System Access Survey/Alignment Given installation, technical infrastructure etc. etc. Monitoring, logging, display, PM, Diagnostics Control applications Coupling between systems Recovery procedures from CCR clearly defined etc. etc. MOVE FROM HWC MODE TO OPERATION MODE

Commissioning Strategy - Chamonix Exit HWC - II All magnet circuits [warm & cold]All magnet circuits [warm & cold] Power convertersPower converters Kickers, SeptaKickers, Septa Collimators, AbsorbersCollimators, Absorbers Beam dumpsBeam dumps RFRF Power systems, low level, cavities, TFB InstrumentationInstrumentation Machine protectionMachine protection QPS, Energy Extraction, Power Interlock Controllers ControlsControls

Commissioning Strategy - Chamonix Machine checkout By OperationsBy Operations With support of equipment specialists, HWC team etc.With support of equipment specialists, HWC team etc. From the PCRFrom the PCR Drive all relevant systems in a synchronized way through the complete operational sequence This where operations get serious

Commissioning Strategy - Chamonix

Commissioning Strategy - Chamonix Exit machine checkout - 1 RFRF Pre-pulses, low level control [cavity control, synchro, beam control, longitudinal damper], transverse damper, power systems. Diagnostics. Synchronisation with injectors Power convertersPower converters tracking control, ramping, squeezing, real-time Kickers, septa,Kickers, septa, Collimators, absorbersCollimators, absorbers Dump:Dump: timing, post-mortem, inject and dump Beam InstrumentationBeam Instrumentation pre-commission, timing, acquisition tests, interface to control system

Commissioning Strategy - Chamonix Exit Machine Checkout - 2 Interlocks & Machine ProtectionInterlocks & Machine Protection Equipment interfaces, links, logic, controls, PIC, WIC, BIC, Safe Beam Flags Software interlocks QPS, Energy extraction displays, diagnostics, post-mortem, recovery Energy meter

Commissioning Strategy - Chamonix Exit Machine Checkout - 3 Controls:Controls: Slow timing, fast timing, synchronisation Alarms, logging, post mortem, fixed displays Equipment control & access Analogue acquisition Software: measurements, trajectory acquisition and correction, ramping etc. etc. Controls infrastructure: servers, databases etc. Sequencer, injection management Procedures for sliding bumps etc. etc.

Commissioning Strategy - Chamonix Exit Machine Checkout - 4 Settings etc.Settings etc. calibrations, optics, transfer functions, ramp, squeeze… Radiation monitoringRadiation monitoring Access systemAccess system INB, EIS Operation ExperimentsExperiments Data interchange Beam aborts

Commissioning Strategy - Chamonix Exit injectors and transfer lines SPS LHC cycleSPS LHC cycle All requisite beams available Beam quality Delivered when required TI8 & TI2TI8 & TI2 Fully qualified LHC pilot beams to final TED

Commissioning Strategy - Chamonix Pre-beam: Magnets Errors: all circuits, full cycleErrors: all circuits, full cycle geometric, beam screen, saturation eddy, RMS/Persistent currents static model powering history dependent model on-line reference magnets Cycle path – all magnetsCycle path – all magnets Transfer functionsTransfer functions for all magnet circuits hysteresis behaviour for corrector circuits where appropriate Strategy for:Strategy for: excitation of nested correctors cycling nested pc/magnets MCS b1pM_MBRS := ; b1gM_MBRS := ; b2pM_MBRS := ; b2gM_MBRS := ; b3pM_MBRS := ; b3gM_MBRS := ;

Commissioning Strategy - Chamonix Planning: with beam 1Injection 2 First turn 3 Circulating beam GeV: initial commissioning GeV: detailed measurements GeV: 2 beams 7 Nominal cycle 8 Snapback – single beam 9 Ramp – single beam 10 Single beam to physics energy 11 Two beams to physics energy 12Physics 13 Commission squeeze 14 Physics partially squeezed

Commissioning Strategy - Chamonix Beam Pilot Beam:Pilot Beam: Single bunch, 5 to 10 x 10 9 protons Possibly reduced emittance Intermediate single:Intermediate single: 3 to 4 x ppb 4 bunches etc. pushing towards…4 bunches etc. pushing towards… 43 bunches43 bunches 3 to 4 x ppb Will stepping up & down in intensity/number of bunches through the phases

Commissioning Strategy - Chamonix

Commissioning Strategy - Chamonix

Commissioning Strategy - Chamonix

Commissioning Strategy - Chamonix At each phase: Equipment commissioning with beamEquipment commissioning with beam Instrumentation commissioningInstrumentation commissioning Checks with beamChecks with beam BPM Polarity, corrector polarity, BPM response Machine protectionMachine protection Beam measurementsBeam measurements beam parameter adjustment, energy, linear optics checks, aperture etc. etc.

Commissioning Strategy - Chamonix Instrumentation – the essentials First turn i.e. immediatelyFirst turn i.e. immediately Screens, BPMs, fast BCT, BLMs Circulating beams at 450 GeVCirculating beams at 450 GeV BPMs, DC BCT & lifetime, BLMs Transverse diagnostics Emittance: wire scanners.. Snapback and RampSnapback and Ramp Chromaticity, PLL Orbit BLMs to BIC etc. Essential. See Hermann & Barbara’s talks

Commissioning Strategy - Chamonix Machine protection Need a well defined plan for the commissioning and integration of the Machine Protection System

Commissioning Strategy - Chamonix Misc - How long? PhaseR1/2 Time [days] Total 1Injection212 2 First turn Circulating beam GeV: initial commissioning GeV: detailed measurements GeV: 2 beams Nominal cycle Snapback – single beam Ramp – single beam Single beam to physics energy Two beams to physics energy Establish Physics Commission squeeze Physics partially squeezed TOTAL 60

Commissioning Strategy - Chamonix Sector Test Rigorous check of ongoing installation and hardware commissioningRigorous check of ongoing installation and hardware commissioning Pre-commission essential acquisition and correction procedures.Pre-commission essential acquisition and correction procedures. Commission injection system: Commission Beam Loss Monitor system Commission trajectory acquisition and correction. Linear optics checks: Mechanical aperture checks. Field quality checks. Test the controls and correction procedures Hardware exposure to beam will allow first reality checks of assumptions of quench limits etc.Hardware exposure to beam will allow first reality checks of assumptions of quench limits etc.

Commissioning Strategy - Chamonix Parallelism? System tests with HWC ongoingSystem tests with HWC ongoing Machine protection Controls RF/Injection/Collimators etc. Machine checkout with HWC ongoingMachine checkout with HWC ongoing Sign over completed sectors to OP TI2 commissioning – LHC with beam 2TI2 commissioning – LHC with beam 2 HWC – partial LHC with beam 2HWC – partial LHC with beam 2 Implications: dump, radiation protection, access, resources, support etc. LHC - partial beam 1 with beam 2LHC - partial beam 1 with beam 2 Options need examining

Commissioning Strategy - Chamonix CONCLUSIONS OBJECTIVESOBJECTIVES Stage 1 PLANNINGPLANNING Before beam Stage 1 PREPARATIONPREPARATION