LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 1/17 LARP Phase II Secondary Collimator RC-1 Collimator Development Status and Outlook Revised.

Slides:



Advertisements
Similar presentations
BARTOSZEK ENGINEERING 1 The Design of the Booster Collimators Larry Bartoszek BARTOSZEK ENGINEERING 3/10/03.
Advertisements

RF Cavity Module G. Gosling Dept. of Mechanical Engineering Imperial College London.
Coll Eng E Doyle 1/18 LARP Phase II Secondary Collimator RC1 Prototype Engineering Status 6/21/06 Jaw-hub-shaft concept - continued Permanent.
4m Undulator Design Concepts Amanda J Brummitt CCLRC RAL On behalf of the HeLiCal Collaboration.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
Update on Be Wall Cavity Steve Virostek Lawrence Berkeley National Lab MTA RF Workshop November 15, 2010.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
SLAC rotating collimator for HiRadMat beam tests 14 March 2014 S. Redaelli, A. Bertarelli, CERN T. Markiewicz, SLAC US LHC Accelerator Research Program.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes now twist, under vacuum, as jaws turn, with R~1.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
ENGINEERING DESIGN AND FABRICATION OF PETS V. Soldatov¹, D. Gudkov¹, I. Syratchev², A. Samoshkin¹, G. Riddone², A. Olyunin¹, S. Atieh² 1 – JINR, Dubna,
A. Bertarelli – A. DallocchioLHC Collimation Phase II – Specification Meeting – 7/11/2008 Phase II Collimators: design status, options and future outlook.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes now twist, under vacuum, as jaws turn, with R~1.
MECHANICAL DESIGN OF TCSP COLLIMATORS Secondary Collimators Embedding BPMs L. GENTINI, A. Dallocchio, A. Bertarelli, F. Carra, M. Garlasche.
LHC Phase II Collimator teleconference - 4 March 2008LHC Rotatable Phase II Collimators 1 beam LARP Phase II collimator Progress and Plans 4 March 2008.
Introduction to collimators Integration of BPM Mechanical design Electrical design Processing Simulations Results Conclusions & Outlook.
1 LARP Phase II Secondary Rotatable Collimator Evolution of design changes 3 rd March, 2010.
Engineering Department ENEN Status of TCSP manufacturing Collimation Working Group (CWG) 24 June 2013 A. Dallocchio, A. Bertarelli, F. Carra, L. Gentini,
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 16 May 2006 No 1 /22 LARP Phase II Secondary Collimator RC1 Collimator Test Program Revised 5/15/06.
SLAC RC Status Report 30 August 2010 LHC Collimation Working Group Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
SLAC R&D Mtg November 2007LHC Rotatable Phase II CollimatorsSlide # / 17 beam LARP Rotatable Collimators for LHC Phase II Collimation 12 November.
LARP LHC PHASE II COLL RC1 - S. Lundgren 1 April 2009 No 1 /6n LARP Phase II Secondary Collimator RC-1 Mechanical Design Review 01/04/09.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
Task List for Phase II Rotatable Collimator Project at SLAC 30 January 2007 CERN/LARP Video Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Collimation Overview 28 October 2008 LARP CM11, Fermilab Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program 1)Short Status.
LARP LHC PHASE II SECONDARY COLLIMATOR CD1 REVIEW. - E. Doyle 15 Dec /25 LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 Prototype Engineering.
LHC Collimators Phase 2 - Visit to Plansee 28th August Materials for Phase II collimators.
7-Sep-2011 CLIC RF Structure Development Meeting «BE/RF» TD26 WITH COMPACT COUPLER FOR CLEX (TD26 CC SiC) ENGINEERING DESIGN this structure will be used.
LARP Rotatable Collimators for LHC Phase II Collimation 09 July 2007 SLAC R&D Status Meeting Gene Anzalone, Eric Doyle, Lew Keller, Steve Lundgren, & Tom.
LARP Rotatable Collimators 19 June 2006 ILC R&D Status Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 10 Dec 2007 No 1 /12 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
PXIE RFQ Engineering Design Steve Virostek Engineering Division Lawrence Berkeley National Laboratory April 10, 2012 Project X Collaboration
1 SLAC RC Status Report 19 July 2010 LHC Collimation Working Group Meeting Jeff Smith/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
LARP Phase II Secondary Collimator Status Report SLAC ILC R&D Summary Meeting 24 April 2006 T. Markiewicz/SLAC.
LCWS11 WG4 Fully featured accelerating structure engineering design
LARP Phase II Secondary Collimator RC1
Complementary ISTC Projects #3888, 3889p
Wideband kickers Mechanical design and Fabrication
Review on collimator movement with stepping motors
Impact of TIDVG problem on LSS5 dump design schedule
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1
Preliminary Y-chamber specifications – First draft
LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 RC1 Construction and Test Plan LARP LHC PHASE II COLL REVIEW – RC1.
EBTF Design Review Technical Meeting Group
LARP Phase II Secondary Collimator RC-1
Review on collimator movement with stepping motors
Recommendations of 12/16/05 review committee & SLAC response
23 April 2012 Tom Markiewicz/SLAC
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Rotatable Collimator
LARP Phase II Secondary Rotatable Collimator
LARP Phase II Secondary Rotatable Collimator
LARP Phase II Secondary Collimator RC-1
LARP Phase II Secondary Collimator RC-1
LARP Phase II Secondary Collimator RC-0 and RC-1
LARP Rotatable Collimators for LHC Phase II Collimation
LARP Phase II Secondary Collimator RC-1
LARP Phase II Secondary Collimator RC-0 and RC-1
Presentation transcript:

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 1/17 LARP Phase II Secondary Collimator RC-1 Collimator Development Status and Outlook Revised 09/21/09 DRAFT

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 2/17 Outline Strategy for Prototype Tests Overview of SLAC design Fabrication update Outlook

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 3/17 Strategy for Prototype Tests Original Plan –Full mechanical prototype “robustness tested” in TT60 –Final version prototype incorporating “lessons learned” in LHC Current plan –Full mechanical prototype with BPMs tested in SPS After off-beamline mechanical, RF & vacuum tests at SLAC & CERN –A robustness test, either in TT60 An “ad-hoc” site to-be-determined if TT60 availability too late relative to a future decision on the desired timeline for technology choices, fabrication and installation of either: The RC-SPS device An “ad-hoc” device: details yet to be determined –No LHC prototype test although a 3 rd generation RC may be constructed

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 4 /17 Mechanical Engineering Decisions Based on Desired Strategy If TT60 Test first: –Vacuum tank cylinder with domed ends attached with conflat flanges for easy access for later examination of beam-induced damage ports for laser micrometers, cameras and TBD instrumentation high vacuum not important –Use RC0 jaw & RC1 jaw as quickest, most economical path forward New jaws, new tank for an LHC prototype For SPS Test first –Shorter domes welded to main tank transitioning to 2-axis BPM assemblies Flange-to-flange length same as for LHC BPM strategy being discussed with experts in a separate loop –Main tank diameter sized for SPS 60mm jaw opening –BPM flanges currently seen as ROUND with 60mm ID –Orientation of jaws and aperture requirements needed now to proceed 60mm x 80mm has been mentioned as a possible requirement

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 5 /17 Consequences If SPS device used for TT60-like test –need to be able to handle device after exposure to SPS beam –tests need to be sequential –must build in enough diagnostic capability to SPS device now –must buy in to grinding off tank from base plate to gain access to jaws for eventual examination after TT60 cooldown If a separate TT60 device is called for –Is this a simple “burn copper” test or are final-design jaws and supports required? –If final-design jaws required need to know asap to begin fabrication of two more jaws would still make sense to use RC0 as the “witness” jaw to that being hit by the TT60 beam and build a second “RC1” style jaw for the SPS test device Ideally would like to reserve “spare materials” for a final lessons-learned third generation design that might include a simplified (non-molybdenum) support scheme

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 6 /17 SLAC design details Ratchet Gear Drive End Support Ratchet Drive mounts here as well Tank geometry allows a 60mm facet-to-facet gap in fully retracted Jaw position BPM assemblies at each end are fiducialized to Collimator 2 or 4 buttons of LHC IR7 Style External Cooling circuits

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 7 /17 Design Details BPMs planned for each end of Tank –CERN Button Feedthroughs (LHCBPM_F0023) could be used and standard LHC BPM processing electronics can be used. –Fiducialization with jaw surfaces should not be a problem –Aperture could limit test/establish Jaw orientation. If needed we could provide ~84mm x 60.5 aperture But.. need to know soon. Two jaws: The original Heater Test Jaw and a new Prototype Jaw ( now under construction) Maximum Jaw separation increased to 60mm Ferrites for HOM damping –Simulations in progress to define ferrite details, previous studies suggest HOM damping will be needed –Verify with bench –Ferrites could be added on base plate under Jaw then a re-test done

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 8/17 SPS (not TT60) Test config. 1480mm Use CERN parts and locations CERN Flange Collimator orientation as shown with CERN agreement BPMs will prevent simple Jaw removal previously planned

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 9 /17 Materials and Parts Already In-House (or nearly so) “RC-0” jaw used for EPAC’08 thermal tests with resistive heater –Two Moly half-shafts and half-hubs modifications required at ends to mount to current stainless jaw supports –OFE copper jaw material, with 20 facets Groove cut in one facet for heater blocks –brazed from 16 ¼-round blocks Facet surface finish and flatness “good”, but expect better in next iterations “RC-1” jaw in fabrication (see later slides and photos) –One piece shaft assembly –Jaws from 5 fully-round Glidcop cylinders Two more grooved OFE Copper mandrels identical to that used in RC-1 Enough raw Glidcop material to make two more full length jaws

Mandrel Machining and Winding completed Machined 3 Mandrels Wound 1 Mandrel LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 10/17

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 11/17 Cooling tube to Mandrel braze completed Braze prep. Brazing results: looks good

End Supports/hardware completed A-286 SST Supports for 2 Jaws Concept view of “appropriately” flexible Support shown with Shaft mounting hardware Cooling tube exits here Ceramic bearings roll in “V” groove created by the 2 45 degree chamfers on these parts LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 12/17

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 13 /17 More Parts are real! Actual Rotator parts now exist Rotator life cycle test to begin soon 5 Jaw Cylinders are rougher out

Image Current Foil Assembly simplified Cone extended the foil to beam pipe flange Height needed to shadow the Gear Drive on top of Jaw End Support Cone deleted (foil deemed far enough from beam to show little effect) Moved Rotator from top of Support so foil height could be minimized No Brazing Required! Mounts to Tank here Mounts to RF bearing here Mounts to beam pipe flange here LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 14 /17

Current housing concept for BPMs DN 150 Rotatable CF flange allows for BPM alignment with Jaw DN 100 Chain clamp flange Current plans are for 60.5mm diameter geometry for saddle-cut BPM buttons Could reconfigure housing for 2 rather than 4 buttons to increase inside dimension shown Increase this dim. if needed and eliminate 2 BPM buttons LHC IR7 Button LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 15/17 BPM target resolution is 25 microns with Jaw to BPM fiducialization on the order of of a few microns

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 16 /17 SPS Test Plan Goals Demonstrate mechanical operation of device in an active machine environment. Demonstrate ability to align jaws with BPMs Measure impedance characteristics of full device, both broad-band and trapped modes. Similar to phase I graphite SPS tests

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 17/17 Outlook Project Milestones are being established to guide completion of Prototype Collimator for late 2010 SPS Installation –Collimator set is planned for preliminary SLAC testing starting January 2010 –Shipment to CERN by August 2010 Key steps requiring careful coordination to complete first MS are: –Machining of Brazed Mandrel (started last week) –Brazing on the Glidcop Jaws (due back at SLAC mid October) –Final Facet machining (at same vendor, later)