DFW Connector Project Main Street Bridge Starting in March 2010 Subject to Change
PHASE 1A The project consists of 7 total phases 1a thru 3b Phase 1a Begins on the east end of the project early 2010, west end begins mid 2010 Phase duration approximately 550 days Many stages within phase 1a Major areas of work include: - West end: FM 1709 – SH 26 - TX 121 SB & NB widenings - Managed lanes: Texan Trail – International Pkwy - North east frontage roads - Main Street bridge
Main Street Bridge Work commences March 2010 with asbestos abatement NORTHGATE COLOR SCHEME for following maps: BLUE = DETOUR CNST YELLOW = CURRENT CNST ORANGE = PREVIOUS CNST
4 CONCEPTUAL PHASING
5
6
7
8
9
DFW Connector Traffic Management Goals of MOT team Maintain mobility Cooperation with stakeholders Safe construction zone Emergency / incident management Contacts Emergency assist Location (mile) markers Emergency pullouts Courtesy patrol