12/2/2015S.Miscetti - ROMA11 S.Miscetti Laboratori Nazionali di Frascati Mu2e Italian Meeting 12/2/2015 University La Sapienza, Roma.

Slides:



Advertisements
Similar presentations
Conference Title L. Stringhetti, IASF Milano, ASTRI Meeting #9, Bologna 24 Feb Status of the ASTRI/CTA project and organization/management issues.
Advertisements

OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
Homework Questions for eRD1 EIC R&D Committee Meeting January 23, What are the concrete plans of eRD1 for the next two years? What are the deliverables.
Doug Michael Jan. 12, First goal is to be ready to select an optimal technology in ~one year. –Demonstrate that fundamental technologies are ready.
Interfaces with the SNS Project for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown Aug.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Mu2e Mu2e Status Andy Hocker, Technical Division All-Experimenters Meeting 8-JUN-2015.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Research & Technology Implementation TxDOT RTI OFFICE.
Mu2e WGM R. Ray Mu2e Project Manager Sept. 14, 2012.
Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Norman McCubbin1 Report from the Collaboration MICE Project Board (CMPB) Norman McCubbin Director, Particle Physics Department MICE/UKNF Oversight Committee.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
Compliance Monitoring and Enforcement Audit Program - The Audit Process.
Workshop Objectives & Highlights from Daresbury Meeting Erk Jensen, CERN.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
MICE CMPB Alain Blondel 1 Highlights on MICE.
TSG-S OMA (Open Mobile Alliance) Ad-Hoc Report Richard Robinson Chair - 3GPP2 TSG-S SC B_Eshwar Pittampalli’s (Lucent) comments/concerns embedded.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
CMS 1.Goal of the experiment CMS is a general purpose apparatus for LHC designed to study the physics of p-p collisions at the center-of- mass energy of.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
Development Project Management Jim Kowalkowski. Outline Planning and managing software development – Definitions – Organizing schedule and work (overall.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Workshop summary Outline  Workshop’s aims  Highlights from the presentations (my selection!)  Costing Exercise – What we learnt  Summary - Roadmap.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
QCG Report Francesco Forti University and INFN, Pisa.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
CERN Neutrino platform 24 th July, 2014 S. Bertolucci CERN.
DOE Mini-Review Summary and Management Updates Mark Palmer Fermilab March 15, 2013.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
OFFICE OF SCIENCE DOE/SC CD-2/3b Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory February 4,
OFFICE OF SCIENCE DOE/SC CD-3c Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory June 14-16, 2016.
Director’s Progress Review Closeout Meeting
IFR Detector R&D status
Physics and Calorimeter Requirements
Jim Fast Pacific Northwest National Laboratory
Mu2e crystals qualification
Status of the MICE Construction Project
Ti/SS transitions A.Basti INFN-PISA*
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
Claudia Cecchi University of Perugia and INFN
Spoke CDS PDR Closeout J. G. Weisend II June 10, 2016.
GE alternative and outcome
Report on Working Group # 2 The MU2E detector
CMS Goal of the experiment
Director’s Progress Review Closeout Meeting
NSS Instrument Project Tollgate Coordinator
Preliminary Project Execution Plan
Scene setter European Commission DG Environment
Detector Proto-Technical board Sep 30, 2010
Presentation transcript:

12/2/2015S.Miscetti - ROMA11 S.Miscetti Laboratori Nazionali di Frascati Mu2e Italian Meeting 12/2/2015 University La Sapienza, Roma

12/2/2015S.Miscetti - ROMA12 Mu2e Collaboration Mu2e Collaboration 2013 ~185 Collaborators, 32 Institutions, 3 Countries Still growing. Discussion with several USA university groups. 2 UK groups joining: UCL(M.Lancaster), Liverpool(T.Bowcock) Dresda joining (A.Ferrari) Expected completion of EU groups April CM

Mu2e Schedule and plans 12/2/2015S.Miscetti - ROMA13 CD2/3b REVIEW DONE last November CD2-CD3b follow-up completed  Recommendation for Cost and Schedule  CD3b follow up to decide the startup for the TS bid Transport Solenoid prototype done from ASG (Genova) FNAL now used for the preparation of technical documentation for final CD2/CD3b review  See Pasquale Vice President will FNAL end of the month for discussing INFN involvement in Neutrino. In the same occasion we are organizing a visit to Mu2e experiment. MoA for cable measurement betwenn INFN and Mu2e ready Construction of tunnel bringing beam to Mu2e underway

Review Closeout: TS solenoid 12/2/2015S.Miscetti - ROMA14

Review Closeout: TS solenoid 12/2/2015S.Miscetti - ROMA15 So far so good. See Pasquale’s Presentation So far so good. see Pasquale’s presentation

Review Closeout: COST & SCHEDULE 12/2/2015S.Miscetti - ROMA16

Review Closeout:Management 12/2/2015S.Miscetti - ROMA17 NO MORE REVIEW. Just adding documentation for TS prototype test and “change request”. Expect to get it soon.

Civil work … 12/2/2015S.Miscetti - ROMA18

Civil work … 12/2/2015S.Miscetti - ROMA19

European Call RISE Together with g-2 (INFN), UK (Mu2e and g-2) and Dresda(Mu2e) we are preparing a call to participate on the program: Research and Innovation Staff Exchange (RISE) Call: H2020-MSCA-RISE-201 (deadline 28 April 2015) Simona is coordinating the call. Responsibility for the different work package to be discussed. Please contact Simona if you are interested. We should also prepare a “scheduled” estimate of the “man-month” presence (secondment) at FNAL during X. Assuming to get roughly months/year. If winning the call, this is the only constraint we have to respect together with milestones and deliverables. Each month corresponds to 4500 Euro. Large benefit for Travelling and lodging. FNAL will be the hosting institution. Doug will act as contact person. CAEN is the industry that can participate to the network DRESDA irradiation facility will be used as the European infrastructure for irradiation. We can held a dedicated meeting (via skype) on this in two weeks. 12/2/2015S.Miscetti - ROMA110

EMC Next steps Calorimeter next steps:  First week of April  be ready with documentation for CTS. Discussion with referees week before CSN1  General report IN COINCIDENCE with CM AT FNAL We should present:  CTS material (description of experiment, magnet+calo)  The available manpower from 2015 to 2020 (Team Composition)  BOE’s ala INFN (Cost and Schedule + Milestones)  Assign responsibility for each BOEs and listed item.  Come up with a total INFN calorimeter cost ( TS magnet is now budget free for INFN) in one specific option.  Be ready for similar cost estimate in the backup option 12/2/2015S.Miscetti - ROMA111

Technology Choice Review Possible date to be placed in the period May 5-25 ?? Decision between BaF 2 with new APDs or CsI+MPPC We are preparing the Review Committee. It will be a mixture of internal and external experts  They will judge the technique.  The TM, myself, D. Hitlin and the spokes will take the final decision after taking into consideration also the cost. I have prepared some charges to discuss with Ron and the spokes. I will before circulate them within the calorimeter group. Two Italian experts: Cesare Bini (accepted), (I.Dafinei?, S.Passaggio?) can be part of the Review committee. Presentation of material to the committee starts on April.  Committee should be formed next month.  We need to conclude our R&D. 12/2/2015S.Miscetti - ROMA112

CTS Presentation of the CTS (June)  Date still to be decided. Next week I will discuss with F. Bedeschi and G.Battistoni (the new CTS chair).  First round: presentation and loading of all material  Second round: reply to CTS questions  I need people (L3s?) backing me up for the writing, preparation of cost and schedule and check all cost estimates.  It assumes we all agree to make the calorimeter *Whatever version is decided from the TCR* 12/2/2015S.Miscetti - ROMA113

R&D: CsI and BaF 2 to be measured We will receive:  9 CsI crystals 30x30x200 mm 3 from SICCAS (as the ones already tested)  2 CsI crystals 30x30x200 nm 3 from Optomaterial (Tortoli’, Italy).  few CsI crystals from Kharkov ( 4 29x29x230 mm 3, 8 20x20x120 mm 3 ). Half of them for us, the other half for Ren Yuan Zhu.  4 BaF 2 crystals (30x30x200) mm 3 from St.Petersburg  10 new monolithic MPPC 12x12 mm 3, UV extended from Hamamatsu We should:  Measure the crystals light-output, LRU, radiation hardness  First neutron flux then Dose, for one sample of each category (Simona)  Measure their transmittance (Marco)  Determine their time resolution when coupled to MPPC/PMT (Ivano)  Radiation hardness test of MPPC is still missing. We HAVE TO DO IT.  For BaF 2, it will be important to receive few RMD APDs to test also electronics. ( We will just adapt the preamplifier but will not proceed with the design of the HV generator at 2000 V until technology choice is not completed.) 12/2/2015S.Miscetti - ROMA114

Determination of G,Idark, PDE of MPPC Since we will receive the UV improved MPPC from Hamamatsu, we need to independently test them with light at different wavelengths:  Use a mono-chromator system to send light at a given wavelength reading them out and compare with PIN diode or PMT response?  Use the new UV led from SETI when arriving …  Compare with measurement at UV light source..  Compare with measurement at photosensors’station in Pisa.. Planning for end of February? Use this occasion to develop a SIPM test for radiation hardness 12/2/2015S.Miscetti - ROMA115

Test under vacuum We should test:  Optical grease (Dow Corning 2000, Bluesil Paste 7)  Optical glue (RTV) partly procured, partly obtained from Caltech via DHL. Hardener of RTV glue evaporated during the flight? Degassing, coupling with Crystals and response under vacuum.  This is essential to estimate our related gas-load and give indication to the mechanics and to the muon beam-line experts.  A test system should be prepared 12/2/2015S.Miscetti - ROMA116

Mechanics, FEE/WF and integration After TCR we should start preparing for CD-3:  end of December 2015 Director Review,  Feb or March 2016 DOE CD-3 review. The TCR will freeze dimension and kind of crystals and kind of photo- sensors. Same freedom will remain on the MPPC size but we should freeze it soon after TCR if selected (July?) Specification of cabling, feed-through, services, Laser, shielding and grounding should be done during summer/fall in preparation for CD3. Freezing and complete design of FEE and WF is also needed. Interferences and interfaces to be fully specified. A final test of electronics under vacuum and irradiation also needed. 12/2/2015S.Miscetti - ROMA117

Conclusions The 2014 was a real tough but successful year for Mu2e:  CD-2, CD3a and CD3b reviews completed  Civil work started.. Escavation of Mu2e hall soon.  TS magnet prototype done (thx Pasquale!) but also for the calorimeter:  Completion of LYSO R&D (Test beams done, analysis/NIM in progress)  R&D of BaF 2 + RMD APD in progress  R&D of CsI+new UV extended MPPC almost done  Irradiation program started  Mechanical, FEE, WF first integration in progress Moreover from INFN  We got the approval for a participation to the experiment PLANS:  We need to get a formal approval and a clear budget envelope from CTS  We need to prepare CD-3 review. 12/2/2015S.Miscetti - ROMA118

ADDITIONAL MATERIAL 12/2/2015S.Miscetti - ROMA119

TCR possible charges …. Are the shown options able to satisfy the calorimeter requirements, i.e. are they able to provide the required energy, time and position resolutions while working under vacuum and in the radiation environment of the experiment? Have the shown photo-sensors proven to have stability of response and reliability to be considered mature enough for their procurement phase and for the following calorimeter construction? Are there any specific risks you see in the shown options? If both options look equally valid and without major risks, is there some criteria you can identify to make a final choice among them? 12/2/2015S.Miscetti - ROMA120

Cost of calorimeter system (1) 12/2/2015S.Miscetti - ROMA121 Evaluated with Euro=1.35 $, Euro=136 Yen. Yen is stable, Euro = 1.13 $  +20% for crystals.

Cost of calorimeter system (2) We have a problem here for the baseline: +20% cost due to the Euro/$ exchange rate Cost/cc is evaluated in $ from SICCAS BaF 2.. Big effort to keep it at 10 $/cc Hexagonal shape has a +20/30% increase. OK proceeding with Square. Cost/cc for CsI is better: 6 $/cc for SICCAS 8 Euro/cc for OptoMaterial. No offers for BaF 2 DOE contribution already reduced for number of crystals.. We have lost 240 crystals in the two innermost rings for the second ring. 12/2/2015S.Miscetti - ROMA122

Project talk: Charge Questions 1.Have the Project and the Laboratory responded satisfactorily to the recommendations of the previous DOE review? Yes  Recommendations to be completed prior to CD-2 fully satisfied  Recommendations for TS Modules on track for April readiness review  Good progress on Recommendations required prior to CD-3c  In particular: o EVMS fully implemented and helping to manage project o Change Control fully implemented and helping to control evolution of project o Project Office positions all filled 2/4/15R. Ray - CD-2/3b Follow-up23

Project talk: Charge Questions 2.Is the detailed design sufficiently mature and appropriately reviewed so that the project can continue, as planned, with the procurement and fabrication work that will be approved by CD-3b. YES  Detector Hall is ready to go.  TS Module Design Complete. Drawings Complete.  Successful TS Module Final Design Review  TS Module design has significant Ic margin, significant temperature margin, significant mechanical margins and demonstrated manufacturing technique.  TS Module Prototype is a fully manufactured prototype that is being used to validate design. Additional stress tests to approximate system operating conditions and confirm margins.  Acquisition strategy in place. Modeled after PS/DS strategy.  Plan to approve procurement after prototype tests defined. 2/4/15R. Ray - CD-2/3b Follow-up24