OVERVIEW Review of completed projects Update on large construction projects Update on other miscellaneous projects
COMPLETED PROJECTS Athletic Complexes $12M Mat-Su Day School $12.4M Valley Pathways $22.5M Big Lake ES Reno Ph I $2.2M Houston/Palmer Jr MS Lockers $335K Flooring Replacements Ph I $2M Palmer HS Mechanical Upgrades $5.5M Trapper Creek ES Roof $1M Swanson ES Ext Upgrades $200K Willow ES Roof $1.3M Joe Redington Sr MS/HS $65M CTHS Addition $16M Houston HS Exterior Siding $600K ADA Upgrades District Wide $1.5M Washroom Upgrade District Wide $800K Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M
DENA’INA ES $26.5M Design: Bettisworth N. Construction: FE Const 44,224 SF K through 5 school Work started April 2015, approx. 85% complete On schedule to occupy summer 2016
DENA’INA ES Classroom Second Floor Hall
IDITAROD ES $25.2M Design: MCG Construction: Collins 50,605 SF replacement school. Pre-K thru 5 Work started May 2015, approx. 95% complete On schedule to occupy spring/summer 2016 Carpenter Circle will be paved by the city
IDITAROD ES Gym Poured Floor Second Floor Hall
FRONTERAS CHARTER SCHOOL $6.9M Contractor: Howdie Const. Funded by USDA loan and $500K from MSB Access road from Seward Meridian is in place Work started July 2015, approx. 85% complete On schedule to occupy summer 2016 Tour - May 24, 2PM
FRONTERAS CHARTER SCHOOL Classroom Exterior
ATHLETIC FIELD IMPROVEMENTS $6.4M Play court upgrades at Finger Lake, Snowshoe, Larson, Glacier View and Houston High completed in 2014 All summer 2015 work complete with the exception of the Iditarod softball/baseball turf in-fields Work on turf fields will start this month
ADDITIONAL PROJECTS Back-Up Generators, District Wide $2.6M - Scope includes base bid - Wasilla MS, Wasilla HS, Palmer HS -- Awarded alternates - Big Lake ES, Butte ES, Snowshoe ES, Willow ES and the Operations & Maintenance Building - Contract awarded to Wolverine March 1 with work underway Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K - Remaining work involves new corridor lighting and ceiling tiles - Assembly approved construction contract to Wolverine Jan 12 - Work scheduled for summer break 2016 District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction (Ph I) -- Work at Butte ES, Pioneer Peak ES, and Snowshoe ES are complete -- Cottonwood ES, Finger Lk ES, Willow ES (new boiler), Goose bay ES, Tanaina MS scheduled for summer Phase II awarded to FE Contracting with work starting at Wasilla MS this summer and a new boiler at Palmer JMS in summer 2017
ADDITIONAL PROJECTS cont. District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - New LED Gym lighting project is complete - Partial window replacements at 18 schools will be advertised this month for summer 2016 construction Flooring Replacements $900K (2010 and 2011 flooring bond balances) - Carpet scope includes Butte, Cottonwood, Finger Lake, Goose Bay, Sherrod, Swanson, Trapper Creek, and Willow Elementary Schools for a total of 108,000 SF of new flooring -- Assembly approved carpet install contract to CYS Enterprises April 5 - Bid for new gym floors at Big Lake and Willow closed May 2, with Alaska Industries contract going to the Assembly May 17 for approval Roof Bond Balance $800K - Project includes Sutton ES roof replacement and Tanaina ES roof mods - Contract to EP Roofing approved Feb 16 for summer 2016 completion