SLIDE 1 SRAS REVIEW QUEENSLAND REGION July 2013 PRESENTED BY PETER BIDDLE.

Slides:



Advertisements
Similar presentations
Summary of Second Draft of the NERC Standard PRC Disturbance Monitoring and Reporting JSIS Meeting August 10, 2010 Salt Lake City, UT.
Advertisements

Demand Resource Operable Capacity Analysis – Assumptions for FCA 5.
1 FREQUENCY CONTROL -- Bhanu Bhushan -- (April, 2011)
SLIDE 1 Extended reserve Technical working group 11 September 2014.
Regional Planning Group Project
Connection of Wind Farms to Weak AC networks – ERCOT Experience and Challenges Shun-Hsien (Fred) Huang ERCOT System Planning CIGRE WG B4.62 Meeting June.
Integrating Multiple Microgrids into an Active Network Management System Presented By:Colin Gault, Smarter Grid Solutions Co-Authors:Joe Schatz, Southern.
Tucson Area Reliability Mike Flores Control Area Operations Tucson Electric Power May 2000.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
System Strength Discussion
Slide 1 Large Wind Integration Challenges for Operations / System Reliability By : Steve Enyeart, BPA With contributions from: Bart McManus, BPA Roy Ellis,
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
1 Voltage Collapse Animation (AC) Created by Peter W. Sauer Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign.
SLIDE 1 AEMO INDEPENDENT ASSESSMENT OF NSW & TAS NETWORKS July 2014 PRESENTED BY NATIONAL PLANNING.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
Thailand, May 2009 Mekong Energy and Ecology Network The First Mekong Energy and Ecology Training.
Generator Data Submittals 5/8/ Transmission Customer Forum Bob Jones Transmission Planning Southern Company Transmission 5/8/ Transmission.
Experiences of the Australian Electricity Market under power disturbances and financial stress Dr Brian Spalding Chief Operating officer WELCOME to NEMMCO’s.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
Pj Overview of Wind Energy Grid Integration in Australia ADB Wind Energy Grid Integration Workshop Sept 23, 2013 Dr Geoff James Specialist, Renewable Energy.
Lyndonville Electric Department Feasibility Analysis Review December 2,
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
Pj Overview of Wind Energy Grid Integration in Australia ADB Wind Energy Grid Integration Workshop Sept 23, 2013 Dr Geoff James Specialist, Renewable Energy.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 2009 Draft Resource Program Released: September 30, 2009 Accepting Comments until: November 30,
HYDROPOWER. Objective: The student will be become familiar with the Corps policy for hydropower development. The student will be have a basic understanding.
Sixth Northwest Conservation & Electric Power Plan Draft Wholesale Power Price Forecasts Maury Galbraith Northwest Power and Conservation Council Generating.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Wind Generation in New Zealand Kieran Devine, Doug Goodwin System Operations Transpower New Zealand Limited.
Renewables and System Services Ann Scully.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
Resource Adequacy Steering Committee Meeting October 4, 2011.
ACC Summer Preparedness Hearing Tucson Electric Power & UNS Electric March 22, 2007 Ed Beck Superintendent Transmission & Distribution Planning.
Review of SONI Power System Operations Alex Baird Grid Operations Manager Real Time.
Implications of Energy-Only Procurement on Transmission Planning CPUC Workshop: Revisions RPS Calculator v6.0 Robert Sparks Manager Regional Transmission.
SCHEDULING METHODOLOGY The station-wise (Ex-bus) capability would be submitted by the ISGSs in the specified format. ISGSs would declare the capability.
The Australian Market Evolution Dr Brian Spalding Chief Operating Officer NEMMCO.
NLDC 1 Ancillary Services in Indian Context. NLDC 2 Outline Definition Drivers for Ancillary Services Ancillary Services in Indian Context.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
Long-Term Solution for Negative Generation Entergy Transmission AFC Stakeholder Meeting August 22, 2006.
ISO Proposed Flexible Capacity Requirements Stephen Keehn Senior Advisor California ISO CPUC Workshop January 26, 2012.
Our Key Objectives A free service to Members Help members reduce their running costs through buying together Help members reduce their Energy Consumption.
Utah State University Logan Utah. Founded 1888 as a Land Grant Institution Host City – Logan, Utah (48,ooo+ population) ~ 15,000 Students (~ 28,700 students.
June 2008 Windsor-Essex Electrical Service Needs and Solutions.
Target Reserve Margin (TRM) and Effective Load Carrying Capability (ELCC) of Wind Plants Evaluation - Input and Methodology ERCOT Planning 03/25/2010.
Southern California Edison The San Onofre Nuclear Generating Station April 14, 2011.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Distribution Systems-General
What’s happening in Spain? Access to the grid request of STE projects by Oct MW.
Performance of the Integrated National Electrification Programme as at 30 June 2008 (4 rd Quarter) Presentation to the Select Committee on Finance 14 August.
SLIDE 1 VICTORIA REGION RESTART July 2013 PRESENTED BY PETER BIDDLE.
1 8. OPERATING, REACTIVE AND BLACK START RESERVES Asko Vuorinen.
BELIZE ELECTRICITY LIMITED Electric System Presentation January 8, 2014 Rolando Santos Senior Manager, System Planning and Engineering & Kevin Longsworth.
SLIDE 1 SOUTH AUSTRALIA REGION RESTART July 2013 PRESENTED BY PETER BIDDLE.
SLIDE 1 POWER SYSTEM ADEQUACY – A TWO YEAR OUTLOOK 2011 October 2011 JAMES LINDLEY.
SLIDE 1 SRAS REVIEW TASMANIA REGION July 2013 PRESENTED BY PETER BIDDLE.
(c) IRD 2002 Power System Restoration (Black Start) Black Start Panel Session IEEE PES Summer Meeting Chicago, Illinois July 23, 2002 M. M. Adibi IRD Corp.,
SLIDE 1 SRAS REVIEW NEW SOUTH WALES REGION July 2013 PRESENTED BY PETER BIDDLE.
Kenya’s INDC: Actions in the Energy Sector
Pan-Canadian Wind Integration Study (PCWIS) Prepared by: GE Energy Consulting, Vaisala , EnerNex, Electranix, Knight Piésold Olga Kucherenko.
ERCOT Black Start Enhancements
Target Reserve Margin (TRM) and Effective Load Carrying Capability (ELCC) of Wind Plants Evaluation - Input and Methodology ERCOT Planning 03/25/2010.
Beyond the Death Spiral
Damitha Kumarasinghe Director General
Ensuring Security of Supply in Estonian Transmission Grid
Economic Operation of Power Systems
Combined operation of different power plants PREPARED BY : Priyanka Grover Btech (EE) SBSSTC,FZR.
ISO New England Net Load Analysis with High Penetration Distributed PV
Power System User Requirements
Presentation transcript:

SLIDE 1 SRAS REVIEW QUEENSLAND REGION July 2013 PRESENTED BY PETER BIDDLE

SLIDE 2 AGENDA 1.The System Restart standard 2.What are the proposed changes a)Main assumptions b)Electrical sub-networks c)Quantity of SRAS d)SRAS Definition 3.Restart process a)North b)South 4.Questions 5.Summary

SLIDE 3 SYSTEM RESTART STANDARD Procure sufficient SRAS to achieve the following targets in each electrical sub-network; o Provide auxiliary supply to sufficient generation within 90 minutes to provide generation & transmission capacity to meet 40% of peak demand within 4 hours For QLD South peak demand = 5100MW o Need to supply 2040MW capacity within 4 hours For QLD North peak demand = 3400 o Need to supply 1360 MW capacity within 4 hours The restoration timeframe represents the target timeframe to be used by AEMO in the procurement process. It is not a specification of any operational requirement that should be achieved in the event of a black system condition

SLIDE 4 RECOMMENDED CHANGES Current assumption is that SRAS is procured to manage a NEM wide shutdown o Changing to a Region only shutdown NEM wide shutdown requires each region to be self- supporting for SRAS o Region only shutdown allows use of adjoining regions as a restart supply Currently three electrical sub-networks in Queensland o QLD North, QLD Central & QLD South

SLIDE 5 RECOMMENDED CHANGES (CONT.) Recommending a combination of the central & north sub- networks  Connections between these areas recently strengthened Now 3 275KV lines from Nebo to Ross + 132KV connections Now 4 275KV lines between Nebo and Broadsound/Bouldercomb + 132KV connections 3 275KV lines between Calvale & Stanwell + 132KV connections and 2 additional 275KV lines in Nov 2013 Currently 6 SRAS in Queensland – 2 x south, 3 x central & 1 x north o Proposing a minimum of 1 SRAS in each sub-network

SLIDE 6 RECOMMENDED CHANGES (CONT.) Current definitions of primary & secondary SRAS has led to a number of perverse outcomes o small gas turbines starting large thermal units at the same power station that do not assist in AEMO meeting the System Restart Standard because:  No output to transmission network for several hours  Do not assist in restarting other generating units o Contracting with diesel units used to restart hydro and gas turbine generating units  Makes testing difficult and inefficient

SLIDE 7 RECOMMENDED CHANGES (CONT.) Recommending a single SRAS definition Objective is to ensure contracted services assist AEMO in meeting the System Restart Standard o ≥ 100MW delivered to the local transmission bus within 60 minutes.  Availability/reliability ≥ 90%  Could be delivered by TTHL Hydro Gas Turbines Other o Testing would involve black starting the unit, connecting to the power system and increasing output to contracted output within the contracted timeframe. AEMO is currently consulting with a number of generators to see if changes to this proposal are warranted.

SLIDE 8 RESTART PROCESS Under AEMO’s proposal Queensland will have a minimum of three restart sources o From NSW o At least 1 SRAS in south o At least 1 SRAS in north A restart will normally start from all three sources concurrently. o For the purpose of this exercise we will assume a restart from NSW is not available so restart will be managed from the SRAS only. The aim is to provide auxiliary supply to the majority of power stations within 90 minutes. o If this is done then the time to restore supply capacity is minimised but is then outside AEMO’s control.  Load restoration determined by rate at which power stations can restore capacity

SLIDE 9 SOME ASSUMPTIONS No change from current process o All generation & transmission equipment is available for service o Generation capability is in accordance with Local Black System Procedures as provided by Generators o Reasonable time frames allowed for restoration of transmission elements o Load may be restored for voltage control o Major generation  North – Callide, Stanwell, Gladstone, Townsville GTs  South – Tarong, Kogan, Millmerran, Wivenhoe, Swanbank, Braemar, Darling Downs, Oakey. o There are potentially a number of ways to do this

SLIDE 10 RESTORATION - NORTH Assume SRAS is Stanwell – TTHL service Energise Stanwell to Calvale and restore 132Kv bus o Restore load at Biloela and/or Moura and auxiliary supply to Callide power stations Energise Stanwell to Bouldercombe then Callipoe River and restore 132KV bus o Restore load at Gladstone North and auxiliary supply to Gladstone o Restore auxiliary supply to Boyne Island (Sensitive load) Energise Bouldercombe to Nebo and start SVC. o Restore load at Mackay and start GT Energise Nebo to Strathmore and start SVC Energise Strathmore to Ross and start SVC and energise 132KV bus Energise 132Kv line to Townsville South and to Mount Stuart o Start GTs at Mount Stuart.

SLIDE 11 STANWELL TO CALVALE & CALLIOPE RIVER

SLIDE 12 BOULDERCOMBE TO STRATHMORE

SLIDE 13 STRATHMORE TO ROSS TO CHALUMBIN

SLIDE 14 TIMING ESTIMATES TO MAKE AUXILIARY SUPPLY AVAILABLE Elapsed time = 30 minutes o Stanwell 1400MW o Callide 1500MW Elapsed time = 60 minutes o Gladstone 1600MW Elapsed time = 90 minutes o Mackay 30 MW o Mt Stuart 400MW Elapsed time = 120 minutes o Townsville 245MW o Kareeya 80MW

SLIDE 15 AFTER 4 HOURS – LIKELY SUPPLY CAPACITY Stanwell 700 MW Callide B 700 MW Callide C 800 MW Gladstone 560 MW Mackay 30 MW Mt Stuart 400 MW Townsville 285 MW Kareeya 80 MW Barron Gorge 60 MW Total = 3615MW (1360MW required to meet SRS)

SLIDE 16 RESTORATION - SOUTH Assume SRAS is Wivenhoe Energise Tarong and restore 66KV bus o Energise 132KV system to Chinchilla & Columbula o Restore load at Tarong plus Tarong auxiliary supply o Restore load at Chinchilla o Auxiliary supply to Roma and Condamine Energise Mt England to Blackwall and start SVC Energise Blackwall to Greenbank and start SVC Energise Greenbank to Swanbank E Energise Greenbank to Belmont and restore load Energise Tarong to Braemar and start SVC o Supply restored to Braemar & Darling Downs power stations

SLIDE 17 RESTORATION - SOUTH Start second Wivenhoe unit Energise Tarong to Blackwall Energise Tarong to Middle Ridge and through to Oakey GTs o Auxiliary supply to Oakey GTs Energise Braemar to Western Downs Energise Kogan o Auxiliary supply to Kogan Energise Braemar to Bulli Creek and Millmerran o Auxiliary supply to Millmerran

SLIDE 18 WIVENHOE TO TARONG & BRAEMAR

SLIDE 19 TARONG TO MIDDLE RIDGE

SLIDE 20 BRAEMAR TO WESTERN DOWNS & BULLI CREEK

SLIDE 21 TIMING ESTIMATES TO MAKE AUXILIARY SUPPLY AVAILABLE Elapsed time = 30 minutes o Wivenhoe 500 MW o Tarong 1800MW o Roma 80 MW o Condamine 140 MW Elapsed time = 60 minutes o Swanbank E 400 MW o Braemar & Darling Downs 1500MW Elapsed time = 90 minutes o Kogan 740 MW o Milmerran 880 MW o Oakey 340 MW

SLIDE 22 AFTER 4 HOURS – LIKELY SUPPLY CAPACITY Tarong 0 MW Tarong North 0 MW Swanbank E 400 MW Roma & Condamine 220 MW Wivenhoe 500 MW Braemar 1000 MW Darling Downs 500 MW Kogan 740 MW Milmerran 0 MW Oakey 340 MW Total = 3700MW (2040MW required to meet SRS)

SLIDE 23 QUESTIONS

SLIDE 24 SUMMARY Region only shutdown Move to two electrical sub-networks Minimum of one SRAS to be procured per sub-network Still three sources of restart supply Expect to be able to provide auxiliary supply/connection to all major generation within 90 minutes. Rate of load restoration will depend on rate of generation restoration and is outside AEMO’s control.