1 | Eton Range Realignment Project RAAG Presentation 10 March 2016
2 | Agenda Deficiencies of Existing Crossing Safety Improvements Reinforced Earth Embankment (REE) Traffic Management Project Details Drive-thru Video
3 | Site of Fatal Accidents HV Traction Issues (11%) Width Constraints Slope Stability Issue High Speed Approaches (Up & Down) Composite Curve Deficiencies of Existing Crossing Hairpins 50 metre radii
4 | RE Embankment Vertical grade 7.5% 4 lanes 5 x CCTV Cameras for incident management Breakdown curves to control approach speed Safety Improvements Hairpin radius improvement, 55m to 75m
5 | Increase speed sooner Alignment follows the crest of ridge Sidelong cut/fill profile Traffic diverted to allow construction of up alignment Safety Improvements Traffic change over point for incident management
6 | Reinforced Earth Embankment (REE) Height 10m – 44m
7 | Reinforced Earth Embankment (REE)
8 | Reinforced Earth Embankment (REE)
9 | Traffic Management Stage 1A Site Office & Entry Traffic Lanes Work Zones Overtaking Lane Closed Duration 2 Months
10 | Traffic Management Stage 1B Site Office & Entry Traffic Lanes Work Zones Overtaking Lane Closed Duration 15 Months
11 | Traffic Management Stage 2 Site Office & Entry Traffic Lanes Work Zones Overtaking Lane Closed Duration 12 Months
12 | Traffic Management Stage 3 Site Office & Entry Traffic Lanes Work Zones Duration 1 Months
13 | Traffic Management Two Lane Operation at All Times except when Blasting All Motorist: VMS Boards used for advanced warning to roadworks Public notices on TMR website for project updates: Stakeholder notification group Heavy Vehicles: Truck pull-off areas maintained – OSOM management performed as normal by Police OSOM restrictions on TMR website - Advised to contact Fulton Hogan prior to travelling: vehicles/Excess-mass-and-dimension-conditions Stakeholder notification group heavy haulage Permit Conditions
14 | Traffic Management Contractor: Fulton Hogan Construction Pty Ltd Project Duration: 16 March 2016 – Late 2018 If you would like to be added to stakeholder notification group, please If you wish to contact the TMR project team, please CC: CC: Project Manager: Mark Weatherley (Ph: ) Project Engineer: Emma Lyons (Ph: )