SBN Near Detector Building Conventional Facilities Update Steve Dixon LAr1-ND Collaboration Meeting 16 September 2014.

Slides:



Advertisements
Similar presentations
NYS Department of Environmental Conservation Update on the Niagara River U.S. RAP Niagara River Remedial Action Plan Implementers Session April 10, 2013.
Advertisements

Student Learning Targets (SLT)
LBNE Reconfiguration Jim Strait, LBNE Project Director Fermilab Community Advisory Board August 23, 2012.
Monthly Conference Call With Superintendents and Charter School Administrators.
LArTF and MicroBooNE Installation
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
Instrument Space Requirements Rob Connatser Chief Instrument Project Engineer November 2014.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
Energy Companies Obligation Update David Fletcher 7 October 2014.
NuMI Offaxis Costs and Whither Next Stanley Wojcicki Stanford University Cambridge Offaxis workshop January 12, 2004.
PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract.
8/26/20151 Building a Legacy Rebuilding Providence Public Schools 2009 Q1 Report.
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
CERN LBNE Test Experiment. Plan view of Bat
LAr1-ND Cryogenics Concept David Montanari Neutrino Cryogenics Requirements Meeting 24 September 2014.
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP Status and Overview.
University of Toronto Mississauga Campus: UTM Master Plan Update Campus and Facilities Planning | March University of Toronto Mississauga Campus.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
Lets and Quantities Report Mark Wolfgram Division of Transportation Investment Management Wisconsin Transportation Builders Association Annual Meeting.
Fermilab 1 AP Dept. Activities Report September 20, 2006Dixon Bogert AP Dept. - Activities Report Dixon Bogert - AP Dept. Meeting September 20 th, 2006.
NO A Project Status John Cooper & Ron Ray October 18, 2006.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Office of Acquisition and Property Management Proposed Changes to Attachment G FY 2011 – FY 2015 Five Year Plan.
LIGO-G M Planning and Implementation Strategy for Advanced LIGO Gary Sanders LSC Meeting Hanford, August 14, 2001.
Fermilab Neutrino Program Jim Strait Neutrino Discussion at CERN 26 November 2013.
James W. Beever III Southwest Florida Regional Planning Council 1926 Victoria Avenue Fort Myers, FL ( , ext 224)
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
BUILDING STRONG ® Mississippi River Ship Channel Gulf to Baton Rouge, LA Propeller Club for Port of New Orleans 24 September 2015.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Gary Feldman MINOS in Cambridge 24 March NO A Update MINOS Collaboration Meeting Cambridge, England 24 March 2009 Gary Feldman.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
Conventional Construction Working Group Meeting Tom Lackowski L2 Conventional Facilities Mu2e Working Group.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Geotechnical Conditions Tom Joos Civil/Structural Engineer BNL Plant Engineering.
SABER, “maybe” a new facility in the South Arc (South Arc Beam Experimental Region) End Station A (ESA) in 2007 ILC Test Beams in 2008 Test Beams beyond.
JOHNSON STREET BRIDGE PROJECT COUNCIL WORKSHOP MAY 21, 2009.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
Work Related to Senate Bill 2202 (effective January 1, 2001)
Reliability Standards Development Plan David Taylor Manager Standards Development Standards Committee Meeting June 12-13, 2008.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES - 3D VISUALS FOR SURFACE STRUCTURES.
News from LBNF C. J. Mossey, LBNF Project Director DUNE Collaboration Meeting - South Dakota School of Mines and Technology 19 May 2016.
PORT OF TACOMA. Contract Increase & Award Pier 7 Structural Repairs Request authorization to expand the scope of existing A/E Contract No and.
Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.
SBN Far Detector Building Conventional Facilities Update Steve Dixon WG3 Workshop 11 September 2014.
The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects the current highway location in order to continue.
Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
WBS Experiment Infrastructure: Design Status Discussion Dixon Bogert Prepared for the MicroBooNE Collaboration Meeting 6/17/11.
1 First Class MTAC Workgroup 102 November 1, 2006.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
Challenges to get LBNF ready for Far Detector installation ASAP Elaine McCluskey ELBNF Proto-Collaboration Meeting 22 Jan 2015.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
OTE Building PMG Report September 10, 2012 Rhonda Merchut 1.
Capital Facilities Program Update San Rafael City Schools August 8, 2016.
County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation.
SBN Far Detector integration model overview
News and brief overview of Beamline plans for the next few months
South Carolina Perspective on Part 61 Proposed Revisions
Reach 4 Air Valve Replacements Award of Construction Contracts
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
Waste Plant Operator Follow-up Meeting
David Salazar, Chief Facilities Executive
Reliability Standards Development Plan
ARIZONA WATER COMPANY East Sedona Water Storage Facility
Far Experimental Hall Hutches Civil Construction
Magnet, Support and Infrastructure
Walker Street Reconstruction Project 25% Design Public Hearing
115-Unit Mixed-Use Project (711 E
JLEIC Accelerator R&D Meeting
Presentation transcript:

SBN Near Detector Building Conventional Facilities Update Steve Dixon LAr1-ND Collaboration Meeting 16 September 2014

Agenda Progress Since July –Design Refinement –Cost Estimate –Potential Changes –Project Plan What’s Next 16SEP14S. Dixon | Conventional Facilities Update2

Location Plan 16SEP14S. Dixon | Conventional Facilities Update3 BNB Target SciBooNE LArTF MiniBooNE NOvA MINOS Near Detector 600m – Far Detector

Near Detector Site Location 16SEP14S. Dixon | Conventional Facilities Update4 Looking North - September 2007

Near Detector Site Location 16SEP14S. Dixon | Conventional Facilities Update5 Looking South - September 2007

Aerial View from West 16SEP14S. Dixon | Conventional Facilities Update6 In Progress Preview

Aerial View from West 16SEP14S. Dixon | Conventional Facilities Update7 In Progress Preview MI-12 MicroBooNE MINOS Service Building NOvA Surface Building MiniBooNE Detector SBN Far Detector Building SBN Near Detector Building View Looking Southwest

Near Detector - Requirements 16SEP14S. Dixon | Conventional Facilities Update8 From D. Montanari 129m3 Version 231m3 Version

Design/Cost Estimate Process – Target: $3.5m July 2014 Design Refined – 2 designs at 2 locations August External Estimate –129m3 Version - $4.3m (total project cost) –231m3 Version - $5.1m (total project cost) Scope Reductions – focused on 129m3 version –Eliminated additional loading dock bay –Removed toilets/utilities –Removed cryostat concrete –Reduced siding cost –Onsite disposal of excess spoils –Moved overhead crane from Base Scope to Scope Contingency August External Estimate - $3.5m (total project cost) 16SEP14S. Dixon | Conventional Facilities Update9

Near Detector Building 16SEP14S. Dixon | Conventional Facilities Update10 Wetland Delineation – June 2014 Plan at Detector Level

Near Detector Building 16SEP14S. Dixon | Conventional Facilities Update11 Plan at Grade Level

Near Detector Building 16SEP14S. Dixon | Conventional Facilities Update12 Section

Near Detector Building 16SEP14S. Dixon | Conventional Facilities Update13 Wetland Delineation – June 2014 Section

Near Detector Building – Potential Changes 16SEP14S. Dixon | Conventional Facilities Update14 Overhead Crane Base scope does not include the crane, only the structure capable of supporting a crane; Recognize that a crane is needed for installation; Cost for 10 ton crane is ~$140k Project Plan (section 2.1 on page 12) identifies the crane as one of the highest priorities;

Near Detector Building – Potential Changes Reduced Size of Lower Level 16SEP14S. Dixon | Conventional Facilities Update15

Near Detector Building – Potential Changes 16SEP14S. Dixon | Conventional Facilities Update16 Shielding - #1 Move enclosure north of SciBoone by ~10 feet;

Near Detector Building – Potential Changes 16SEP14S. Dixon | Conventional Facilities Update17 Shielding - #2 Be able to accommodate 9 feet of shielding above the detector; Current Span (30’-8”) is longer than standard shield blocks 24’ “G” Block = 22’ clear * 30’ “N” Block = 28’ clear ** Revised Ledge Raise ground level Larger crane * Standard Fermilab Block, but availability uncertain/unlikely (7.7 tons) ** Non-standard Fermilab Block (9.7 tons)

What’s Next Project Plan (SBN-doc-72) Issued for Comment and Compliance Review Revise document based on comments Ready to submit for FY15 funding in October 2014 Subsurface Investigation Soil boring to confirm the soil conditions Final Design Develop an request for proposal for an AE firm Start Final Design in Spring 2015 (based on construction funding in FY2016 – October 2015) 16SEP14S. Dixon | Conventional Facilities Update18

Questions 16SEP14S. Dixon | Conventional Facilities Update19