Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer www.europeanspallationsource.se Review of ESS Accelerator Conventional Facility Design.

Slides:



Advertisements
Similar presentations
Nov. 19, 2008 ILC08 Global Design Effort 1 Status Report Alternative Siting and Tunnel Design Tom Lackowski.
Advertisements

CERN TS Department / Civil Engineering Group 8 February 2008 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC/ILC Collaboration Meeting 8 Feb 2008.
Instrument Space Requirements Rob Connatser Chief Instrument Project Engineer November 2014.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II.
PH-DT Infrastructure Investments M.Capeans SPOB meeting CERN, 20/3/14.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
TS Department / Civil Engineering Group 17 October 2007 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC workshop – Working group: Two beam hardware.
Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing.
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson Technical Board June 23,
Global Design Effort1 September 20-22, 2006 MAC Review Power and Water breakout (mixed results) Marc Ross GDE.
John Osborne : GS-SEM Civil Engineering 19 May 2009 Report on behalf of CLIC Civil Engineering and Services (CES) WG CTC 19 May 2009 Tunnel Cross Section.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
Conventional Construction Working Group Meeting Tom Lackowski L2 Conventional Facilities Mu2e Working Group.
Progress on Remote Handling Systems TAC 12 Magnus Göhran – WPM 15 th October 2015.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP STATUS REPORT V. Kuchler,
CMS Pixels upgrade CO2 cooling transfer lines Draft spec – for introduction Paola Tropea & Hans Postema 5 December 2012.
Global Design Effort Working Group C Conventional Facilities Parallel Session IRENG07 V. Kuchler, A. Enomoto, J. Osborne September 19, 2007.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson ADI Meeting July 2, ADI Meeting Ewan Paterson 7/2/15.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
CLIC MODULE TRANSPORT AND INSTALLATION Keith Kershaw CES, 8 October 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Status report on ICS interfaces (Accelerator, Target, NSS, CF) and related activities Miha Reščič Deputy Project Manager, ICS
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
Fundamental Concepts for Design of Special Hazard and Fire Alarm Systems Chapter 1.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Installation plans for RFQ and Superconducting linac Dave McGinnis Chief Engineer Eugene Tanke Systems Engineer March 20,
(1/17) 14/11/13 – RadWG meeting PS East Area Update Outline Layout updates of the facility Conveyer Rail system Mock-up Other news.
ESS Cooling System - Interface with DTL 1 John Jurns Cooling System Engineer.
Update on the ESS monolith design Rikard Linander Monolith and Handling Group ESS Target Division TAC 10, Lund, Nov 5,
ESS Cooling System - Interface with RFQ 1 John Jurns Cooling System Engineer.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.
Accelerator Installation Plan: Graphical representation E. Sargsyan & L. Lari DRAFT - March March 2016.
Introduction to the Accelerator layout February 2016 Nick Gazis Mechanical Integration Lead Engineer.
SuperB Experimental hall General considerations on the Babar experimental area Preliminary space requirements hall proposal. A floor plan. Specification.
E- source kick-off meeting e- Source RDR- Conventional Facility & Siting Overview Fred Asiri/SLAC.
Update on the PSB Cooling and Ventilation Systems
Cryomodule test stand at ESS site
CLIC Civil Engineering Update
Conventional Facility & Siting (CF&S) Overview for the Positron Source
COOLING & VENTILATION INFRASTRUCTURE
Operations, Risks & Hazards
Ciprian Plostinar Workshop on Testing and Commissioning
The Bunker Project Overview Zvonko Lazic
Operations Section Leader
Mechanical Engineering & Technology (MET)
RSFs & categorisation 20 May, 2019.
WP16 Water cooling systems
Radwaste: status & way forward
High Level Readiness Reviews
RF introduction Anders Sunesson RF group leader
Charge and Agenda of the 18th TAC meeting
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Accelerator Installation Schedule
Overview of the TARGET Monolith Rough Vacuum
General Overview of WP 12 ESS Vacuum System
Presentation transcript:

Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design

Outline ESS plant layout Integration – Accelerator Tunnel (AT) – Front-End Building (FEB) – HEBT Loading Bay (HLB) – Beam Dump (BD) – Accelerator to Target & Gallery Support Area (A2T & GSA) Conclusions NG - Accelerator Tunnel Layout G012

ESS accelerator areas NG - Accelerator Tunnel Layout G013 HLB FEB BD AT A2T FEB: Front-End Building AT: Accelerator Tunnel HLB: HEBT Loading Bay A2T: Accelerator to Target GSA: Gallery Support Area BD: Beam Dump lvl 110: first floor lvl 100: ground floor lvl 090: underground G01

Accelerator Tunnel (AT) design NG - Accelerator Tunnel Layout G014  1. Drift Tube Linac (DTL) 2. DTL to Spoke   3. Spoke 4. Medium Beta  Linac (MBL)

Accelerator Tunnel (AT) issues The high schedule pressure results in accumulating mistakes and less mature design Issue: The accelerator design is in preliminary stage and the site infrastructure design is finalized and concrete is being poured Risk: Our proposals and estimations include high error margins Mitigation: Use of space holders and mock-ups for as real as possible space evaluation Issue: The design is complex and the turn around is slow (every 3 weeks) Risk 1: Work on outdated models and overlapping inconsistent results Risk 2: We might have to review the accelerator design according to the changes in the site infrastructure Mitigation: Time spent on monitoring changes in a weekly basis, ad-hoc solutions and work on agreeing on dedicated space envelopes per system Issue: After agreeing on the requirements, their implementation is not always straight forward and there is no verification process (e.g. fire doors in the FEB, HLB) Risk: The layouts can become dysfunctional and/or miss the actual needs reflected by the requirements (with a future risk on cost for later corrections) Mitigation: Coordination meetings and iterations for coming up with valid revised concepts and layouts Issue: Absence of drainage system in the Accelerator Tunnel Risk: Any potential leaks inside the tunnel will result in areas with accumulated liquids Mitigation: Proposal for a ditch along the tunnel or local low points NG - Accelerator Tunnel Layout G015

Front End Building (FEB) design NG - Accelerator Tunnel Layout G016 HVAC  lvl 100 Water skids, cooling manifolds, entrance to the gallery etc.  lvl 090 Racks, cooling pipes, entrance to the AT, etc.

Front End Building (FEB) issues NG - Accelerator Tunnel Layout G017 Issue & Risk 1: Not enough space for the water skids and the pipe routing for the cooling water Mitigation: Working on increasing the space of level 100 Issue & Risk 2: Fire door limiting the width and height of the opening between FEB and AT Mitigation: Integrate the fire door in the double-door safety system on the other side of the chicane -lvl 100- HVAC -lvl

Front End Building (FEB) issues NG - Accelerator Tunnel Layout G018 -lvl Issue & Risk 3: FEB elevator is not wide enough to transport accelerator equipment for installation or replacement (e.g. SPK CM) Mitigation: Drop hatch in the other side of the FEB level 090

HEBT Loading Bay (HLB) design and issues NG - Accelerator Tunnel Layout G019 Issue: Fire doors implemented in the transportation corridor of the heavy equipment Risk: Narrows down the corridor width Mitigation: Review of AD installation and transportation processes to define if the new values are acceptable

Beam Dump (BD) design and issues NG - Accelerator Tunnel Layout G0110 Issue: The design installation of the BD is not finished Risk: No possibility to maintain and/or replace the BD. Mitigation: The BD can be accessible for maintenance by disassembling accelerator equipment and removing the concrete floor of the AT

- Accelerator to Target (A2T) design and issues - Gallery Support Area (GSA) design and issues NG - Accelerator Tunnel Layout G0111 Issue: The GSA should be enclosed by walls (NSS requirement) Risk: That leads to a need for HVAC room Mitigation: AD proposes to have the area wall free Issue: No power/heat can be dissipated to the air from the GSA (NSS requirement) Risk & Mitigation: Investigating the increased cost solution of water cooling racks 100 m2

Accelerator Tunnel (AT) -G01- Conclusions We have a preliminary accelerator design and a site infrastructure design is finalized and now concrete is being poured We have done a good team work to integrate the machine in the Accelerator Tunnel (G01) and the progress is considerable The preliminary accelerator design is in place and we are trying to reach the next state of design maturity Several issues were presented in this talk and mitigations for all of them are being worked as we speak NG - Accelerator Tunnel Layout G0112