Update on the conductor analysis for the PANDA solenoid Gabriella Rolando Herman ten Kate Alexey Dudarev Helder Pais Da Silva 19 September 2014 1.

Slides:



Advertisements
Similar presentations
Panda Solenoid Timelines. General Layout constraints and HOLD POINTS.
Advertisements

Q1 for JLAB’s 12 Gev/c Super High Momentum Spectrometer S.R. Lassiter, P.B. Brindza, M. J. Fowler, S.R. Milward, P. Penfold, R. Locke Q1 SHMS HMS Q2 Q3.
Zian Zhu Superconducting Solenoid Magnet BESIII Workshop Zian Zhu Beijing, Oct.13,2001.
Guenther Rosner FAIR Design Study, PANDA 3, GSI, 19/1/06 1 PANDA3: Magnet design and integration of detectors Tasks & participants Progress Milestones.
MUTAC Review, 9 April MuCOOL and MICE Coupling Magnet Status Michael A. Green Lawrence Berkeley Laboratory Berkeley CA
Briefs submitted for the TB to approve Tesla’s long lead items: 1)Cold Mass Forging 2)Super conductor wire.
October, 2003 P. Fabbricatore and S. Farinon Spectrometer magnets – Possible layout of cryostat in the end region In order to define the cryostat layout.
Progress on the MICE Cooling Channel Solenoid Magnet System
1 Update on Focus Coil Design and Configuration M. A. Green, G. Barr, W. Lau, R. S. Senanayake, and S. Q. Yang University of Oxford Department of Physics.
1 Spectrometer Solenoid Design and Cost Update Michael A. Green Lawrence Berkeley Laboratory 10 February 2005.
1 The Genoa Tracker Solenoids and their Contribution toward a New Design Michael A. Green Lawrence Berkeley National Laboratory and Pasquale Fabbricatore.
CM-18 June Magnet Conductor Parameters and How They affect Conductor Selection for MICE Magnets Michael Green Lawrence Berkeley Laboratory Berkeley.
Twin Solenoid Twin Solenoid - conceptual design for FCC-hh detector magnet - Matthias GT Mentink Alexey Dudarev Helder Pais Da Silva Leonardo Erik Gerritse.
Chapter IV Compressible Duct Flow with Friction
Superconducting Large Bore Sextupole for ILC
Powered Magnets, DB Formation and Decelerator Alexey Vorozhtsov (JINR) International Workshop on Linear Colliders October 2010.
Status of CEPC Detector magnet
Joint Institute for Nuclear Research Further optimization of the solenoid design A.Efremov, E.Koshurnikov, Yu.Lobanov, A.Makarov, A.Vodopianov GSI, Darmstadt,
Calorimeter Analysis Tasks, July 2014 Revision B January 22, 2015.
Forced two-phase helium cooling scheme for Mu2e Transport Solenoid Greg TatkowskiSergey ChebanNandhini Dhanaraj Daniel EvbotaMauricio LopesThomas Nicol.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Review of PANDA Magnet Designs Reviewers A. Dael, D. Tommasini, and A. Yamamoto Held at GSI, th April, 2007.
1 Numerical study of the thermal behavior of an Nb 3 Sn high field magnet in He II Slawomir PIETROWICZ, Bertrand BAUDOUY CEA Saclay Irfu, SACM Gif-sur-Yvette.
Zian Zhu Magnet parameters Coil/Cryostat/Support design Magnetic field analysis Cryogenics Iron yoke structure Mechanical Integration Superconducting Magnet.
CEA DSM Irfu - F. KIRCHER - [Seoul Workshop, Feb 16-18, 2009] 1 ILD detector magnet: LoI version F. Kircher, O. Delferrière CEA Saclay, DSM/Irfu/SACM.
Review of Quench Limits FermilabAccelerator Physics Center Nikolai Mokhov Fermilab 1 st HiLumi LHC / LARP Collaboration Meeting CERN November 16-18, 2011.
Baby-Mind Magnetic Module Design A. Dudarev, G. Rolando, E. Noah, H. Pais Da Silva and H.H.J. ten Kate Baby-MIND update meeting #1 July 29,
Open Midplane Dipole (OMD) Design for Dipole First Layout R. Gupta (BNL), N. Mokhov (FANL) bnl - fnal- lbnl - slac US LHC Accelerator Research Program.
Subscale quadrupole (SQ) series Paolo Ferracin LARP DoE Review FNAL June 12-14, 2006.
Magnet design, final parameters Paolo Ferracin and Attilio Milanese EuCARD ESAC review for the FRESCA2 dipole CERN March, 2012.
N.Delruelle, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Design choices.
16 T Dipole Design Options: Input Parameters and Evaluation Criteria F. Toral - CIEMAT CIEMAT-VC, Sept. 4th, 2015.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
Cold test of SIS-300 dipole model Sergey Kozub Institute for High Energy Physics (IHEP), Protvino, Moscow region, Russia.
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
Reducing the Iron in the Endcap Yoke of CLIC_SiD Benoit Curé, Konrad Elsener, Hubert Gerwig, CERN CERN, June 2014 Linear Collider Detector Magnet Meeting.
Baby MIND magnet design or “how to best magnetise a steel plate” Alexey, Etam, Gabriella, Helder, Herman Baby Mind Magnet CERN June 10, 2015.
Super Fragment Separator (Super-FRS) Machine and Magnets H. Leibrock, GSI Darmstadt Review on Cryogenics, February 27th, 2012, GSI Darmstadt.
AUGUST 3, 2010 BRYCE AUSTELL UNIVERSITY OF ILLINOIS FERMILAB SIST INTERN ADVISOR: RYUJI YAMADA Muon-to-Electron Conversion Experiment (Mu2e) Detector Solenoid.
Thermal screen of the cryostat Presented by Evgeny Koshurnikov, GSI, Darmstadt September 8, 2015 Joint Institute for Nuclear Research (Dubna)
F. Kircher CLIC concept meeting 12/15/08 1 Some points about the superconducting magnet for a CLIC detector F. Kircher (CEA Saclay/DSM/Irfu/SACM) December.
Preliminary analysis of a 16 T sc dipole with cos-theta lay-out INFN team October 2015.
Update on PANDA solenoid design and analysis Gabriella Rolando Helder Pais Da Silva Herman ten Kate Alexey Dudarev 3 November
Thermal Analysis of the Cold Mass of the 2 T Solenoid for the PANDA Detector at FAIR G. Rolando 1, H. H. J. ten Kate 1, A. Dudarev 1 A. Vodopyanov 2, L.
Results from the cold test of the first QD0 prototype
Status of the PANDA Solenoid Magnet Production in BINP
Design ideas for a cos(2q) magnet
Status of the PANDA Solenoid Magnet Production in BINP
Update on PANDA solenoid design
CBM magnet overview of the BINP work
Renuka Rajput Ghoshal John Hogan Ruben J. Fair Probir K. Ghoshal
TQS Structure Design and Modeling
Status of work on the cryostat design
CERN Conductor and Cable Development for the 11T Dipole
JLAB MEETING FDR – April 23-24th 2013
Status of the PANDA Magnet
Mechanical Modelling of the PSI CD1 Dipole
Yingshun Zhu Accelerator Center, Magnet Group
Magnet Options Forward dipoles vs. forward solenoids
Status of the PANDA Solenoid Magnet Production in BINP
MQXF coil cross-section status
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
November 14, 2008 The meeting on RIKEN AVF Cyclotron Upgrade Progress report on activity plan Sergey Vorozhtsov.
November 7, 2008 The meeting on RIKEN AVF Cyclotron Upgrade Progress report on activity plan Sergey Vorozhtsov.
Status of the PANDA Solenoid Magnet Production in BINP
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
as a prototype for Super c-tau factory
Cross-section of the 150 mm aperture case
F.Pasdeloup, H.Prin, L. Williams
Presentation transcript:

Update on the conductor analysis for the PANDA solenoid Gabriella Rolando Herman ten Kate Alexey Dudarev Helder Pais Da Silva 19 September

Outline  Conductor layout  Conductor cost  Coil dimensions & field quality  Magnetic force between yoke and cold mass  Thermosiphon – preliminary calculation 2

Conductor layout 3  To minimize the risk of coil training and quenches due to unexpected heat loads, we specified a temperature margin ΔT > 2.4 K.  For ΔT = 2.4 K we need 26 strands. Parameter New layout Old layout Number of strands 2620 Strand diameter [mm] 0.8 Cu : nonCu ratio Rutherford dimensions [mm] 9.7 x 1.58 x 1.15 Conductor bare dimensions [mm] 24.6 x 3.40

Conductor cost 4  A budgetary offer has been requested to Furukawa on July 31; and yielded a shocking high price of 267 $/m; some 90% higher than expected!  Based on the costs quoted to Fermilab for the Mu2e solenoid conductors, the expected cost of the Panda conductor is $/m! Unit Minimum unit length Unit length for downstream coil m3200 Unit length for center coil m1500 Unit length for upstream coil m3200 Total conductor lengthm7900

Conductor cost 5  After a second complaint about cost and request to mention cost drivers, on September 15 they mentioned the conductor unit length for Panda much longer than for Mu2e.  After serious complaints and inquiry about cost drivers, Furukawa made a second offer on August 29 of 191 $/m; much better, but still 36% higher than expected. Unit Minimum unit length NEW Minimum unit length OLD Unit length for downstream coil m2 x Unit length for center coil m1500 Unit length for upstream coil m2 x  Mu2e has unit lengths of 1750 m, 1660 m, 1280m, 1100 m and 750 m.  We requested shorter unit lengths for downstream and upstream coils, thus accepting and extra layer jump joint.

Conductor cost – Next steps 6  We are waiting for a confirmation that the offer now is in the expected range of $/m; answer is awaited in the coming days. Likely they will reduce cost but probably not entirely to the level we wish as they still need a margin for the real tender (with Hitachi as competitor).  Enquiry at FNAL: it seems the companies have underestimated the effort and may not making profit, which can be part of the explanation.  Also, Furukawa has requested a face-to-face meeting for further discussion of the conductor price by early October, date to be agreed. Next: o Cost may be $/m in budget offer, further down with the competitive tender. o Finalize the conductor specification based on new unit length, issue these documents. o Need budget availability confirmation to start the tender by early October. o Need confirmation of the organization issuing the tender (FAIR in the draft agreement). o Start to draft the commercial tendering documents and send tender by October.

Coil dimensions & field quality – Radial dimensions Assess the effect of radial dimension errors of the coils on the field quality within the tracker region.  The coils thickness is fixed at the nominal value, i.e. 50 mm.  The radius of a coil is varied in the ± 9 mm range.  The present coil radius is optimized for field homogeneity.  Small reductions of the coil radii are allowed. However, increase of the radii will result in the integral of the radial field component to exceeding the maximum allowable value of 2 mm. 7

Coil dimensions & field quality – Axial dimensions Extra length|δ| max [%]Int max [mm] Criterion: < 2.0< 2.00 Default, perfect shape ½ turn - upstream turn - upstream ½ turn - downstream turn - downstream  The eventual loss of one turn, and thus the need to increase the coil length, brings the integral of the radial field component just above the allowed threshold.  The increase is larger when the extra length is added towards the downstream side of the detector. 8 Assess the effect on the field quality within the tracker region of small deviations in the axial dimensions of the coils. The length of the coils is increased by half or one turn at each coil end plane (upstream & downstream).

Magnetic force on the cold mass by the yoke 9 Cross-check of the axial force between cold mass and yoke: Reference values are in the table following R. Parodi and H. Orth (2012). F x [kN]F y [kN]F z [kN] Nominal maximum current Under tolerable misalignment ±45 ±100 Model F z [kN] ANSYS 2D -41 ANSYS 3D -60 Opera 2D -38 Opera 3D -57 Calculations of the axial force at nominal position and - operating current:  The two 2D are consistent, and the two 3D calculations as well!  The 2D calculation results agree with the reference value  Not clear what the origin of the difference between the 2D and 3D results is. Investigation of the issue is ongoing.

Thermo-siphon – preliminary calculation 10 Preliminary assessment of the feasibility of thermosiphon cooling of the Panda coils: Homogenous model as used for the preliminary study for CMS in ‘Experimental and theoretical study of a two phase helium high circulation loop’ P. Bredy et al. AIP Conf. Proc. 823 (2006) Two-phase friction correlation: Continuity, momentum and energy equations:

Thermo-siphon – preliminary calculations 11 Main approximations:  Pressure drop at singularities neglected. In preliminary CMS studies, this was found to be one of the dominant terms. It could lead to a reduction of the order of ̴30% in the computed mass flow (and consequent increase in vapor fraction).  Difference between outflow flow and liquid level in the dewar neglected. Heat load Q = 57 W (from TDR) Mass flow rate ṁ = 112 g/s Vapor fraction x = < 3%  Based on these numbers we expect that the thermo-siphon mode will work for the present pipework layout and dimensions.