Community Infrastructure Levy – Charging Schedule.

Slides:



Advertisements
Similar presentations
Department of Arts and Culture Briefing on the Use of Official Languages Bill to the Select Committee on Education and Recreation Date:15 August 2012.
Advertisements

KHG Future Funding Workshop Community Infrastructure Levy – 14 June 2013 James Renwick Ashford Borough council.
Laura Wood Team Leader –Strategic Planning 16 th February 2015 Little Gaddesden Parish Council Meeting.
Savills.com CIL – An Industry View Philip Brown MRTPI Associate Director, Savills 16 October 2012.
Community Infrastructure Levy (CIL) Gwyn Jones City Growth and Development Manager Sustainable Development Panel Briefing 27 July 2011.
The Croydon Monitoring Report Planning Obligations and Community Infrastructure Levy December 2014.
LEVY IMPLEMENTATION 27 JANUARY TO 14 FEBRUARY 2014.
Dr Chris Boomer Development Plans Manager (DoE Northern Ireland)
Engaging with Planning Agents Reform of the Planning System 30 April 2015.
New approach to infrastructure Proposed LDP policies on Delivery Role of Action Programme New guidance on Developer Contributions and Affordable Housing.
System of Environmental-Economic Accounting SEEA-Energy Implementation United Nations Statistics Division Oslo Group Meeting September 2013 Baku,
Setting up a Neighbourhood Forum Lee Green Assembly meeting 23 June 2015.
HRA Self-Financing Update What it means & what we’ve done Housing Briefing 19 January 2012.
Corporate Services Grants Programme 2013 – August 2012.
Affordable Housing: Policies into Practice Louise Dwelly Housing Strategy & Enabling Manager October 2004.
© Grant Thornton UK LLP. All rights reserved. Review of Partnership Working Vale of Glamorgan Council Final Report- July 2008.
LOCAL BUFFER SUPPORT PROGRAM 1 May 2014 MAV. Liveability, growth and waste As Melbourne continues to grow, we need secure the right mix of resource recovery.
Guidance for AONB Partnership Members Welsh Member Training January 26/
Meeting the Challenges of the Changed Economic Environment Annual Conference September 2009 Water Services Training Group 13 th Annual Conference 10 th.
Local Transport Plan 3 Vision and Issues. The Local Transport Plan Will replace LTP2, which expires 31 March must have LTP3 approved and operative.
Community Infrastructure Levy Preliminary Draft Consultation.
Community Infrastructure Levy Planning Advisory Service Gilian Macinnes October
Planning Obligations & Section 106
Neighbourhood Planning
December_2009 Partnership building. December_2009 Partnership building within the partnering process COREGROUPCOREGROUP FORMAL LAUNCH $ $ $ $ $ cost centre.
Neighbourhood Planning. What is neighbourhood planning? Neighbourhood planning gives communities direct power to develop a shared vision for their neighbourhood.
Sub-theme 4 Building blocks for NSDS 3 REPORT BACK National Skills Conference 2008 “Reflection on a decade of skills development for the future”:
Neighbourhood Planning Miles Thompson Shared Planning Policy Manager South Oxfordshire and Vale of White Horse District Councils
Communications and marketing Presentation by Jennifer Moore, Head of Planning Peter McAnespie, Policy Team Leader Date 17 July 2012 NPPF/Localism.
Low Emission Strategies in Practice Rob Pilling (London, 12 th May 2009) web:
Presentation to the Parliamentary Portfolio Committee on Water and Environmental Affairs, 23 January 2012, Parliament, Cape Town.
Fair Go Rates System Dr Ron Ben-David Chairperson MAV Rate Capping Forum 26 November 2015.
Regional planning I local plan I design & regeneration I transport planning I research & information Southend-on-Sea Core Strategy Development Plan Document.
Virginia Office of Public-Private Partnerships (VAP3) Adopted Public-Private Transportation Act (PPTA) enabling legislation in 1995 Public-Private Education.
Presentation to the Portfolio Committee Establishment of an Agency for Social Security 26 February 2003 Department of Social Development.
CIL : The Spending. Background and Context The levy cannot be expected to pay for all of the infrastructure required: – 10-30% – Consider CIL as just.
CIL – a local authority perspective Jeni Jackson, Woking BC.
Community Infrastructure Levy Implementation July 2014.
INTRODUCING CIL AND DEALING WITH SCHEME SPECIFIC VIABILITY ISSUES – BRISTOL’S APPROACH Jim Cliffe Planning Obligations Manager Bristol City Council.
CIL vs S106 The Regulation 123 list. The levy cannot be expected to pay for all of the infrastructure required: – 10-30% – Consider CIL as just one part.
PLANNING & SUSTAINABLE DEVELOPMENT City Planning Team PLANNING OBLIGATIONS – BRISTOL’S APPROACH Jim Cliffe Planning Obligations Manager Bristol City Council.
Community Infrastructure Levy in Islington Eric Manners London Borough of Islington PAS Seminar – ‘Making CIL Work’ 12 January 2016.
Community Infrastructure Levy S106 and S278 vs CIL July 2014.
Implementing a CIL in Sheffield - Lessons Learned Richard Holmes Principal Planning Officer Forward and Area Planning Sheffield City Council.
Savills.com CIL Latest Research & Findings Emily Harvey, Associate.
Guest speaker: Lizzie Cullum (Savills). savills.com Viability Testing of CIL and Local Plans Effective Practice Lizzie Cullum BA (Hons) MRICS Surveyor,
Local Authority Experience Managing an effective S106 process Stephen Pointer Strategic Planning and Housing Manager Harborough District Council.
Torbay Council Partnerships Review August PricewaterhouseCoopers LLP Date Page 2 Torbay Council Partnerships Background The Audit Commission defines.
PAS CIL Seminar Leeds 7 January 2016 Implementing CIL Mike Molyneux Planning Policy Manager Preston City Council.
S106 Agreements Development Control User Panel. s106 agreements What are s106 agreements? How are they managed? The future:Community Infrastructure Levy.
1 Section 106: What they are and where we are DARREN WILDING DCLG.
IMPLEMENTING CIL – BRISTOL’S EXPERIENCE Jim Cliffe Planning Obligations Manager Bristol City Council.
PAS CIL EVENTS JULY 2014 The Leeds Community Infrastructure Levy - Lessons Learnt.
Neighbourhood Planning in Haringey Myddleton Road Strategic Group 7 th November 2013.
Community Infrastructure Levy The fundamentals. Response to questions.
Community Infrastructure Levy S106 vs CIL July 2014.
Councillor briefing Developer contributions: Community Infrastructure Levy, S106 obligations, viability Date: July 2013www.pas.gov.uk.
1 Community Infrastructure Levy Mark Lee. 2 Community Infrastructure Levy Introduced in April 2010 as fairer, faster more certain and more transparent.
Demystifying viability The local authority experience Dominick Mennie, Deputy Team Leader (Plan Making)
Community Infrastructure Levy Project Planning and Infrastructure Evidence July 2014.
No.1 for Service and Value CIL – the experience Martin Howell, Group Planner – Policy & Information, Wandsworth Council
Laura McCulloch Strategic Manager – Planning Hampshire County Council The Community Infrastructure Levy: The Hampshire Experience.
Implementing a CIL in Sheffield - Lessons Learned Richard Holmes, Principal Planning Officer Forward and Area Planning Sheffield City Council.
Place CIL Implementation – the Bristol experience Jim Cliffe (Planning Obligations Manager – Bristol City Council)
S106 – Where we are- current context Gilian Macinnes Date: March 2015www.pas.gov.uk.
AGENDA The current focus on housing Do we need older people’s housing? The role of planning? National Level Local Level Opportunities to influence Planning.
Fair Go Rates System Dr Ron Ben-David Chairperson
Neighbourhood Planning
Fair Go Rates System Dr Ron Ben-David Chairperson
The partnership principle in the implementation of the CSF funds ___ Elements for a European Code of Conduct.
Presentation transcript:

Community Infrastructure Levy – Charging Schedule

Community Infrastructure Levy Developing a CIL Charging Schedule 1.identify the infrastructure funding gap 2.develop the draft charging schedule (viability assessment and infrastructure planning) 3.set the levy, two rounds of consultation, examination & adoption 4.Council to operate as a collecting authority Mayor’s CIL 1 April 2012 – Collecting Authority

Community Infrastructure Levy – Early Essentials Establish a project team –Planning Policy –Development Management –Infrastructure Planning –Service providers (internal (education / capital delivery hub) and external (health)) –Consultants – viability, infrastructure and project management Project management important Corporate ‘buy in’ essential Communication (internal and external)

London Borough of Croydon’s CIL - Programme Evidence Base –Infrastructure Delivery Plan –Infrastructure Cost Report –Viability Report Preliminary Draft Charging Schedule – September – October 2011 Draft Charging Schedule – January – February 2012 Submission – June 2012 Examination – September 2012 Adoption – February 2013 Introduction – April 2013

Preliminary Draft Charging Schedule CIL Rates

Preliminary Draft Charging Schedule

Issues arising from representations: 1.Concern from developers on the impact on viability. 2.Requests for a facility to pay by instalments 3.Requests for Croydon to allow exceptional relief 4.Challenge by London First on the technical basis of viability assessment

Draft Charging Schedule Reported consultation outcomes to LDF Board, CMT, Leader and Cabinet member Sought approval for next steps Continued dialogue with development industry and key stakeholders Undertook additional office viability assessments Increased business rate in CMC to £120 sq m to better align with viability evidence Agreed the introduction of an instalment policy Agreed to trigger exceptional relief

Draft Charging Schedule CIL Rates – January 2012 Table 2: Proposed Schedule of RatesProposed CIL rate £ per m 2 Use Croydon Metropolitan Centre Rest of the Borough Residential –Dwelling Houses (C3)0120 Business (B1, B2-B8)1200 Institutions (C2) (D1)0 All other uses120

Draft Charging Schedule Examination Submission - June 2012 Examination - September 2012 Main Issues Is the charging schedule supported by background documents containing appropriate available evidence? Is the charging rate informed by and consistent with the evidence? Does the evidence demonstrate that the proposed charge rate would not put the overall development of the area at serious risk?

Draft Charging Schedule Examination Largely uncontested extent of infrastructure needed to support the growth set out in the Core Strategy Largely uncontested infrastructure funding gap Contested Development viability assessment site sample size sufficient Two charging zones justified CIL rates supported by the evidence Should certain community uses be exempt from CIL Do the CIL rates put overall development of the area at serious risk

Draft Charging Schedule Examiner’s Report In setting the CIL charging rate the Council has had regard to detailed evidence on infrastructure planning and evidence relating to economic viability. It has struck a credible balance between, on the one hand, the need to achieve a reasonable level of income to address the acknowledged gap in infrastructure funding and, on the other, the need to ensure that the overall development of Croydon is not put at serious risk.

CIL and Section 106 Non Statutory CIL and Planning Obligations Guidance Role of Section 106 Affordable housing Development mitigation – Regulation 122 Non material contributions CIL Regulation 123 list 5 pooled contributions Instalment policy Exceptional relief Lawful use / Demolition

Community Infrastructure Levy and Local Plan - Strategic Policies Joint Submission and Examination

Joint CIL and CLP Submission and Examination CLP and CIL PINS SLAs – September 2011 CLP Submission – April 2012 CIL Submission – June 2012 CLP and CIL Examinations – September 2012 Inspector’s and Examiner’s Reports – December 2012

Joint CIL and CLP Submission and Examination – Benefits and Efficiencies Appointment of one programme officer Coordinated submission Evidence base remains relevant Coordinated Examination arrangements Period of Examinations focus Same Inspector and Examiner Coordinated receipt of reports and adoption

Joint CIL and CLP Submission and Examination – Risks Public and stakeholders aware of difference Evidence base coordinated Consistent messages at both examinations Officers and consultants available

Community Infrastructure Levy – Payment and Collection

Introduction Level of understanding regarding the requirements and implications still developing. Requirements largely set out in the 2010, 2011 and 2012 CIL Regulations. Croydon has been operating as collecting authority since April 2012 – Mayoral CIL. Borough’s CIL 1 April 2013 – Council February. Equally, if not more, challenging than developing a CIL Charging Schedule.

Early Essentials Develop a good understanding of the CIL regulations. Acknowledge CIL payment and collection is a project and establish a project team. Boroughs should produce ‘theoretical’ flowcharts – have to be clear what needs to be achieved (the who, when and how). Revise the flowcharts to reflect particular borough circumstances – e.g. presence of capital delivery hub. Share knowledge with stakeholders and developers – increasing awareness is essential.

Croydon’s Four Block Process 1.Planning services – planning application / CIL 2.Exchequer services – collection 3.Delivery – corporate function 4.Planning services - monitoring

Collecting Authority Project Group Members Project group members Planning Policy Development Management Planning Administration Exchequer Services Corporate Finance Land Charges Legal Capital Delivery Hub / Capital Finance IT

Planning services 1.Planning application submission 2.Notice of chargeable development 3.Assumption of liability 4.Possible instalment policy 5.CIL relief submitted, assessed and calculated 6.Planning permission granted 7.Liability notice issued 8.Possibly appeal lodged 9.Commencement notice submitted 10.Commencement date fixed

Planning services Strongly encourage boroughs to host generic guidance and forms on their websites and develop borough specific guidance and forms (if necessary). If not already, boroughs should start communication regarding CIL through developer forums, the Pre App process and planning application correspondence. Essential boroughs are clear what and when CIL material should ideally be submitted. Important the development industry familiarise themselves with the requirements and processes.

Exchequer services Bill / Demand Notice issued – possibly in instalments Payment received Land charges notified at all stages CIL income transferred to Infrastructure Finance Group or GLA Non payment – Exchequer Services and Planning Services Function Recovery action commences Reminder Summons issued Liability order and costs issued Recovery action taken Stop Notice process (Planning Service Function)

Delivery Transfer Mayoral CIL to GLA Infrastructure Finance Group Manage and monitor CIL and Section 106 income Assign income to prioritised Infrastructure Delivery Plan projects / Capital Programme Transfer money to external parties / providers Monitor delivery of projects

Planning services Authorities Monitoring Report Annual demand Annual Collection Annual Spend Annual schedule of infrastructure delivery Updated Infrastructure Delivery Plan published Unspent CIL Outstanding CIL Collection

Collecting authority Liable Party Developer/ Land owner) Submit Notice of Chargeable Development Submit Assumption of Liability Notice Receive Assumption of Liability Notice and acknowledge Issue Liability Notice Receive Liability Notice (consider appeal) Submit Commencement Notice minimum (1 day before commencement) Receive Commencement Notice and acknowledge Issue Demand Notice Receive Demand Notice Commencement development and start making payments Receive payments and issue receipts for each one received Collection Flow Chart Receive Notice of Chargeable Development Planning Application Grant planning permission Determine the deemed commencement date Submission of relief forms / Instalment policy engaged

CIL Collecting Authority - Position Mayoral CIL – April Liability Notices - £1.1m 9 Demand Notices - £74k No formal enforcement action Additional thoughts Relief protocol Monitoring commencement when no commencement notice Don’t forget PD is CIL liable Pre CIL introduction Section 106 pressure

Key Messages –Boroughs should provide guidance –All necessary documentation should be on the borough’s web site –CIL must be integral to pre application discussions –Submit required information with the planning application and in accordance with the desired process –Make clients aware of CIL –Corporate support for CIL implementation essential