TS3 preparatory meeting 6.11.2015 A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.

Slides:



Advertisements
Similar presentations
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

André Augustinus 16 June 2003 DCS Workshop Safety.
TS1 preparatory meeting A.Tauro. General information TS1 week 25: 15 to 19.6 LHC beam stops on Monday morning at 6:00 AM. Cavern access starts.
MEF - Machines & Experimental Facilities Technical Stop #4 29 th August - 2 nd September 2011 Summary Julie Coupard Schedule and Coordination LHC-TS4 -
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
May Exp-Area meeting1 Safety Systems Installation status Flammable Gas Detection System Fire Detection System in SG8 ODH Detection System CO2 Detection.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 7&8 A.Tauro
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
DCS - general Unscheduled power cut Wed. morning ( , human error) –DCS (and HLT) off, due to UPS on bypass –In the middle of DB migration, had.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
LS1 planning meeting Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
EN-CV interventions during YETS
ALICE TC meeting – Plans for the next technical stop A. Tauro.
André Augustinus 9 October 2006 Interlocks update.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
Muon Tracking Meeting SOR issue First priority Diagnostic: MCH DetectorScriptError Arriving at the initialization stage: the whole or part.
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
TC meeting P2 planning wks 9&10 A.Tauro
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
24/03/2010ALICE TOF General Meeting March TOF hardware and data taking 2010 Andrea Alici Museo Storico della Fisica e Centro Studi e Ricerche “Enrico.
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
ALICE TC Meeting – CV Detcool1 LHC stop 31 May, 1-2 June – CV/DETCOOL Interventions Cavern interventions: 31 9:15: Sampling with RP.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
E Ethernet C CAN bus P Profibus HV HV cables LV LV cables (+busbar) S Serial (RS232) Signal cable Other/Unknown Liquid or Gas Cable and/or Bus PCI-XYZ.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
Claudio Bortolin. pump: replaced outlet filter: replaced demineralized cartridge: replaced mechanic filter on air control: replaced SSD chilled water.
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
André Augustinus 13 June 2005 User Requirements, interlocks, cabling, racks, etc. Some remarks.
TC meeting P2 planning wks 3&4 A.Tauro
CALO News Pascal Perret LPC Clermont 22 January 2012.
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
DCal-ALICE integration and installation plan and status A. Tauro.
André Augustinus P2 events & perturbations 07 May 2010 ALICE Technical Coordination Meeting.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
EYETS planning A.Tauro.
ALICE 5 o’clock meeting Wk 51.
TS2 preparatory meeting
Safety Systems for ALICE
Update of MVD services and requests
LS1 planning meeting
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
ALICE TC meeting – Plans for the next technical stop
LHCb & EYETS
ALICE 5 o’clock meeting Wk
November technical stop activities:
Presentation transcript:

TS3 preparatory meeting A.Tauro

General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00 AM. Cavern access starts at 9:00 AM, after the RP check. – Switch off both magnets: 6:00 AM  SL – take out interlock keys – RP check: 8:30 - 9:00  Andre Access mode: automatic restricted (with token) The underground access will stop on Fri at 16:00 PM Tunnel access (around P2): from Monday midday to Friday midday. NO access to triplets area (ADC) 28/08/15TS3 preparatory meeting2

UX25 access Access possible from Mon 9:00 to Fri 16:00 except the following slots: – UX25: Wed between 6:00 AM and 8:00 AM: siren and evacuation button test (GS-ASE) Fri between 6:00 AM and 8:00 AM: cavern lift maintenance (EN-HE) – L3: Mon between 9:30 AM and 11:00 AM : confined space course – Miniframe: No access  check with Arturo 28/08/15TS3 preparatory meeting3

Detector activities ITS: services verifications TPC: – laser maintenance – access a few IROCs on the upper A side to make sure the HV connection is ok (half day) MCH: – change one quadrant on station 2, CH3L (Indian colleagues) – change few slats: one on CH5L and others on CH7R and CH8R (if possible) – Nacelle needed on I-side MTG: minor maintenance activities foreseen: – one noisy trigger cable. A diagnostic in-situ is needed but we'll probably have to replace the connector(s) – one faulty FE card. We'll need to open MT12-outside in order to access the card and then we'll probably install a spare (from nacelle or scaffolding) – (PH-DT): replace membrane on gas pump (switch to spare, stop 20’) 28/08/15TS3 preparatory meeting4

Detector activities PHOS: – Dismount the PHOS STU, change the SIU card and mount STU back, then test the fiber connection – Hopefully for the task we (2-3 person) need 1-2 days access to L3 (9.11 afternoon and are preferable) EMC/DCA: – Check FECs and TRUs – Install the SRU cooling prototype (Wed) – We need at least 3 days (6 shifts) of access, if possible, and a watcher will be provided, if needed Т0: minor maintenance activities foreseen – Investigation problems in restore_after_ramp (access to C-racks) CTP: change INT board 28/08/15TS3 preparatory meeting5

Detector activities TOF: – Rack O30 to be checked by EN-EL (two PSs and one notch filter in this rack found damaged) (with Andre) After this intervention: – check/replacement of CAEN 48V Power Supply A3485A – Install two CAEN notch filters NF3000 – Three HV connectors to be reworked inside L3 (sectors A-03 and C-12). Welding needed: smoke detection off? – Replacement of 3 DCDC converters in sector C-05, C-10 and C-16. – Finalize Ethernet redundancy (connect power supply) TRD: routine checks and maintenance operations (outside L3) – Cleaning cooling pipes of some Wiener PS (access to galleries I and O side) – Routine check of all Ethernet switches and MUXes (access to galleries I and O side, and C-area) – Inspection of optical fibers at the GTU (access to C-area) 28/08/15TS3 preparatory meeting6

L3 access Watcher in bold 28/08/15TS3 preparatory meeting7 MonTueWedThuFri AM shift (9:00 – 12:30) PHOS/DCA /TOF DCA/PHO/ TOF DCA PM shift (13:30 – 17:00) PHOS/DCA PHOS/DCA /TOF DCA/PHO/ TOF DCA

EN-CV-DC activities TS3 28/08/15TS3 preparatory meeting8 TaskDaysSystem affectedComment Filling of the systems10/11/15 morning SSD/SDD – TPC – TRD - TOFFilling in run Replacement of the mixed flowmeter and valve 10/11/15 afternoon HMPIDWill stop the system Check of the filtration loop 11/11/15TRDReplacement of the demineralized cartridge if necessary Visual check + swap of the circulation pump 11/11/15SPDNeed to be discussed Replacement of communication modules 10/11/15AllWILL STOP COOLING PLANTS HALF DAY – MON PM

DCS Usual maintenance (implying restart of all projects) on the Monday morning (09h-13h). In addition we request (again as usual) a test with all detectors (ramp up, ramp down, simulated handshake etc.) towards the end of the TS to be sure nothing was 'broken'. 28/08/15TS3 preparatory meeting9

Other activities SPIE: complete connection work on one box (work not completed in TS2) ? Vibration measurements (tbc) Sarvadon: acoustic wall L3 power converter (SX2) EN-HE: install crane electronics (Mon AM) + load test cavern cranes (Tue, half day) EN-HE: VIC lift replacement (Tue 9:30, no interruption) TE-VSC: GIS table inspection IT-CS – (+Arturo+Andre): inspection cabling work inside L3 – Mon 9:15 – TETRA measurements on air in ALICE cavern (UX25) and PX24 lift GS-ASE: – Maintenance fire detection systems – Maintenance gas detection systems (SG2/CR5/UX25) – Mon, no impact for ALICE – SNIFFER maintenance – Mon, no impact for ALICE 28/08/15TS3 preparatory meeting10

Other activities EN-CV: – Maintenance ‘puisard eaux usees’ – Replacement belt on UAPX-282 – Test alarm on all ventilation units: uapx (PMD), uapx (MCH1-2), uapx (MCH ST3+MTG), uudc (extraction MCH ST4-5), uudc (extraction MTG) – (with SPIE) Inspection routing ITS ventilation pipe (installation in YETS, week 3) EN-EL: – Install cables new PX24 lift (tbc) – UPS battery test: 1.UPS transfer Off-line = transfer to Bypass source with no interruption (but battery backup still available thanks to 2nd UPS in operation) 2.Firmware upgrade 3.Preventive maintenance 4.Battery measurements 5.UPS transfers back ON-line once preventive maintenance completed 28/08/15TS3 preparatory meeting11

Activities – P2 tech Philippe: – Install one DCal SRU cooling prototype (top A-side) - Wed – Install 4th air duct PHOS SRU crate + inspection with SPIE for final solution – (with Arturo/Albin and if needed Viktor) install the main N2 line inside L3 up to ITS manifold C3 Arturo + Elisa: visit PP4 Yannick: check TPC transfer rails 28/08/15TS3 preparatory meeting12

Visits No underground visits TS3 28/08/15TS3 preparatory meeting13