A Gallagher Oct 2015 Electrical Integration MPB October 2015.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Andrea Paoli AdV 1 st Project Review Cascina, November 3 rd, 2008 IME – infrastructure modifications for environmental noise reduction.
Power Supply System John Joseph LBNL Spectrometer Solenoid Test Plan Review Feb 17 th 2012.
Focus Coil Update Roy Preece / Tom Bradshaw / Mike Courthold STFC – RAL VC 17 th Jan 2013.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
1 Preparation for MQXF Short Model Tests G. Chlachidze Fermilab.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
The 23 rd MICE Collaboration Meeting -1- ICST/HIT Jan.13 to 17, Harbin/China Large Prototype Coil Test and Plan Fengyu Xu Institute of Cryogenics.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
Proposed Design and the Operation of a Disconnecting Device for Small EG Installations Prepared by Hendri Geldenhuys.
During a mains supply interruption the entire protected network is dependent on the integrity of the UPS battery as a secondary source of energy. A potential.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
MICE Hydrogen Control System MICE H2 Review Meeting RAL 15 th Jan 2015 PJ Warburton – STFC Daresbury Lab.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Active Safety Systems + EHN1: Draft EN/EL proposal for replacement of Nano PLC 1.Current situation 2.Requirements definition 3.Current solutions (Atlas/CMS)
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
Instrumentation and Controls Test Plan Review 17 th February 2012 Roy Preece (STFC RAL)
Electrical & Control Power Supplies Trevor Hartnett.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Superconducting IR Magnets CHEN, Fusan May 11, 2007.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
MICE Hydrogen Control System MICE Safety Review Meeting 4 th Oct 2011 PJ Warburton - Daresbury Lab.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 Mice Collaboration Meeting CM28 Bankya Palace Spa Hotel, Sofia, Bulgaria 3 rd -8 th Oct 2010 Daresbury Laboratory Spectrometer Report Authors : Ian Mullacrane.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
World Leaders in Combustion Management Solutions Module Gas Setup Introduction The Mk7 E.G.A Cell Status Further Information.
The D50 Is a state of the art environmental monitor using only the best quality components available. It offers multiple sensors in a single unit with.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
CM 28 – 6 th October 2010 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
MICE Power Supply System John Joseph LBNL Spectrometer Solenoid Controls & Monitoring Review Dec 11 th 2012.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
MICE Spectrometer Solenoids Step IV running
S A Griffiths CM42 June 2015 Electrical & Control.
Electrical Configuration and System Protection
S. Feher MICE Magnet Readiness Review RAL, June 28th, 2016
Considerations from machine protection and the ELQA teams
ARAC/H/F Air-cooled water chillers, free-cooling chillers and heat pumps Range: kW.
D1 and D2 powering and protection
Electrical & Control.
Project Manager’s Report + DC/MoM Report
LV Safe Powering from UPS to Clients
Focus Coil Quench Detector
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

A Gallagher Oct 2015 Electrical Integration MPB October 2015

A Gallagher Oct 2015 Rack Room 2 – UPS Inverter and Batteries 2 UPS for Critical Load Two 30kVA UPS (inverter) including infrastructure have been installed and commissioned. These support Control, Power Supplies, Vacuum and Instrumentation in RR2. Batteries The 2 x 30kVA UPS operate in parallel and share a common battery pack.

A Gallagher Oct 2015 Rack Room 2 – UPS and AC Infrastructure 3 US Voltages – 208/110V UK Voltages – 400/230V All the electrical infrastructure for Step IV has been installed and Certified as compliant with Electrical Regulations Transient suppression installed to protect equipment and a power quality system is available to monitor the integrity of supply Separate distribution for UK and US voltages

A Gallagher Oct 2015 MICE Hall – Functional Earthing / Grounding 4 50mm x 6mm Busbar North, South & West walls 25mm x 3mm Busbar NE corner 25mm x 3mm Busbar in main trench Electrical Functional / Safety Earthing has been enhanced in the MICE Hall with the installation of a 50mm x 6mm copper busbar. Additional busbar earthing has been installed under metal floor to improved equipotential bonding. Bonding to support structures, cable management and steel plates has been significantly improved. Earth bonding between the MICE Hall and RR2 has been enhanced with copper busbar connected between the 2 areas and the cable management is now appropriately bonded. 70mm 2 earth cables have been installed between each magnet and the main earth busbar located on South wall.

A Gallagher Oct 2015 RR2 Layout – Rack allocation 5 SS Power Supply racks FC & SS Control & Instrumentation racks FC QD System rack Auxiliary rack (Tracker & Diffuser) SS ground fault protection rack SS QD System rack FC Power Supply rack Oxygen Depletion System rack

A Gallagher Oct 2015 FC & SS Instrumentation & Control Racks 6 All Instrumentation cables have been installed and terminated All magnet temperature sensors checked, some sensor issues have been identified on the SS magnets. Temperature curves programmed for FC. Temperature curves for SS still to be finalised – some issues sourcing the calibration data. Helium level sensors measured and checked for SS and FC. Anti-icing heater commissioned for FC – reliability issues need to be resolved Fans for anti-icing on SS fixed to magnet and terminated – reliability issues need to be resolved. Pressure heaters commissioned for FC. Pre-cool heaters for SS commissioned. Main pressure vessel regulation heaters for SS commissioned. Racks installed in RR2

A Gallagher Oct 2015 DC and Instrumentation cables 7 5 DC link boxes have been installed in MICE Hall. 240mm 2 and 70mm 2 cables have been installed from RR2 to link boxes. 95mm 2 and 70mm 2 cables have been installed between DC link boxes and magnet local termination point. DC link boxes will enable the FC and SS to be changed from Solenoid to Flip mode and vice versa. All control interfaces for FC have been relocated to the top of the North side for convenient access. Cables have been installed and commissioned for the FC Load cells and are being monitored.

A Gallagher Oct 2015 Quench Detection System 8 SS QD system rack has been installed in RR2 and commissioned with the control system. SS voltage tap cables were installed, but there are still quality issues with the connectors. SSU has been fully trained to 285A and the QD system has operated reliably. SSD has been partially trained, but there has been issues with a broken voltage tap wire and magnet component failure. FC QD system rack has been installed in RR2 and calibrated with magnet. The FC magnet has been operated at 10A, the circuit still needs to be optimised before ramping to nominal current. A full systems check was performed on both QD systems before powering magnets. FC - QD system rack Space allocated for second FC QD System SS - QD system rack

A Gallagher Oct 2015 FC & SS Power Converter Racks 9 SS power supplies have been fully commissioned with control system. Full electrical sign off of all interlocks and controls checked and signed off. Power supplies have successfully provided power for full training of SSU, and partial training of SSD. Solenoid valves fitted to transfer cooling to towns water in case of a fault with the chiller/ air blast unit. Racks installed in RR2 FC power supply has been commissioned and tested. FC power supply has been ramped successfully to 10A, further testing of the magnet is ongoing (114A solenoid mode???)

A Gallagher Oct 2015 SS Power Supply Instabilities 10 Due to the long cable lengths and the bidirectional diode configuration the power supply became unstable once the forward conduction voltage of the diodes was reached. This varied between SSU and SSD due to the difference in cable length, but could be seen at approx. 200A. This was resolved by removing the energy discharge absorber diodes from the circuit as these primary discharge paths are provided by the power supply. The series energy absorber diodes remain in circuit as these maintain a linear discharge rate. SS Match Coil SS Power Supply Rack Long cable length between RR2 and SS magnets Energy absorber diodes are configured to conduct bidirectional

A Gallagher Oct 2015 Upgrade to SS Energy Absorber Diodes Kapton tape used solely as an electrical insulator causes the diode to operate at unreliable temperatures. Adding silicon pads improves both electrical insulation and thermal conductivity, allowing the diodes to operate at a lower temperature. Using only Silicon pads offers the best thermal conductivity, but the Kapton provides added electrical insulation. 11 SS Diode absorbers under test Samples of Silicon Pads tested Original silicon pads utilised caused earth leakage failures due to pressure rupturing of the silicon pockets

A Gallagher Oct 2015 Emergency Off Procedure Emergency Off buttons have been installed on the SS power supply racks. These buttons open the DC contactors and artificially quench the magnet if pressed. Currently there is no alternative way of discharging the magnet energy without software reliance. A report detailing the emergency off procedure hierarchy has been issued and is awaiting agreement. There are options available to remove the reliance on software, which include replacing the AMI 420 with AMI 430 controllers. An emergency off button will also be installed on the FC power supply rack, but this can ramp the current to zero via the AMI 430 controller without quenching the magnet. The natural discharge rate set by the SS circuit parameters will quench the magnet, so the power supplies cannot be disabled. The FC natural discharge rate needs to be investigated to see if it will quench the magnet, additional cable could be installed. 12 Emergency Off buttons installed on SS racks

A Gallagher Oct 2015 Auxiliary (Diffuser and Tracker) Control Rack 13 The tracker control rack has been installed in RR2 to allow ease of access. 2 Control crates have been manufactured for housing in RR2 rack and containing the Canbus modules. Both crates is are completed, tested and in position in RR2. Full system commissioned and verified tracker can be controlled from RR2. However some rack modification required to control AC power to the WIENER cryostat.

A Gallagher Oct 2015 Ground Fault Protection 14 FermiLab designed and assembled the ground fault protection crates. The 2 crates have been installed and tested with the SS circuits. They were used to identify the earth leakage issues on the energy absorber diodes. The system did initially suffer from over sensitivity issues and caused spurious trips. The topology used only works when connected to a circuit which has a relatively high impedance to ground. Unfortunately for the FC magnet the centre of the energy dump circuit is referenced to ground, to minimise the voltages generated during a quench. An alternative solution was designed and implemented for the FC magnet.

A Gallagher Oct 2015 Compressors and Vacuum Rack 15 Extra shut off valves were requested for the SS turbo pumps, these are now operational. Control philosophy for backing line scroll pumps has been finalised and implemented. Hard wired vacuum status provided to RR2. RS232 controls interface for compressors commissioned and operational. Vacuum / compressor rack has been installed and commissioned in North / West corner Some of the FC compressors moved closer to improve cooling efficiency

A Gallagher Oct 2015 Oxygen Depletion System Additional O 2 sensors have been installed at agreed locations. A second controller has been installed to interface with additional sensors. Cable management and cables installation and terminated from RR2 to MICE Hall. ODS rack designed, assembled, installed and commissioned in RR2 The OD System has been checked, sign off and is fully operational. 16 Position of new and existing O 2 sensors Controllers mounted in blister in RR2

A Gallagher Oct 2015 Resource Summary The electrical budget estimates for the end of September were £73k staff and £25k non -staff (contract effort) To the end of September staff costs have been £116k and £50k non staff Non staff costs are twice the expected level as contract effort has been retained. Staffing levels are 38% higher than originally estimated as electrical support during magnet training has been higher than expected. Expected staff budget was £135k however with current cost levels and further scope creep this is expected to rise by £50k. 17

A Gallagher Oct 2015 Questions? 18