LHC Beampipes Ray Veness / AT-VAC FP420- 6 XII 08Beam Vacuum- R.Veness.

Slides:



Advertisements
Similar presentations
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Progress and Plan for Superconducting RF Cavity RF Group.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
T. Montagne LTU – Beam Dump Installation April 16, LTU and Beam Dump Installation April 16, 2007.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
Vacuum system in the main Linacs C. Garion CERN/TE/VSC CLIC09 workshop, October.
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
FP420 Vacuum Ray Veness. Contents o What is FP420? o How would it be installed in the LHC? o What would it look like? o What are the issues/interest for.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
SuperKEKB Vacuum System - for the positron ring - Y. Suetsugu KEKB Vacuum Group Outline Design and production status of key components Beam pipes for arc.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
NLC - The Next Linear Collider Project NLC Beam Delivery Lehman Review, May 1999 Vacuum System Cost Model Presentation by Leif Eriksson.
Peter Spiller, COLMAT-Kick off meeting, Cryo-Collimator, CERN, COLMAT Kick-off meeting CERN Peter Spiller Cryo-Collimator (Catcher) for.
Low Energy RHIC e - Cooling Meeting Minutes – 11/19/14 1. Cooling Section Magnets and Power Supplies –Most of power supplies will be from ERL (R. Lambiase).
23 rd WP8 Bi-weekly meeting Lukasz Krzempek (TE-VSC-DLM) TAS-Q1 – vacuum equipment design.
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
Preliminary View on the LHeC Experimental Vacuum Chambers Jonathan Bosch - University of Manchester And Ray Veness - TE/VSC J.Bosch and R.Veness LHeC -
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
TCLDA Design status Collimation Upgrade Specification Meeting L. GENTINI.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Eric Montesinos - CERN - First SPL collaboration meeting - CERN December 11th 2008 First SPL collaboration meeting Experience with the LHC Main power Coupler.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Vacuum, Surfaces & Coatings Group Technology Department 22 nd January 2015 C. Garion2 Beam Line Interconnection: snapshot of present design principles.
RF power couplers vacuum issues J.M. Jimenez Vacuum, Surfaces and Coatings Group (TE-VSC)
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
MAIN LINAC CRYOMODULE DESIGN REVIEW INPUT COUPLER September 5, 2012V. Veshcherevich.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Technology Department MKP status L. Sermeus, L. Ducimetière TCM 18 November 2014.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
2008/12/10 INFN R&D on Low Impedance Beam Chamber and Components Y. Suetsugu, for KEKB Vacuum Group Contents Introduction Beam Chamber Components Connection.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
1 IPN Orsay / Division Accélérateurs The Spoke cryomodule Vacuum aspects P. DUTHIL on behalf of the IPNO team ESS Lund February 19 th 2013.
Movable beam pipe and NNC Study & prototype development Manchester 14/12/20091D. FP meeting.
1 Workshop on Vacuum System Design for Synchrotron light Source ALBA - Barcelona, Sept New trends in the vacuum design and technology.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Vacuum System P. Chiggiato TE-VSC
Teleconf ACS – FREIA 28th March 2017
CERN – Zanon discussions
Ultra-vacuum components and systems
Alignment of VSC components along LSS 1&5
HFM Test Station Main Cryostat
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
General remarks about the HESR and PANDA vacuum system
Preliminary Y-chamber specifications – First draft
Fast Wire Scanner Prototype Mechanical Design
LHC Experimental Vacuum Systems Status October ‘07
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
FRESCA2 Update on the dipole design and new calculations
CEPC Vacuum System Dong Haiyi 2017/11/5.
Upgrade Strategy for the Experimental Vacuum Systems
XFEL Collimation and Beam Switchyard Vacuum Issues
Discussion on the TDI impedance specifications
XFEL Bunch Compressor BC1 and BC2 Vacuum Issues
BGC Collaboration Meeting –
Presentation transcript:

LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness

Contents o General requirements for LHC room temperature beam vacuum o Vacuum equipment relevant to FP420 o Bellows modules o Instrumentation assemblies o Beam position monitors o TOTEM roman pots (from a vacuum perspective) o Summary FP XII 08Beam Vacuum- R.Veness

FP XII 08Beam Vacuum- R.Veness Key Vacuum Requirements Relevant to FP420 o Physical Aperture o Beam screens on both sides have 34.3 mm vertical and 44 mm horizontal section o Electrical requirements at low and high frequency o Low frequency o The requirement is a function of geometry (diameter, thickness) and material – see spec. o Standard LSS vacuum chambers are 80 mm diameter, 2 mm thick copper o High frequency o Limits on sharp internal profile transitions (15° is standard) o Cavities such as bellows and pumping ports have RF shields (see slide on bellows) o Vacuum / surface requirements o All standard LHC chambers are NEG coated o Materials with high SEY (eg, aluminium, beryllium) must have NEG coating o Some short stainless steel or copper sections do not have NEG coating o All standard sections are baked to 250  C to activate NEG o Some short lengths are only baked to ~150  C to de-gas water o Designs and Materials o All designs and materials used for forming part of the LHC beam vacuum system must be approved by AT-VAC, and acceptance tested before installation o This includes ‘standard’ materials such as stainless steels

Warm Vacuum Functional Specification FP XII 08Beam Vacuum- R.Veness This specification is being revised, but contains more information on many of the main requirements for the LSS vacuum system

Room temperature Bellows modules o Bellows Concept: o Designed to be modular, composed of o body with flanges and bellows o Removable copper inserts with Cu-Be RF contacts o 100+ variants for the ~1600 installed in the LHC machine o Design o Standard LSS bellows are all RF screened o Some exceptions, agreed with Accelerator Physics group, with special designs for LHC experiments (see next slide) o Bakeable to 250°C o Standard bellows units are not NEG coated FP XII 08Beam Vacuum- R.Veness

Non-standard bellows for LHC Experiments o Justifications to date o Special request from the experiment for minimisation of material close to the interaction point o Examples in all 4 large experiments o Limited transverse space, leaving no room for implementation of RF contacts o Inside the ATLAS calorimeter o There are ~25 such bellows around the 4 large LHC experiments o Procedure o Derogation to install given by the Accelerator Physics group leader o Design a bellows according to vacuum group guidelines to minimise impact on the machine FP XII 08Beam Vacuum- R.Veness

FP XII 08Beam Vacuum- R.Veness Vacuum Instrumentation Functional Requirements o Separate the cold and warm vacuum sectors o Type 47 VAT RF-screened all-metal valve o Different diameters exist in the LHC o Interlock the valve between warm and cold sectors o low and high pressure gauges on both sides of valve o Allow initial pump-out of vacuum chambers o At least one roughing valve per sector o Pump non-getterable gasses in the warm sector o Ion pumps on the warm side of the valve o Diagnostics for vacuum status o Low pressure gauges and gas analysers installed where required o Mechanical flexibility o Lateral offsets for alignment of objects o Axial compression during bakeout of warm sector (7m chamber) o Bellows on both sides of valve o Safety o Over-pressure rupture disc o Detection of beam obstacles o Reflectometers installed in some places

Beam Position Monitors o General o Fulfill all vacuum requirements PLUS beam instrumentation o Solid stainless steel body o Bakeable, but not NEG coated o 4 button electrodes o A number of variants for the LHC warm sectors o Mounted on rigid, alignable structures with survey targets FP XII 08Beam Vacuum- R.Veness

FP XII 08Beam Vacuum- R.Veness TOTEM Roman Pots were designed in close collaboration with the vacuum group

FP XII 08Beam Vacuum- R.Veness

Roman Pot Bakeout FP XII 08Beam Vacuum- R.Veness

Summary o Requirements o The LHC beam vacuum has many inter-linked requirements with accelerator physics, beam instrumentation, cryogenics, magnets etc o There is close control on anything that may impact on the LHC performance or reliability o LHC Vacuum components o There are many variants of ‘standard’ vacuum components in the LHC o They have all been designed, produced and tested according to the same strict criteria o Non-standard components o A number of non-standard components are installed, mainly related to the LHC experiments, but: o Make sure first there is not something that has already been developed and tested that can do the job o Be prepared to defend the justification for installation, and the impact on the machine FP XII 08Beam Vacuum- R.Veness

Additional Material FP XII 08Beam Vacuum- R.Veness

FP XII 08Beam Vacuum- R.Veness Vacuum Schematic eg LHCLSVI_0014 Drawing STDVTGS_0001 explains symbols