WP 17.1 Civil Engineering Platform height / 442.0 vs. 443.5 option Status on 18.03.2016 M. Manfredi on behalf of WP17.1 team.

Slides:



Advertisements
Similar presentations
Construction Damage & Prevention Construction damage is one of the greatest causes of tree death and decline in urban areas. Presented by: Courtney Blevins,
Advertisements

Project Planning: Assembling a Mortenson “Integrated Work Plan”
Big Pond Tank Mobile, Reusable Construction/Frac-Water Storage.
Earthwork Operations & Equipments
Foundations and basements
If we don’t use the Quantm system we won’t get the best alignments Queensland Department of Main Roads, Australia.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
CE 486 DEEP COMPACTION Name : Ali Hamood Al-teeb. ID :
 Embankment Construction – LOTs  What is the maximum length of a LOT? Mainline pavement lanes, turn lanes, ramps, parking lots, concrete box.
PILE FOUNDATION BY-.
SOIL, GEOTECHNICAL ENGINEERING AND FOUNDATION ENGINEERING
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
Foundation Engineering CE 483
John Osborne GS/SE March 2013
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Topic B2 Sub-structure groundworks
1 7. R EPETITIVE C ONSTRUCTION Objective: To understand how production and production rates are affected by repetition of tasks, and to learn how to plan.
Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History.
Lecture 2 Introduction to Earthmoving
19 February Summary: Updating on the activities completed (Done) since the last meeting List activities on going (Next steps) and related Actions.
Preparing Foundations for Cylinders & ASME Tanks
Soil and Earth Works Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lecture 3 - Week 2 2 nd Semester 2008/2009 UP Copyrights.
Specification & Quantities Estimating Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
09 July EHN1 civil engineering project status (JUNE) Summary: Updating of the activities carried out on-site (Done) in JUNE List activities on going.
06 August EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
Modern GROUND IMPROVEMENT TECHNIQUES FOR HIGHWAYS
22 October Summary: Updating of the activities carried out on-site (Done) in SEPTEMBER List activities on going (Next steps) and scheduled for OCTOBER.
Foundation Loads Dead Load Live Load Wind Load
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
FHI 32: FCC tunnel layout and transferline update Tuesday, 9 February 2016 CE Updates: Comparison of 100km Intersecting and Non-Intersecting options New.
MDI 9 th Meeting - 22 nd January 2016 FCC Experimental Caverns - Feasibility and Excavation C. Cook (GS), J. Osborne (GS),
Infrastructure and Operation meeting 20 th January 2016 Amberg’s Report Summary : Comparison of 100km Intersecting and Non-Intersecting options C. Cook.
Survey Meeting John Osborne, CERN 8 February 2016
ICARUS Collaboration Meeting Dec A. Scaramelli.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
BUILDING CONSTRUCTION
Proposal for rerouting of buried electrical networks and optical fibres at Point 1 LS2 Committee meeting S. Bertolasi on behalf on EN/EL WP17.2 HL-LHC.
SANKALCHAND PATEL COLLEGE OF ENGINEERING,
FOUNDATIONS.
BULDING CONSTRUCTION ( )
DESIGN OF AIRPORT TERMINAL AND CONTROL TOWER
Pieter Mattelaer (SMB-DI)
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
10 December Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER.
WP 17.1 Civil Engineering Point 1 - Networks LS2 COMMITTEE – CERN – Pieter Mattelaer (SMB-DI)
Deep Residential Basement, Chelsea. Toureen Plant Toureen Plant Toureen Contractors City Basements Groundworks RC Frames Groundworks RC Frames Petrol.
25 June EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going.
AIRPORT SURVEYS.
Leads Institute of Technology & Engineering
A.D.I.T New V. V. Nagar Branch : Civil Engineering (5th semester) Subject : Soil Mechanics ( ) Topic : Cofferdams Prepared by : Tina Naik ( )
Substructure Groundworks - Hazards
Jet grouting underpinning of a building on a marl embankment platform
SMR 21/09/2017 P. Fessia.
In the Name of Allah The Most Beneficent & Merciful
SOIL, GEOTECHNICAL ENGINEERING AND FOUNDATION ENGINEERING
Types of Protection Introduce the module. Trenching & Excavations Continuing Education Third Quarter 2017 Session 2.
CE Status: Activities executed until 03/08 and ongoing
EHN1: CE Integration process updating
EAG346-Sem II 2014/2015 Lesson 2.
B.V.Patel Institute of Technology-Diploma studies
East Hall under construction
CT Reinforced Earth Structures
REVISION 1 1. Foundations.
Construction Considerations
6th. Semester Schedule: 1st. Week
Presentation transcript:

WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team

WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on BASELINE OPTION BASELINE OPTION: Horizontal platform at 442.0m

 Construction of a retaining wall (~45m long) adjacent to the access road, close to SD building;  Power lines and OF buried networks to be diverted (EN-EL). 3 BASELINE OPTION BASELINE OPTION: Horizontal platform at 442.0m Cost: Impact: 1.Retaining wall (45m long): 40 KCHF; 2.Networks deviation: see EN/EL slides on indicoindico Creation of a no-go zone for CE equipment beyond the wall to protect buried lines; Easy access to and from Atlas site (transport); All ‘risks’ linked to the deviation of networks can be anticipated and managed before HiLumi civil works commence. WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on Deviation path TBC by EN/EL

4 ALTERNATIVE OPTION ALTERNATIVE OPTION: Additional platform at 443.5m WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on

5 ALTERNATIVE OPTION ALTERNATIVE OPTION: Additional platform at 443.5m  Raise the surface level of all buildings, but bottom level of foundations is fixed (to stay in good ground conditions); Thus, higher foundations are needed;  Power lines and OF buried networks won’t be touched. Cost: The process to estimate the ‘extra’ costs, w/ respect to the baseline option, is identified below: 0.Baseline lay-out w/ buildings at 442.0m. Platform created w/ excavated ground material WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on Assuming shallow foundations to be executed

6 ALTERNATIVE OPTION ALTERNATIVE OPTION: Additional platform at 443.5m 1.All buildings raised to 443.5m (see example of SHM). 2.Need for 1.5m of fill material to reach higher platform level. Backfilling w/ compacted material under the building footprint Backfilling w/ excavated site material WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on m

7 ALTERNATIVE OPTION ALTERNATIVE OPTION: Additional platform at 443.5m 3.We assume building foundations at the same level as for 442m platform. 4.Excavation w/ support system up to the correct foundation level (Δ=1.5m). WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on m

8 ALTERNATIVE OPTION ALTERNATIVE OPTION: Additional platform at 443.5m 5.Execution of higher concrete foundations (Δ=1.5m). 6.Final backfilling along foundations and technical galleries. WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on m

9 ALTERNATIVE OPTION ALTERNATIVE OPTION: Additional platform at 443.5m Cost (*) : Related to raising the level of all HiLumi buildings  Earthworks and filling w/ on-site material up to level:  Cost reduction for reduced soil volume exported from CERN site:  Earthworks and filling w/ compacted material up to level:  Excavation w/ temporary soil support system (Δ=1.5m):  Execution of higher concrete foundations (Δ=1.5m):  Final backfilling along foundations and galleries: TOTAL (*) : 160 KCHF -270 KCHF 235 KCHF 395 KCHF 695 KCHF 100 KCHF ≈ 1’315 KCHF WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on (*) Lowest possible cost, based on the foundation scheme considered. Costs can easily being much higher if deep foundations need to be executed instead. Consultant will determine whether or not deep foundations are required.

10 ALTERNATIVE OPTION ALTERNATIVE OPTION: Additional platform at 443.5m Risks: Issues in getting the Building Permit application approved due to the higher platform (pyramid effect, buildings too visible from all perspectives) Shallow HV power lines and OF networks close to SD and SHM footprint. Unsafe and uncontrolled conditions during the 5 year long CE worksite area. Heavy CE machinery will be used by contractor or sub- contractors. Accidental damage to networks cannot be excluded and is likely. Big consequences (time, cost) on the LHC operation in case of fault. WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on m deep 443.5m Sensitive Area !! Strategic Power lines and Optical fibers for CERN-LHC machine below 1.5m of soil, during 5 year long CE worksite area Let’s start to excavate the SD building foundations Deep / piled foundations might be necessary to reach good ground conditions => Higher costs for HiLumi buildings. Transport issue to access the HiLumi site from ATLAS via long and moderately steep ramp. 1.5m soil protection might be not sufficient: earthworks with heavy machine will be carried out nearby (compression and decompression ground effect). Additional costs linked to temporary protection might be necessary. From a construction pov, the necessity to create such a large 2 nd platform and raise all new buildings to avoid a deviation of local networks is difficult to defend.

WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on Risk Comparison Risk Comparison: Platform at 442.0m vs m Topic442.0 platform443.5 platform Scope of civil works More limitedMore significant Interface riskDiversion of networks before civil works start, no overlap or interface Complicated interface, e.g. existing networks need to be protected when HiLumi buildings are constructed very nearby (≈2m) Extent of riskLocalized (the places where lines will be cut & jointed) Along entire length of SD17 and partially SHM17 Duration of riskFew days (only during cutting & jointing of networks) Years (during the civil works on HiLumi site ) Risk managementRelatively easy - limited interface between networks and civil works Very difficult - impossible to ensure ‘precision’ with heavy CE equipment Risk levelRelatively controlled risks associated to re- routing of existing networks Uncontrolled risks related to contractor’s care on site ≈ network damage is likely Impact on building permit Base caseAdditional platform may negatively impact application Cost (SMB + EN-EL)≈ 560 KCHFMIN. ≈ 1315 KCHF

Back-up slide WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on

WP17.1 Civil Engineering / Platform height / 442.0m vs m option / Status on