09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.

Slides:



Advertisements
Similar presentations
LCW Upgrades Update Booster Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions were.
Advertisements

LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
The MICE Target Lara Howlett University of Sheffield.
F.G. Garcia X37981 chopper Linac cable tray Cable penetration Overall View from the Linac Bridge Beam direction.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
MTA Installation Progress Report June 8, MTA Installation Web Page F.G. Garcia AD/Proton.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
A. Bross MTA RF WS August 22, Welcome MTA RF Workshop.
Robert Ruland Intra Girder Assembly and Alignment - October 20, 2005 Internal LCLS Undulator Alignment and Motion Review 1 Intra.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
LINAC LASER NOTCHER READINESS REVIEW August 5 th, 2014 Kevin Duel – Mechanical Support Engineer.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
Preparation for May-2013 Review of UCN Beamline March 27, Date: May 2-3, 2013 Review Committee finalized Scope – Overall concept, focusing on 2014.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
The Stripping Foil Test Stand in the Linac4 Transfer Line
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
19 Dec 2007Water manifolds for FD magnets 1 Installation Questions abut the cooling water manifolds for the FD quads& sextupoles. Questions for Araki,
Booster L12/Noker-L13/Absorber Update PIP Update Talk August 15, 2012 Salah Chaurize.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
MTA Installation Meeting March 7, 2007 Agenda 1)Progress report (Fernanda) 2)Water skid discussion (Maurice) 3)Alignment needs (O’Sheg + all) 4)AOB Key.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
MEF - Machines & Experimental Facilities March 2013 Project meeting Activities in Linac4 tunnel and building in 2013 March 2013 Project meeting 14/03/2013J.Coupard1.
MTA Installation Meeting February 21, 2007 Agenda 1)Progress report (Fernanda+Carol) 2)Floor Plan layout (Fernanda+Larry) 3)AOB Key Red – critical Orange.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
RFQ Installation Status 10/27/2015 October 27, 2015 Jim Steimel & Curtis Baffes.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Operations meeting on FY07 Shutdown Date: June 27, W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Accelerator Installation Plan: Graphical representation E. Sargsyan & L. Lari DRAFT - March March 2016.
Shutdown Update Switchyard - Neutrino Muon MTest - MCenter Michael Geelhoed 2/22/13.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Status of Mechanical Design of LEBT Rich Andrews, Matt Alvarez, Tim Hamerla, Danny Snee.
Two-beam module layout
S A Griffiths CM42 June 2015 Electrical & Control.
Teleconference ACS – FREIA 31th May 2017
CBETA Technical Review
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
IHEP Cryomodule Status
Two-beam Test-stand Design and Construction Status
APTM and GRID interface requirement PBIP and PBW
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
SC1R Cold Box PDR Assembly Sequence
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week 7) MTA – Week5

09/21/07Shutdown’07 Week 7 F.G. Garcia2 MTA Weekly Report – Week 7  Electrical Work Cable pull complete  Termination of load cables ongoing (50%)  Termination of the instrumentation cables ongoing (gallery and tunnel) Interlock box installed and electrically terminated Next week: Finalize cable termination and instrumentation connections  Alignment Beam line has been rough aligned Some issues were revealed:  Magnets stationing of most components were unsatisfactory Quadrupole magnets were repositioned and realigned  Cause: installation error CDA magnets still need to be repositioned and realigned  A new nominal values were released for these magnets Beam sleeve thru the shielding wall has been aligned AMG started referencing the MW cans. Next week: - Aid on the adjustment of the CDA magnets station - Continue referencing the MW cans

09/21/07Shutdown’07 Week 7 F.G. Garcia3 MTA Weekly Report – Week 7  LCW work System was hydrostatic pressure tested Water techs are fabricating hoses and fittings Next week: Start making hose-connection between the manifold and magnets  Vacuum work Spool piece progress was delayed due to problems with magnets stationing  Quadrupoles spool pieces resumed middle of the week MW cans assembly ongoing Next week: Finalize the spool piece connections Receive and install the MW vacuum cans Start roughing vacuum by the end of the week

09/21/07Shutdown’07 Week 7 F.G. Garcia4 MTA Weekly Report – Week 7  Mechanical installation Beam stop mechanical parts have been delivered from the machine shop  Currently parts have been cleaned  Final assembly started Next week: Install the beam stop (upstream)  Shielding installation Shielding added around the beam pipe sleeve Gathering material to complete the shielding requirements in the utility penetration Next week: Finalize the shielding requirements for beam operation in Linac.