Preliminary Engineering Analysis and Design Foxcroft Colony and Mosby Woods Condominiums Prepared for: City Council Work Session November 3, 2015.

Slides:



Advertisements
Similar presentations
County of Fairfax, Virginia Department of Transportation Review and Discussion of Draft Scope of Work for Study of Issues Associated with Increasing Transportation.
Advertisements

City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting November 19, 2012.
18 October 2012 WATERSHED Science & Engineering WEST Consultants Chehalis River Basin Hydraulic Modeling and Flood Relief Alternatives Evaluation.
Southside Flood Protection Red River Channel Extension Clay County Courthouse September 8, 2008.
A flood occurs... Any time a body of water rises to cover what is usually dry land.
May 22, 2012 Charlotte-Mecklenburg Flood Risk Assessment and Risk Reduction Plan ASFPM 2012 Annual Conference Timothy J. Trautman, P.E., CFM Flood Mitigation.
Permanent Protection System Opinion of Probable Cost May 2010 Courtesy USACE Photograph Courtesy USACE.
November 24, 2008 Agenda Purpose of Hearing Introductions Project Presentation Public Comment Period Southside Flood Control.
HSDRRS Wave Overtopping Risk Reduction for Return Events Greater than 100 yr. By: John Monzon, P.E. Flood Protection Division Chief and Rickey Brouillette,
City of Sunset Valley Drainage Master Plan Assessment Final Recommendation Report March 24, 2009.
ROUTE 27 (PARK STREET) CORRIDOR SEWER EVALUATION Mark J. Thompson, P.E. Gus O’Leary Kleinfelder / S E A Consultants Inc.
City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012.
Using Mitigation Planning to Reduce Disaster Losses Karen Helbrecht and Kathleen W. Smith United States: Federal Emergency Management Agency (FEMA) May.
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012.
Federal Emergency Management Agency Map Modernization Project City of Bryan City of College Station & Brazos County, Texas.
Council Bluffs Value Engineering Workshop
South Side Red River Bridge Corridor Study Phase III Preliminary Geotechnical Study Phase IV New Alignment Alternatives Evaluation.
City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010.
1 FEMA Flood Insurance Rate Map Update FEMA Public Meeting October 22, 2009.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
Flood Risk Mapping Project Identifying the Risk Editorial Board Meeting [COMMUNITY NAME] Flood Risk Mapping Project.
Understanding Advisory Base Flood Elevations (ABFEs) Understanding Advisory Information and the Implications for Your Home December 2012.
Risk and Emergency Management Division Southside Hampton Roads Hazard Mitigation Plan.
Floodplains and your Treatment Plant How Hurricane Katrina Is Changing Your Floodplain in Michigan Daniel Schechter, P.E. Greeley and Hansen 1.
Southside Flood Protection
ASFPM – May 24, 2012 CASE STUDY – 408 PERMITTING AND LEVEE ACCREDITATION FOR WATERLOO, NEBRASKA ASFPM MAY 24, 2012 Presented by Randy Behm, PE, CFM Lalit.
Gaviota Beach Road – Transportation Division County Project Summer Crossing – Pre 1997 Located west of Highway 101 Access to Gaviota Beach and Hollister.
US Army Corps of Engineers BUILDING STRONG ® Kansas Citys, Missouri and Kansas Flood Risk Management Project Presentation to Kansas City Industrial Council.
Proposed Benefit Assessment District Overview Three Rivers Levee Improvement Authority (TRLIA) TRLIA.ORG March 10,
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
HAZARD MITIGATION 101 Sandusky County Initial Planning Meeting March 11, 2014.
Back Creek Floodplain SEPTEMBER 2, Why are we here Introductions Almost 300 parcels affected by revised flood study of Back Creek Outline ◦History.
Sewer Relief Project. Basement Flooding has been a major problem for city of Selkirk residents. High intensity summer rain storms can result in extensive.
Resilience Meeting: [Watershed Name] [LOCATION] [DATE]
Flood Map Modernization Flood Map Modernization Mapping the Risk Editorial Board Meeting October 2005 HILLSBOROUGH COUNTY FLOOD MAP MODERNIZATION V
Flood Map Modernization Flood Map Modernization Mapping the Risk Editorial Board Meeting [date] V [COMMUNITY NAME] FLOOD MAP MODERNIZATION.
FEMA FLOOD INSURANCE STUDY UPDATES City Council Workshop July 7, 2008.
Lower Taylor Creek Restoration Project Property Acquisition Seattle City Council - Seattle Public Utilities and Neighborhoods Committee June 9, 2015.
Our Mission MITIGATIONS. MEANING OF MITIGATION MITIGATION IS THE PERMANENT REDUCTION OF THE RISK OF DISASTER MITIGATION IS THE PERMANENT REDUCTION OF.
PICAYUNE STRAND RESTORATION PROJECT PUMP STATIONS PRELIMINARY DESIGN South Florida Water Management District Water Resources Advisory Committee April 6,
05C112011B Template Master – Update Tracking Number and Date Information Here Update tracking number and date on this slide Template Master – Update Tracking.
Natural Hazards Science: Reducing America’s Risk from Floods David Ford David Ford Consulting Engineers.
Yuba County Comprehensive Flood Protection Program
Oakcreek, Copperfield Court, and Coulee’s Crossing Area Flood Risk Management Project City of Fargo Oakcreek, Copperfield Court, and Coulee’s Crossing.
Central Valley Flood Protection Board Meeting – Agenda Item No. 9A CVFPB MEETING – October 25, 2013.
Central Valley Flood Protection Board Meeting – Agenda Item No. 7D Methylmercury Open Water Workplan.
Tempe Town Lake Downstream Dam Replacement NEW DAM ALTERNATIVES SELECTION January 5, 2012.
Suwannee-Satilla Drainage Basin: Flood Control Issues and Requested Action Suwannee-Satilla Regional Water Planning Council Douglas, GA December 8, 2010.
California’s Flood Future Recommendations for Managing the State’s Flood Risk Flood Risk Management & Silver Jackets Workshop August 21, 2012.
APPLICATION NO LEVEE DISTRICT No. 1 Of SUTTER COUNTY STAR BEND SETBACK LEVEE SUTTER COUNTY April 17, 2009.
Planning Commission Study Session: Preferred Plan July 23, 2015.
ACQUISITION OF REAL PROPERTY LOCATED AT 2110, 2222 AND 2244 SOUTH AIRPORT WAY Stockton Redevelopment Agency October 7, 2008 City Council Agenda Item 6.13.
“State Road 100 MPC Lots” Comprehensive Plan Amendment & Rezoning City Council Public Hearing November 17, 2015.
K1 Proposed National Levee Safety Program An Introduction for the Tribal Assistance Coordination Group May 12, 2011.
City of Stockton Levee Flood Protection Status Report January 29, 2008 Agenda Item 4.03.
May 14, Planning Commission Planning Commission May 14, 2015.
ND Downstream Watersheds Comprehensive Detention Planning
Four Winds Condominium Association August 2, 2017
Designing a Commercial Shopping Center
The Oakton Condominium Association September 12, 2017
Design of a Commercial Shopping Center
WEST & EAST DISTRICT PROJECTS PRESENTATION
PROPOSED MARCH LANE / HOLMAN ASSESSMENT DISTRICT
Water Reclamation Plant Feasibility Study Update May 28, 2014
MANAGING YOUR FLOOD RISK All stakeholders contribute to risk reduction
City of Ithaca Local Flood Hazard Analysis
Any time a body of water rises to cover what is usually dry land.
FEMA FLOOD INSURANCE STUDY UPDATES
Delta Water Supply Project
Presentation to Sacramento Environmental Commission May 21, 2018
Presentation transcript:

Preliminary Engineering Analysis and Design Foxcroft Colony and Mosby Woods Condominiums Prepared for: City Council Work Session November 3, 2015

Project History and Timeline City allocated additional funds to continue Initial Feasibility Study to address flooding issues. Preliminary Engineering Analysis and Design Initiated May 2014 Recommendations to address flooding issues presented to City and HOAs. Fall 2014 Public Meetings to discuss recommendations. Spring 2015 Completed Preliminary Design of recommended options. October

Impacted Areas  Based on the FEMA Flood Insurance Rate Maps (FIRMs) for the City of Fairfax: -There are 28 condominium units in 7 buildings at the Foxcroft Colony Condominium complex that are located in the 100-year floodplain and are at risk of future flooding -There are 28 condominium units in 7 buildings at the Mosby Woods Condominium complex that are located in the 100-year floodplain and are at risk of future flooding -Several commercial properties in the vicinity are also located within the floodplain and affected during large storm events 3

Impacted Areas – Foxcroft Colony 4

Impacted Areas – Mosby Woods 5

Work Completed  Continued Feasibility Analysis -Evaluated potential options for improvements -Conducted initial Benefit to Cost Analysis -Held stakeholder outreach meetings  Selected recommendations for improvements  Prepared preliminary plans  Developed preliminary cost estimates 6

Flood Protection System and Pump Station Flood protection system consists of a concrete floodwall and earthen levee in height between 1 ft. – 5 ft. Wall height designed for 25-year storm -Partially located within Pickett Road right-of-way -1 pump station to remove water behind system -New portions storm drain system on property Estimated Construction Costs are about $2.3-$2.7M -Land acquisition is not included FEMA funding is unlikely due to project having a low benefit –to–cost analysis Foxcroft Colony – Recommended Design 7

Foxcroft Colony - Proposed Flood Protection System and Pump Station 8

Concrete Floodwall and Earthen Levee Concrete Floodwall in height between 8 ft ft. Portion on upstream end is earthen levee Designed to meet the 100-year flood elevations -No freeboard provided New storm drain system to bypass flow Scour protection – grouted rip-rap Estimated Construction Costs are about $2.8-$3.3M -Land acquisition not included – City owned land Potential for FEMA funding due to benefit-to-cost analysis near/above 1 Mosby Woods – Recommended Design 9

Mosby Woods – Proposed Concrete Floodwall and Earthen Levee 10

Mosby Woods – Proposed Concrete Floodwall and Earthen Levee 11

Mosby Woods – Proposed Concrete Floodwall and Earthen Levee 12

 Finalize Design -Design Documents o 30%, 60%, 90%, final documents -Construction Permitting -USACE Permitting (Mosby Woods) -Land use agreements -FEMA grant application (Mosby Woods)  Construction -Construct Flood protection systems -Construction Administration/Management Next Steps… 13