LFUCG Group 1 Remedial Measures Plans September, 2011 Presentation to Lexington-Fayette Urban County Residents.

Slides:



Advertisements
Similar presentations
CMOM CMOM Capacity, Management, Operation & Maintenance and Remote Wireless Monitoring of Collection Systems 5 th Annual FVOA Mini Conference August 18,
Advertisements

Bergen County Utilities Authority Bergen County Utilities Authority Little Ferry, New Jersey Rain Derived Infiltration/Inflow Reduction and Sanitary Sewer.
Steve White Urban Water Council US Conference of Mayors
Utah Pollutant Discharge Elimination System (UPDES) Utah Sewer Management Program (USMP)
City of Clinton Fiscal Year 2013 Sewer Rate Recommendations Committee of the Whole April 24, 2012.
City of Berea North End Area Sewer Investigation Project- Phase I Commencing Fall 2011.
Evaluation of Private Property I/I Sources for Sanitary Sewer Evaluation Study City of Grand Rapids – E. Leonard Heights Area Presenter: Jay Zawacki, CDM.
Greeley and Hansen Agenda New Rules For Sanitary Sewer Systems EPA Enforcement Overflow from a Manhole on to the Ground – into a stream, into a basement.
South Maple Street Sanitary & Storm Sewer System Improvements Project October 14, 2014.
Presented by: Agustin Socarras, P.E. Chief, W & WW – Conveyance Section Department of Environmental Resources Management DERM July 31, 2002 Pollution Prevention.
Department Of Public Works Environmental Engineering Section Inflow and Infiltration (I/I) Demonstration Project Sanitary Sewer Lateral Lining 1 City of.
The Metropolitan District Clean Water Project Update Connecticut Watershed Network Conference May 11, 2012.
Fox Valley OperatorsAssociationCMOM Capacity Management Capacity ManagementOperationMaintenance January 2011 C apacity M anagement O peration & M aintenance.
1 Milwaukee Metropolitan Sewerage District Legislative Audit Bureau November 2003.
Collection System Regulatory Initiatives in California SCAP Collection System Committee August 26, 2009 Presented by: Eric Wessels, P.E.
1 TOWN OF NEWMARKET FLOODING ON SEPT. 13, 2006 Committee of the Whole February 5, 2007.
Holden Heights Community Improvement Project Update Orange County Board of County Commissioners December 17, 2013.
Center for Watershed Protection Illicit Sewage Discharges in the Chesapeake Bay 2012 Chesapeake Bay Stormwater Retreat Lori Lilly Watershed Ecologist/Planner.
The City of North Bend Sanitary Sewer System
Utility Extension Project
District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Briefing on: NORTHEAST BOUNDARY NEIGHBORHOOD PROTECTION PROJECT FIRST.
1 Innovative Use of Administrative Order Authority Management, Operation and Maintenance (MOM) Program.
Do You Know Where Your Peak Flow Is?. - OR – Why Everyone Needs to Know About Blending Presented at BACWA Wet Weather Management Workshop May 28, 2008.
An Application in GIS for a Sanitary Sewer Overflow Emergency Response Program Mike Pritchard Penn State MGIS Capstone Project Advisor: Jan Oliver Wallgrun.
- SEWER REHABILITATION - A TEN-STEP STRATEGIC PLAN GEORGE KURZ, P.E., DEE * A significant portion of this work was conducted.
SSES and GIS, A Great Partnership Cindy Fort, PE Technical Director Environmental Engineering and Jeff McCann GIS Coordinator.
Special Order by Consent Wastewater Collection Improvement Projects Mark Fisher and Dennis Asbury Final Report to City of Eden October 20, 2009.
Streamlining Development Permitting March 8, 2011.
Metropolitan Council Environmental Services A Clean Water Agency Presented to the Environment Committee February 9, 2010 Legislative Update: Inflow & Infiltration,
1 Underground Asset Management Jonathan Mongie. 2 Asset Management ► Improved Asset Condition l Increased System Efficiency ► Prolonged Asset Life l Reduced.
Department of Public Works NPDES Low Impact Development and Green Streets Resolutions City Council August 17, 2015.
Waste Water Facilities Plan Update November 2, 2009 Palmer Engineering Company / Hazen & Sawyer / CDP Public Hearing Presentation.
Separating Inflow Reduction From Infiltration Removal Using Simple Tools Frederick Bloetscher, PhD, PE Florida Atlantic University.
1 District of Columbia Water and Sewer Authority George S. Hawkins, General Manager August 29, 2012 Revised August 30, 2012 Operating Agency Workgroup.
Facilities Plan Update July 2, 2009 Palmer Engineering Company / Hazen & Sawyer / CDP.
Suzanne Trevena EPA Water Protection Division Chair Milestone Workgroup December 4,
1 NASHVILLE’S PROGRAM REMOVES 3.6 BILLION GALLONS OF I/I George Kurz, P.E., DEE Gregory Ballard, P.E. (Metro Nashville) Paul.
Charlotte-Mecklenburg Il Problem CE 572 Spring 2006.
1 Discussion Points for IMA Participants – Flow Studies December 19, 2006 District of Columbia Water and Sewer Authority.
All About Sanitary Surveys David Edmunds Environmental Program Specialist ADEC Drinking Water Program Sustained Compliance: What It Means to Public Water.
NPDES Permit Application and Annual Fees NPDES Permits NPDES Permits are issued for the discharge of municipal, industrial, or commercial (non- storm.
1 Briefing for IMA Participants on Results of Flow Studies October 31, 2006 District of Columbia Water and Sewer Authority.
Wastewater Treatment Plant # 2 Engineering Services Council Workshop July 8, 2014.
Status update presentation #1 for the Cayucos Sustainable Water Project Status update presentation #1 for the Cayucos Sustainable Water Project November.
Metropolitan Council Environmental Services A Clean Water Agency Proposed Combined Sewer Overflow Changes Environment Committee March 11, 2008 Keith Buttleman.
Frederick A. Laskey Welcome to the EBC Breakfast Meeting The CSO Program Update Frederick A. Laskey Executive Director Massachusetts Water Resources Authority.
Multi-Jurisdictional-Use Facilities Flow Analysis Study Update Presented to Blue Plains Regional Committee March 24, 2011 District of Columbia Water and.
Veneta City Council Worksession November
March 3, 2016 Discovery Sewer/RWQCB LSM Vallecitos Water District Regional Water Quality Control Board (RWQCB) Lake San Marcos February 10, 2010.
Water System Master Plan & Rate Study City of DeKalb, Illinois City Council Presentation May 16, 2015.
Kevin Colvett, P.E. Nashville Corrective Action Plan and Engineering Report, Phase III for Metro Water Services and the City of Brentwood, TN Presentation.
City of Pacifica 1. Why is this Project necessary? 2 City has a history of sanitary sewer overflows (SSOs) – January 2008 storm caused SSOs throughout.
City of McCall Sanitary Sewer I&I Study Community Stewardship for Economic Benefits Nathan Stewart, PE, City Engineer Matt Neukom, PE, Project Manager.
Budget Study Sessions ENVIRONMENTAL & UTILITY SERVICES Proposed Operating Budget OUTCOMES: -Reliable Utility Infrastructure -Healthy.
Spring 2009 Town Meeting Article 41 East Framingham Sewer Improvement Project (EFSIP) May 2009 Town of Framingham Department of Public Works "Preserving.
FY 2010 Budget Slide 1 Public Works March 18, 2009 Wastewater User Fees Wastewater Collection Proposed RCO Fee Surcharge Recommendation: Regional Consent.
Remedial Measures Plans Response to EQC Questions June 21, 2011 Presentation to Lexington-Fayette Urban County Government Environmental Quality Committee.
Town Branch Wet Weather Storage Public Information Meeting February 19, 2014 Lexington Fayette Urban County Government Division of Water Quality.
Miami-Dade Water & Sewer Department Miami-Dade Water and Sewer Department |  1   Reuse, Every Drop Has Value Seminar FPL JPA.
City of Sausalito Sewer CIP Vivian Housen, P.E. V. W. Housen & Associates March 25, 2015.
Why the Need for Increased Stormwater Funding? Citizens expect a higher level of protection from flooding Increased development.
VILLAGE OF SHOREWOOD PPII REDUCTION PROGRAM. Shorewood’s response to the 2010 flooding has been direct and decisive Immediately start identifying problems.
I/I Reduction Efforts EBMUD and the Satellite Agencies
Update on PI Modeling and Nitrogen Removal at Blue Plains
Separating Inflow Reduction and Infiltration Removal
Manchester’s CSO Program: A Look Behind and a Look Ahead
City of Valdosta Utilities Department.
LHC Outfall Sewer.
Facilities Plan Update
MS4 OVERVIEW 2015.
Presentation transcript:

LFUCG Group 1 Remedial Measures Plans September, 2011 Presentation to Lexington-Fayette Urban County Residents

Consent Decree Background USEPA enforcement action due to violations of Clean Water Act Typical of similar-sized communities Lodging date: March 2008 Entry date: January 2011 Lodging and Entry dates determine specific deadlines

Consent Decree Goal (Wastewater) Primary Goal: eliminate recurring SSOs caused by wet-weather infiltration and inflow Recurring SSO: An SSO that occurs in the same location more than once in a twelve month rolling period.

Watershed Groups Group 1: –West Hickman –East Hickman –Wolf Run Group 2: Cane Run and Town Branch Group 3 – North and South Elkhorn Service area split into groups to prioritize corrective actions

Recurring Sanitary Sewer Overflows – West Hickman

Recurring Sanitary Sewer Overflows – East Hickman

Recurring Sanitary Sewer Overflows – Wolf Run

Typical Sanitary Sewer Defects Leaking Manhole Smoke testing indicates private lateral defects Active I/I in 54-inch West Hickman trunk sewer

Capacity Assessment Findings Group 1

Existing West Hickman Capacity Issues

Existing East Hickman Capacity Issues

Existing Wolf Run Capacity Issues

Capacity Map Summary Model results depicted on maps represent a 2-year / 24-hour storm – minimum criteria for future Capacity Assurance Program (CAP) Orange and red color coding most critical from CAP perspective – limited capacity for infill and redevelopment DWQ is tracking recent and future repairs to acquire “capacity credits” DWQ will continue to monitor flows and maintain hydraulic models

RMP Reporting Schedule Reporting to be by Groups SSSA Reports –Group 1: April 2011 –Group 2: October 2011 –Group 3: April 2012 RMPs –Group 1: October 2011 –Group 2: April 2012 –Group 3: October 2012

Remedial Measures Plans Master plan of physical improvements necessary to eliminate Recurring SSOs Strategies: –Transport and Treat –Equalization (storage of peak flows) –System Rehabilitation to reduce I&I RMP to include combination of all 3 strategies

Proposed West Hickman RMP Charlie – the 39.5 MG EQ at WHWWTP would be about 40’ deep in Commonwealth Stadium. The 2 nd biggest EQ is at Idle Hour Park – 4.4 MG or about 6’ deep in the stadium.

Proposed East Hickman RMP

Proposed Wolf Run RMP

Estimated Costs Current estimates for Group 1 watersheds (excluding system rehabilitation), based on 2-year storm: –West Hickman $193,000,000 –East Hickman $71,000,000 –Wolf Run $33,000,000 Total Group 1 = $297,000,000 Other 4 watersheds expected to be less costly to address Long-term system rehab ($5 million / yr)

Group 1 Construction RMP Preliminary Capital Cost for 2Yr24Hr West HickmanEast HickmanWolf Run ItemQuantity ≤15" (ft) 9,955 17,987 2,679 18"-24" (ft) 34,635 12,614 17,650 27"-36" (ft) 5,925 2,200 10,142 42"-54" (ft) 18, ,368 60"-72" (ft) 3, >72" (ft) Force Main (ft) - 33,359 - Subtotal Pipe (ft) 72,445 66,160 33,839 PS Improvements (MGD) EQ (MGAL) WWTP Improvements (ea) Total Capital Cost ($M) $ 193 $ 71 $ 33

RMP - Public Involvement Conducted 3 public meetings in March 2011 Stakeholder involvement –LFUCG Council, Mayor, Water Quality Staff –Commerce Lexington, Homebuilders Association, media, etc. –Civic and neighborhood associations Web site developed to provide current and future project status updates Separate public meetings for each RMP Group

Long-Term CD Schedule Construction to take place Permanent sewer rehabilitation program

Web Site – now online

Summary DWQ is on track with Consent Decree schedule Remedial Measures being developed to eliminate Recurring SSOs and meet EPA requirements at lowest cost Next Steps: –Solicit public input –Complete RMPs and submit to USEPA –Initiate sanitary sewer improvements

Questions?