CMWG Update to WMS 5-11-09. Met 4/24 & 5/11 Continued Work on PRR 801 –Discussed outages as related to TCR Cases –ERCOT evaluates various outage combinations.

Slides:



Advertisements
Similar presentations
Additional CREs to address Stability Limits Beth Garza TAC June 26, 2008.
Advertisements

Critique of Proposal to Designate SAPS-Shrew as CRE Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) June 4, 2009.
CSC/CRE Technical Review 6 October Outline  Review the process used in calculating Power Transfer Distribution Factors (PTDFs).  Information.
1 Generation Adequacy Task Force Report to TAC April 7, 2005.
CMWG Update June WMS Meeting CMWG Update 1. CMWG (Vote) Confirmation of new Vice Chair: Greg Thurnher (Representing Luminant/TXU Energy) 2.
CRR Update Dave Maggio CMWG July 18, CMWG 7/18/ Transaction Limit Utilization Metrics Discussion on Special “One-Time” Auctions of CRRs Upcoming.
Monthly TCR Calculation DRAFT 3 James J. Teixeira 05/11/02 Also review ERCOT Protocols Section 7 for more details and additional data.
COMMUNICATIONS AND SETTLEMENTS WORKING GROUP (CSWG) April 2015 Update to COPS.
Nothing below this point Subtitle Nothing below this point Congestion.
1 WMS Report To TAC September In Brief Four Working Group Reports Four Working Group Reports One Task Force Report One Task Force Report Three.
April, 2008 Maximum Shadow Price. April, 2008 Protocol Requirement: Transmission Constraint Management (2)ERCOT shall establish a maximum Shadow.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
West to North CSC Location Scenario 3b WMS August 20, 2008.
QSE Managers Working Group Meeting Notes 7 November, 2008 Report to WMS 19 November, 2008 David Detelich - Chairperson.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Report to TAC August In Brief Working Group Reports Working Group Reports CMWG CMWG DSWG (No report) DSWG (No report) MCWG MCWG MWG (No report)
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
April 28, 2008 Constraint Competitiveness Tests, an Overview Congestion Management Working Group.
ISO Comparison – CAISO Alex Lee (ERCOT)
RCWG Update to WMS December 5, General Update Agenda Items for Today: Verifiable Cost Manual clarifications (vote) White Paper on Long Term Fuel.
UFE 2005 Analysis 1 UFE 2005 ANALYSIS Compiled by Load Profiling ERCOT Energy Analysis & Aggregation.
Nodal Credit Monitoring and Management – Business Requirements ERCOT CREDIT Department October 11, 2006.
December 18, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott January 6, 2015 TAC Update to RMS 1.
MIG TF Voting Items Market Participant Notification Period (Transmission outage) – =1 Year Interconnection Date for Protocol Considerations – First Interconnection.
CMWG Update to WMS Report of CMWG Meeting of M Wagner Edison Mission Marketing & Trading.
ERCOT, Market Analysis 2013 Annual Constraint Competitiveness Test (CCT) Study Results – Update for 8/27/12 CMWG 8/27/2012 ERCOT Public.
September 2010 Wholesale Market Subcommittee Report to Technical Advisory Committee.
Transmission Congestion Rights – Credit Perspective April 17, 2014.
1 TAC Report to the ERCOT Board June 21, TAC Summary 8 PRRS 8 PRRS Withdrawal of PRR 552 Withdrawal of PRR 552 Potomac Recommendations Potomac.
December 2, 2004 Congestion Causes and Effects Presented to WMS January 14, 2005 Beth Garza.
CMWG Update to WMS Report of CMWG Meetings of &
Protocol Revision Subcommittee Report to ERCOT Technical Advisory Committee October 9, 2003.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
2003 State of the Market Report ERCOT Wholesale Electricity Markets.
2010 CSC & Zone Selection: 6 Lines W-N & 4 Zones (WN2_SN0-4Z) Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) August 19,
Graham Generation and the Market – The Facts October 8, 2008.
ERCOT CSC – Vote “Yes” to 3b Jan A. Bagnall Sr. Director Transmission, Reliability & Compliance October 2008.
Report to TAC July In Brief Working Group Reports Working Group Reports CMWG CMWG DSWG DSWG MCWG MCWG MWG MWG QMWG QMWG VCWG VCWG Task Forces Task.
CMWG NATF 11/02/2010- CCT/DME update + Outages in the CRR Model follow-up Steve Reedy – Market Design and Analysis 1.
Congestion Management Work Group Update WMS I Flores, S Reedy—ERCOT M Wagner--PSEG TX.
ROS July 10, 2008 Meeting WOTF Update on ROS Action Plan Summary: EECP Step #2 (Feb.26 th, 2008) Mark Garrott WOTF Chair.
1 WMS Report TO TAC April In Brief Two Working Group reports Two Working Group reports Two Task Force Reports Two Task Force Reports BENA presentation.
MISUG TAC Update Jackie Ashbaugh ERCOT 3/7/ TAC3/7/ /22/2011 Meeting Focus on the high priority items from MISUG: Review task list prioritization.
Technical Advisory Committee Presentation to the ERCOT Board of Directors September 16, 2008.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
CMWG Update to WMS Report of CMWG Meeting of M. Wagner Edison Mission Marketing & Trading Thanks to ERCOT Staff for Graphics See ERCOT.
Constraints Competitiveness Tests (CCT) Results Analysis of 2010 SSWG Peak Summer Case Presented to CMWG 1/27/2010.
August 2012 Wholesale Market Operations Constraints Competitiveness Tests (CCT) – Annual CCT 2013 Study Result with New Approach Market Support and Analysis.
1 TAC Report to the ERCOT Board November 14, 2006.
CMWG Update to WMS M Wagner Edison Mission Marketing & Trading.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule Kris Dixit 1.
QSE Managers Working Group Meeting Notes 9 June, 2009 Report to WMS 17 June, 2009 David Detelich - Chairperson.
CMWG Update to WMS Report of CMWG Meeting of
1 Project Prioritization Review May 14, Approved Revision Requests “Not Started” – Planned to Start in Future Months Revision Request Target Start.
Day-Ahead Market Discussion/Clarification TPTF April 24, 2006.
2009 ERCOT CSCs and Congestion Zones (10/8/08) C. Richard Ross American Electric Power Service Corporation.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
Technical Advisory Committee Presentation to the ERCOT Board of Directors July 15, 2008.
Project Funding Review February 7, Background ERCOT has a $15M project budget in 2013 (same as 2012) –To allow for new additions to the.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Texas Congestion Management Work Group Update For WMS Marguerite Wagner, PSEG Texas.
Wind Operations Task Force Overview for ROS Jan 2009 mtg: WOTF is continuing work on issues #1a/b/c, 1d, 3e, and 5. The WOTF makes no recommendation to.
Report to TAC June In Brief Working Group Reports Working Group Reports CMWG CMWG MCWG MCWG QMWG QMWG VCWG VCWG Other Reports Other Reports NOGRR.
WMS UPDATE CMWG n CMWG has completed their data collection and evaluation of congestion n Based on this evaluation WMS recommends that the same CSCs with.
1 Market Operations Presentation Board of Director’s Meeting February 16, 2005.
Protocol Revision Subcommittee
Mark Garrett – Direct Energy Clayton Greer – J Aron
Review of Abnormal MCPEs
Presentation transcript:

CMWG Update to WMS

Met 4/24 & 5/11 Continued Work on PRR 801 –Discussed outages as related to TCR Cases –ERCOT evaluates various outage combinations & translates the impacts into a CSC flows ERCOT will evaluate 3 TCR cases to compare: Transfer capability for sale vs. most limiting transfer capability (on each CSC) given different sets of outages –Only point of agreement so far is that revenue neutrality should be for forward month only (not to make up historical shortfalls Discussed SCR on posting VSAT limits for N  H

SAPS-Menard ERCOT to provide at meeting

W  N Stability Limit ERCOT Studies are completed ERCOT will provide market notice & new matrix by end of May Permian RMR units –Permian 5 (114 MW) –Permian 6 (515 MW) Only Permian 6 has PSS (but other units in W Zone also have PSS)

CRE Criteria Refinements Discussion Current Protocols: Goal is to find transmission elements that respond similarly to the CSCs from the deployment of BES Experience with CREs (past) shows that refinements may be needed.

Potential Approach Under Consideration: 4 Component Test Threshold weighted shift factor/PTDFs –Shift Factors between Source/Sink Zones –Weighted averages consider only price responsive gen Resource concentration Boundary generation –Generation that has impact on constraint that is counter to the zone it is in Concentration of Effective Generation –Compare percentage of capacity to the percentage of impact Correlation of CRE to its zone

Upcoming Work Review ERCOT findings on TCR Cases for PRR CSC Process Kicks off In June