Project Management Terry A. Ring Chemical Engineering University of Utah.

Slides:



Advertisements
Similar presentations
Commissioning Approach Integrated Service Solutions
Advertisements

Best Practices for an Owner Estimating Organization
Introduction to Chemical Engineering(II) Department of Chemical and Biomolecular Engineering Sogang University Kee-Kahb Koo.
PLANT DESIGN (I) Prof. Dr. Hasan farag.
Capital Cost Estimation
WinSim Inc. Advanced Engineering Software
Objectives: Understand importance of utility and maintenance system in industry/plant.
Group Meeting #1 January 29 th, 2013 Michael Bentel Jeremy David Erik Peterson Arpit Shah 1.
Production of Dimethyl Sulfoxide from Lignin
Chapter 11 Simulating Wireless Control. Simulate Parameter – Analog Input Block  The current or digital outputs of these transmitters and switches are.
Hazard and Operability Studies - HAZOP ChE 258 Chemical Process Safety University of Missouri - Rolla Fike Corporation.
PROJECT AND STUDY DRAWINGS & DIAGRAMS
Chapter 1 - Chemical Process Diagrams
-P&ID- Piping & Instrument Diagram
Process Engineer’s Role in Project Management Dr Abdullah Malik.
CAPITAL COST ESTIMATES INSTALLED EQUIPMENT COSTS.
AXSYS ®.Process Overview. AXSYS Products AXSYS.Process – Process Engineering Environment for Front End Design & Engineering, providing an integrated Process.
Overview of Process Design
HAZARD AND OPERABILITY STUDY
Given a P&ID, the learner will be able to identify the purpose of that P&ID according to their student guide. – Given a P&ID, locate the title block and.
Equipment Sizing Preliminary Equipment Sizing for Capital Cost Estimation.
1 OCCUPATIONAL EXPOSURE at JAPANESE NUCLEAR POWER PLANTS in 2005 October 12, 2006 Shigeyuki Wada Safety Information Division Japan Nuclear Energy Safety.
CH EN 4253 Design I Course Overview Terry A. Ring Chemical Engineering University of Utah.
FLOW-SHEETING What we will cover here? PFD?
Bioprocess Diagrams Including PFD and P&ID
Introduction to Hazardous Evaluation Techniques Guidelines for Hazardous Evaluation Procedures (1992 by AIChE). Second Edition with Worked Examples. Center.
P&ID’s PIPING & INSTRUMENTATION DIAGRAMS.
PIPETECH CONSULTANCY WELCOME TO PIPE TECH CONSULTANCY
Safety & Economic Supervised By: Prof. Mohamed Fahim Eng. Yusuf Ismail Presented by Hessa Al-sahlawi Beshayer Al-Dihani Latifah Al-Qabandi.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Application – Identifying, Listing Equipment, and Documentation
Piloting New Technologies Continental Technologies: Helps advance chemical, fuels, catalyst & polymer technologies Is the only fabrication service provider.
ERT 213 PROCESS INSTRUMENTATION BY: ZULKARNAIN MOHAMED IDRIS
Senior Design Project Chapter 22. Project Overview –Feed Pre- conditioners –Reactor(s) –Separator(s) –Product Conditioners –Recycle –Heat Integration.
+ Example processes P1. sterilizing ketchup. + Problem statement Heinz Ketchup is made in just a few plants in North America, one of which is in Fremont,
TOTAL CAPITAL INVESTMENT
© 2007 Bentley Systems, Inc Bentley Confidential ConceptualizeDesign Analyze Construct HandoverOperate & Maintain AutoPLANT PlantSpace AutoPIPE STAAD/RAM.
CHEMICAL PROCESS DIAGRAM
Last Week of Project Terry A. Ring. Project Schedule.
Guided by: Prof. Ashish Modi Pacific School of Engineering, Surat.
Process Safety Management Soft Skills Programme Nexus Alliance Ltd.
HAZARD AND OPERABILITY STUDY Brainstorming, Multidisciplinary Team Approach Structured Using Guide Words Problem Identifying Cost Effective.
Industrial Process Design
BSB Biomanufacturing CHAPTER 2 Process Plant Design – Part III
Flowsheeting: What is a flowsheeet Importance of flowsheet
Installation of an Instrument on a CERN machine
Extra Homework Required for Friday
Manajemen Industri Instructor: Rama Oktavian
Layers of Protection Analysis
Preliminary Lab Conference
Terry Ring Chemical Engineering University of Utah
Introduction to CHEN Process Design II
Exercise 1 HYSYS Review 11/12/ Design & Analysis II.
Introduction to Chemical Process Design
Estimating Capital Costs
AIChE Contest Organization
Terry A. Ring Chemical Engineering University of Utah
CHPE308 Engineering Economy Estimation of Manufacturing Costs
Chemical Process Diagrams
The most effective way of communicating information about a process is through the use of flow diagrams. Block Flow Diagram (BFD) Process Flow Diagram.
Terry A. Ring Chemical Engineering University of Utah
AIChE Contest Organization
SNC/SCANA – New Build Configuration Management
CHPE308 Engineering Economy Estimation Of Capital Cost
HAZOP Guidewords Base Set
Piping and Instrumentation for Process Industries
Terry A Ring Chemical Engineering University of Utah
Layers of Protection Analysis
Terry A. Ring Chemical Engineering University of Utah
Synthesis of the PFD from the Generic BFD
Presentation transcript:

Project Management Terry A. Ring Chemical Engineering University of Utah

Waterfall Style of Project Management

Waterfall Style of Project Management with Recycle Loop

Agile Project Management Agile methodologies are proven to be 3x more successful than traditional waterfall methodologies and 2x faster

Estimating – Hours for Deliverables Scope of Work/Schedule Development 10 hrs for PFDs 10 hrs for Process Simulations & Equipment Data Sheets 5 hrs for P&IDs Development of Process Design Basis 20 hrs for PFDs Includes Plant Wide Control System Major Components of Safety System 10 hrs for Process Simulations 10 hrs for P&IDs PFDs 20 hrs for PFD Development 4 hrs/PFD for PFD Review 4 hrs/PFD for Materials of Construction Breaks

Estimating – Hours for Deliverables Scope of Work/Schedule Development 10 hrs for PFDs 10 hrs for Process Simulations & Equipment Data Sheets 5 hrs for P&IDs Development of Process Design Basis 20 hrs for PFDs Includes Plant Wide Control System Major Components of Safety System 10 hrs for Process Simulations 10 hrs for P&IDs PFDs 20 hrs for PFD Development 4 hrs/PFD for PFD Review 4 hrs/PFD for Materials of Construction Breaks

Estimation Process Simulations 2x PFD hours Includes H&MB Tables for PFDs Utilities Summary Feed and Effluent Summaries Could Increase for: Startup, Shutdown, Overdesign, Underdesign, Summer, Winter Operations, Impurity Dispositions P&IDs 80 hrs per Inside BL P&ID 40 hrs per Outside BL P&ID 20 hrs per Outside BL P&ID 8 hrs per Demolition P&ID In-house reviews 6 P&IDs per day for Design Team Reviews at 50% and 100% complete

Estimation Process Simulations 2x PFD hours Includes H&MB Tables for PFDs Utilities Summary Feed and Effluent Summaries Could Increase for: Startup, Shutdown, Overdesign, Underdesign, Summer, Winter Operations, Impurity Dispositions P&IDs 80 hrs per Inside BL P&ID 40 hrs per Outside BL P&ID 20 hrs per Outside BL P&ID 8 hrs per Demolition P&ID In-house reviews 6 P&IDs per day for Design Team Reviews at 50% and 100% complete 10%

Estimating Equipment List & Data Sheets 4 hrs. for Equipment List Formating Pumps & Compressors 6 hrs each on PFD 12 hrs each on P&ID Vessels/Tanks/Towers 4 hrs each on PFD 12 hrs each on P&ID Reactors 8 hrs each on PFD 24 hrs each on P&ID Heat Exchangers/Fin-Fans 4 hrs each on PFD 8 hrs each on P&ID Fired Heaters 16 hrs each on PFD 24 hrs each on P&ID Engineering Support for Vendor Requests and Non ChEs 30% of Hrs for Equipment List & Data Sheets Process Data for Piping 5% of Total P&ID hours 6 Hours for AIChE Project using Aspen/ProMax Equipment Data Sheets

Estimating Process Data for Process Instrumentation 2 hrs for each instrument 2 hrs for each Process Control Loop Process Safety Valve Design Assume 1 PSV per vessel 4 hrs per PSV Support for Cost Estimation Done by the Cost Estimation Team 5% of Hrs for Equipment List Items for PFD Items 5% of Hrs for Equipment List Items for P&ID Items HAZOP Analysis Review of 4 P&IDs per day 2 process engineers, 8 hrs/day AIChE Cost Estimation – 6 hrs

Estimating Supervision Supervision and Coordination 10% of a Process Engineering hrs for PFD development 5% of a Process Engineering hrs for P&ID development 5% of Process Engineering hrs for Equipment List and Data Sheets Piping Data Instrumentation PSV Designs Documentation/Data Books/Reports 5% of PFD hours 2% of P&ID hours Contingency + 10% of Total PFD hours + 10% of Total P&ID hours AIChE Project add 10% of total project time for Communication