December 2, 2014.  Introductions  Disclaimers  Ground Rules  Project Overview  CMGC RFP Overview  CMGC Process  ICE/EE Procurement  Design Consultant.

Slides:



Advertisements
Similar presentations
S.P (TH 43) Winona Bridge Project Mississippi River in Winona Industry Outreach Meeting July 29, 2013.
Advertisements

RFP AND CONTRACT PHASE Jeff Wassenaar, P.E., HQ Project Development Benjamin Acimovic, P.E., Region 1.
TH 169 & I-494 Interchange Design-Build Project S.P January 27, 2010 Michael Beer, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING.
TH 610 Design-Build Project S.P February 25, 2009 Dan W. Penn, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING Looking TH 169.
CMGC Contracting at UDOT Program, Projects & Lessons Learned
Introduction to EIS/EA Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation.
TH 55 Mill and Overlay Design-Build Project S.P
November 19, 2013 Preparing a Successful RFP to get Desired Results.
Alternative Project Delivery
Lunchtime Topics Craig Weise Construction Reform Program Director Lisa Conomy Construction Counsel OSU Office of Legal Affairs.
1 Use and content of the RFP  Request for Proposals (RFP) is similar to bidding documents and include all information of the assignment, selection of.
Project Bidding Procedures Enhancing Data and Presentation Skills for Engineers EDASPE Writing the RFP Training Courses – July 2004.
REQUEST FOR PROPOSALS RFP #08-56 Project Management and Procurement Assistance Consultant for an Intelligent Transit System Solution (I.T.S.S.) October.
New York State Department of Transportation
New York State Department of Transportation
Greenfield District Utility/RR Engineer, INDOT
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Route 110 over Route 27 Design-Build Project (PIN , D900027) Town of Babylon, Suffolk County Request.
RFP Overview Alan A. Phillips, CPPB CTPM Texas Southern University Summer 2012.
Office of Business Development Training
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Interstate 81 Bridges over Route 80 Design-Build Project (PIN , D900023) Town of Tully, Onondaga County.
New York State Department of Transportation
CITY OF HALLANDALE BEACH PROCUREMENT PROCESS City Commission Workshop February 23, 2015.
Rural Intersection Conflict Warning System (RICWS) Design-Build Project.
I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
ROAD ACCIDENT FUND COMPULSORY BRIEFING SESSION RAF/2014/00008 Date: 24 March 2014 Time: 11:00.
TH 2 – Wilton Bridge Replacement Design-Build Project S.P March 5, 2009 Todd Vonasek, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING.
Utility & Rail Coordination in Project Development Jennifer McCleve Utilities & Rail Branch Manager.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
1 Technical Assistance - PTAB Selecting and Hiring the Design Professional Dave Maxwell, P.E. Chairman, New Mexico Professional Technical Advisory Board.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
New York State Department of Transportation Accelerated Bridge Program Phase 1B Design-Build Projects Request for Proposals Informational Meeting April.
Research & Technology Implementation TxDOT RTI OFFICE.
Elk Run Interchange Design-Build Project S.P (TH 52) Elk Run Interchange Design-Build Project S.P (TH 52) PROJECT INFORMATIONAL MEETING.
VI. Developing a VSMP Program General Stormwater Training Workshop.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Construction Review LaVon M Marshall Greenfield District Utility/RR Engineer, INDOT June 11, 2015.
1 Comprehensive Tactical Infrastructure Maintenance and Repair (CTIMR) Area 3 Pre-Proposal Site Visit HSBP1015R0040 Sectors EL PASO / BIG BEND, TX
Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
1 © 2013 Protiviti Inc. All Rights Reserved. This document has been prepared for use by OOCEA’s management, audit committee, and board of directors. This.
Construction Management At Risk Process
ECNM Meeting October 1, Project Purpose The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects.
 Working with FHWA on review.  Submit to Cooperating Agencies (EPA and Corp of Engineers)  45 day review May  Respond to agency comments  Publish.
FHWA CMGC Workshop October 23, Project Purpose The purpose of the US 53 project is to address the termination of the 1960 easement agreement that.
December 17,  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low.
The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects the current highway location in order to continue.
Procurement of Professional Services.  Professional Services:  Architects, Engineers  Surveyors  Geotechnical engineers  Nonprofessional Services:
Iron Range Tourism Bureau April 25, 2013 Hwy 53 Update.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
Solicitation VA69D-16-R-0583 Rehab Renovation Pre-Proposal Conference June 22, :00am CDT NCO 12 Great Lakes Acquisition Center.
Technical Issues Design Status Due Diligence Materials Tony DeVito, Project Director Jan. 28, 2016 I-70 East Project.
Compliance with CCNA F.S..  Advertisement  Longlist  Shortlist  Request for Proposal  Scope of Services Meeting  Technical Proposal Review.
Sanitary Sewer Lift Station Rehabilitation Design Services Pre-Submittal Meeting September 20, 2016.
Procurement & Strategic Sourcing
Construction Oversight
Request for Proposals For Banking Services CMU
Procurement & Strategic Sourcing Charter Bus Transportation Services
Joint Parking Task Force Update Procurement & Strategic Sourcing
ROAD ACCIDENT FUND COMPULSORY BRIEFING SESSION RAF/2014/00008
Procurement & Strategic Sourcing
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
MANDATORY PRE-BID MEETING
PRE-PROPOSAL MEETING LOGAN WWTF
Procurement & Strategic Sourcing
Overview of The Bidder Response Form and Changes to the IT RFP Template March 8, 2019.
SP TH 169 Redefine Informational Meeting July 25, 2019
Brieana Reed-Harmel, Broadband Project Manager
Procurement & Strategic Sourcing
Presentation transcript:

December 2, 2014

 Introductions  Disclaimers  Ground Rules  Project Overview  CMGC RFP Overview  CMGC Process  ICE/EE Procurement  Design Consultant Contracts  Oversight Contracts  Questions

 MnDOT Hwy 53 Relocation District Team: ◦ Pat Huston – Project Manager ◦ Rob Ege – Design Engineer ◦ Andy Johnson – Construction Engineer ◦ Jeff Hall - Support  MnDOT ◦ Jay Hietpas – CO Project Management ◦ Kevin Hagness – CMGC Program Manager ◦ Kevin Western – Bride Design Lead/ Design Consultant Contracts  Our job is to ensure all proposers have the same information and to partner with the successful CMGC team and consultants.  Feel free to ask questions at any time.

 What is discussed today is informational only, meant to assist Proposers in pursuit of contracting opportunities on this project.  Proposers are responsible for following the final RFP(s).  If there are any discrepancies, submit a clarification request.

 This meeting is being recorded and will be made available on the following Project Supplemental Information website: ftp://ftp2.dot.state.mn.us/pub/outbound/Dulu th/Hwy 53 Relocation RID/

As per the CMGC RFP: Pat Huston is the Single Point of Contact. Each Proposing team needs to identify a S.P.O.C.

 Relocate TH 53 in the area of the United Taconite Mine by November 15, This includes the construction of a new four-lane TH 53 facility that is complete and open to traffic and the removal of the existing TH 53 (including the removal of roadway facilities, bridges, and utilities) to allow for mining by November 15,  Design and construct a quality, cost effective project while minimizing future maintenance costs.  Avoid and Minimize impacts to the environment.  Minimize or eliminate future risk to MnDOT related to mining operations.  Minimize impacts to all stakeholders.

Based on Current Project Scope and Risk Profile the Total Estimated Construction Contract cost is: $125 to $165 Million * This includes City Utilities and Multi-use Trail on the Bridge

 Right of Way Access  Alignment and Profile  Permits  Utility Complexity  Mine Blasting/ Seismic  Rock Excavated RGGS  NEPA Schedule

 RGGS Parcels  DNR Parcels  Other

 Section 4f  Iron Formation  Environmental Justice  Wetlands  Geotechnical  NEPA Corridor

 COE Wetlands  NPDES  Drinking Water – MDH Design Reviews

 City of Virginia and Virginia Public Utilities ◦ 12”-18” Sanitary Sewer ◦ 12” Watermain ◦ Electric ◦ Gas  CenturyLink  Minnesota Power  Paul Bunyan  Mediacom

 United Taconite Blasts ◦ Every 7-10 days ◦ Occasionally closes TH 53 Traffic ◦ Vibration Monitoring for Concrete  Rock Excavated from RGGS Parcels ◦ Possibility that RGGS will want to retain ◦ Depends on Easement Negotiation and Mineral Value

 Alignment Corridors Identified in DRAFT EIS ◦ Deviation would require backup in NEPA process  No Construction Contracts until ROD ◦ Except for Early Steel Package at risk with State Funds  The preferred alignment must still be vetted through the draft and final EIS process with all build and no-build options. The final alignment will not be “final” until the completion of the final environmental impact statement (FEIS).

 Fall 2014: Proceed with contractor and designer selection  Late 2014/Early 2015: Publish Draft EIS for review/comment.  Late Summer of 2015: Publish Final EIS.  Fall of 2015: MnDOT publishes adequacy determination; FHWA publishes combined final EIS and Record of decision.

 Late Fall of 2015: Start Construction Contract  Reminder: This schedule is best case scenario and is subject to change.

 Test Foundations – Winter ◦ E2 West Pier Drilled Pile ◦ E2 West Pier Drilled Shaft  Rotosonic and Cores – Winter ◦ E2 West Pier ◦ E2 East Pier  Roadway Soil Borings – Dec 2014 ◦ E2 fill ins

December 2, 2014

One-step Best-Value Request for Proposals (RFP) Final CMGC RFP is currently advertised on MnDOT’s Consultant Services website: Thank you to those who submitted comments on the Draft CMGC RFP

A notification to Proposers has also been posted on MnDOT’s Consultant Services website to help Proposers identify what changed between the draft CMGC RFP and the final CMGC RFP. In the event of any discrepancies between this document and the final CMGC RFP, the final CMGC RFP shall take precedent.

Recommended Alternative The recommended alternative that is anticipated to be identified as the preferred alternative in the DEIS is E-2. For the purposes of the CMGC RFP, Proposers shall use E-2. Alternative E-2 may, or may not, be the final alternative eventually chosen through the environmental process.

Completion Date MnDOT’s current agreement with the mine requires TH 53 to be relocated by May, MnDOT is working on a time extension to the existing agreement. For the purposes of the CMGC RFP, TH 53 in the area of the United Taconite Mine is to be relocated by November 15, 2017.

Table Procurement Schedule MILESTONEDATE Issue CMGC RFPNovember 24, 2014 Project Informational MeetingDecember 2, 2014 Deadline for Proposers to Submit Requests for Clarification on the RFP December 12, 2014 Responses to Requests for Clarification on RFP Issued December 15, 2014 Deadline for Proposers to Submit ProposalDecember 19, 2014 InterviewsJanuary 8, 2015 CMGC Contractor SelectedJanuary 13, 2015 Notice to Proceed – P/T Services ContractFebruary 2015

Communications Pat Huston, Project Director, is the sole MnDOT contact person for clarification requests, communications about the project, the RFP, and Proposal submittals.

Communications CMGC programmatic questions shall be directed to Kevin Hagness, CMGC Program Manager:

Proposal Delivery, Content, Format Proposals shall not exceed 18 pages; not including cover letter, table of contents, section dividers, appendices, and required forms Resumes for Key Personnel shall not exceed two pages per position 2-11x17 pages allowed for Project Experience Table

CMGC Project Approach Bridge types under consideration noted in TH-53 Decision Matrix and supplemental project information.

Approach to Cost Estimating Sample estimate values do not need to reflect actual values for rates/prices. The sample estimate is only being used to demonstrate the approach to estimating is transparent.

Preconstruction Price Proposal Submitted in a separately sealed envelope Evaluated around an average Note your fully burdened hourly rates in the preconstruction price proposal form – MnDOT will do the calculations to determine the total cost

Addendums and Clarifications Proposers need to acknowledge all addendums and clarifications issued in their Proposals. RFP Clarification Request Forms can be found on MnDOT’s CMGC website: manager-general-contractor.html manager-general-contractor.html

Mandatory Technical Interviews Approximately one hour in length No handouts or formal presentations Will consist of set questions for all Proposers and clarification questions for each Proposer based on their Proposal Will not be scored separately – will be used as additional information in support and to clarify the information contained in the proposal Questions will not be provided to Proposers in advance of the interview Up to five representatives from Proposer’s team – must include PM, CM, Lead Cost Estimator and Project Principal Proposers must contact CMGC PM to schedule an interview time

Builder’s Risk Insurance Builder’s Risk insurance will be required on this project. MnDOT may acquire or may require the successful responder to purchase and maintain “All Risk” or equivalent Builder’s Risk policy for any executed construction contract(s) insuring the interest of MnDOT, the Contractor, and any tier of Subcontractor. MnDOT will, at their discretion, provide further details regarding the requirements for the Builder’s Risk policy prior to executing a construction contract(s) for the project.

Construction Services Fee Do not submit the Construction Services Fee Proposal Form, Exhibit 4, with the Proposal. The apparent successful Proposer is required to submit this form within five business days after the CMGC selection.

Conflict of Interest

Formal workshops for design review, risk, and cost estimating are anticipated to occur at the 30%, 60%, and 90% design milestones. For each of these milestones, the cost estimates will include an Independent Cost Estimate (ICE), Owner’s/Engineer’s Estimate and the CMGC’s Opinion of Probable Construction Cost (OPCC).

The ICE and an Engineer’s Estimate will be performed at the time of bid and will be used by MnDOT to validate the CMGC’s bid.

Further information available on MnDOT’s CMGC website: nst-manager-general-contractor.html

There will be one RFP advertised for two separate contracts for the ICE and the Owner’s/Engineer’s Estimating services.

Scope of work for both contracts is very similar: production-based, contractor-style estimates at each of the design milestones and at bid schedule analysis and development at each of the design milestones and at bid

Desired Skills: production-based, contractor-style estimating for major bridge projects of similar size, scope and complexity schedule analysis and development for major bridge projects of similar size, scope and complexity Relevant CMGC experience and an understanding of the CMGC process

Responder’s submission of a proposal is acknowledgement that Responder may be assigned, at the discretion of MnDOT, the ICE or the EE services contract.

Procurements Schedule RFP scheduled to be advertised early December, 2014 Proposals due early January, 2015 ICE and EE executed contracts by February, 2015

Continue to watch the MnDOT Consultant Services website for procurement updates, clarifications, and addendums: s.html

MnDOT’s CMGC Website: manager-general-contractor.html

Disclaimer What is discussed today is informational only. Proposers are responsible for following the final RFP(s). If there are any discrepancies, submit a clarification request.

One-step Request for Proposals (RFP) Final RFP is currently advertised on MnDOT’s Consultant Services website: ml ml

Developed matrix to compare alternatives Main issues identified Bridge design complexity Design and construction schedule Construction method Geotech Risk

CIP Concrete Arch Steel Truss Arch Steel Truss CIP Balanced Cantilever Segmental Steel Plate Girder Steel Delta Frame Suspension Single-Tower Cable Stayed

CIP Concrete Arch Steel Truss Arch Steel Truss CIP Balanced Cantilever Segmental Steel Plate Girder Steel Delta Frame Suspension Single-Tower Cable Stayed

CIP Concrete Arch Steel Truss Arch Steel Truss CIP Balanced Cantilever Segmental Steel Plate Girder Steel Delta Frame Suspension Single-Tower Cable Stayed

o Bridge plans can be completed quickly o Early steel contract – June 2015 o Complete plans – Fall 2015 o Steel erection allows for faster on-site construction o We needed type to develop design RFP

Project Understanding and Work Plan Company Background and Experience Key Personnel Availability and Experience Quality Management Plan Cost

Project Manager Bridge Lead(s) Roadway Lead Lead QC for Bridge Lead Geotechnical Engineer

Proposals due December 30, 2014 Selection Week of January 19-23, 2015 Notice to Proceed End of February 2015

Coordination required with: CMGC Peer Reviewer (Bridge) MnDOT Oversight (Roadway) ICE/EE Your team (Bridge, Roadway, Geotech, etc)  Communication will be important

First 30 days Make final decision on Bridge Type Determine additional Geotech needs First 90 days Finalize Preliminary Plans COMPLETE early steel plans Final Plans complete to 60% level Final Bridge Plan by Sept 2015

Your Design Staff Leads with: CMGC Peer Review Oversight MnDOT Allows for quick decisions Scheduled and just-in-time issue meetings 90 day ‘fast burn’ requirement

 RFP after the Design Consultant is Selected  Cover Tasks Necessary to assist MnDOT with: ◦ Roadway Design Review ◦ Project Management ◦ Construction Oversight/ Engineering ◦ Inspection Services  Proposals will be evaluated on a “best value” basis with 70% qualifications and 30% cost considerations.

 Design Phase ◦ Project Manager – full time ◦ Roadway Design Engineer – full time ◦ Communications Manager – ¼ time ◦ Geotechnical Engineer – ¼ time ◦ Hydraulics Engineer – full time ◦ CPM Schedule Reviewer – ¼ time ◦ Environmental Compliance Manager – ½ time ◦ Utility Coordinator - ¼ time

 Construction Phase ◦ Project Manager – ¼ time ◦ Communications Manager – ¼ time ◦ CPM Schedule Reviewer – ¼ time ◦ Environmental Compliance Manager – ½ time ◦ Utility Coordinator - ¼ time ◦ Office Manager – full time ◦ Lead Bridge Inspector – full time ◦ Lead Roadway Inspector – full time ◦ Roadway and Bridge Inspectors – full time ◦ Materials Testers – full time