Production CM QA/QC Plans and Systems Production Cryomodule Final Design Review Jamie Blowers 12-May-2015.

Slides:



Advertisements
Similar presentations
Quality Assurance U. S. ITER Project Office U.S. ITER Project 1 November 15, 2006 U. S. ITER QUALITY ASSURANCE Gail Okulczyk, Presenter U. S. ITER Quality.
Advertisements

Quality Management Training Quality circles Bench Mark Kaizen.
Child Safeguarding Standards
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
NAVAL REACTORS PROGRAM TMDE Status
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
SAE AS9100 Quality Systems - Aerospace Model for Quality Assurance
Lecture 8. Quality Assurance/Quality Control The Islamic University of Gaza- Environmental Engineering Department Environmental Measurements (EENV 4244)
Quality Management System
Computer Engineering 203 R Smith Requirements Management 6/ Requirements IEEE Standard Glossary A condition or capability needed by a user to solve.
Quality Management Dr. S.W. Poon. Quality Management Introduction Meaning of quality Quality Control (QC) Quality Assurance (QA) Differences between QC.
Slide 1 FAA’s Special Technical Audit of Boeing and the Audit Resolution Plan.
An Introduction to the Hennepin County Hennepin County GIS Technical Advisory Group (eGTAG) 10/20/2009.
Systems Engineering Management
Quality Assurance/Quality Control Policy
Configuration Management
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
Purchasing Updates Faculty and Staff Presentation Fall, 2010
Welcome ISO9001:2000 Foundation Workshop.
The BIM Project Execution Planning Procedure
The Key Process Areas for Level 2: Repeatable Ralph Covington David Wang.
Federal Emphasis on Accountability in Higher Education and Regional Accreditation Processes Carla D. Sanderson Commissioner, Southern Association of Colleges.
Effective Management and Compliance 1 ANA GRANTEE MEETING  FEBRUARY 5, 2015.
From Research Prototype to Production
Fermilab Cryomodule QA/QC Model Jamie Blowers LCLS-II EDM/PLM Applications 31-Mar-2014.
Training Seminar on Implementation of Effective Quality Assurance Systems in Romanian Higher Education Institutions April 1-3, 2009 Sinaia Criteria for.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Setting up an Internal Audit Program By
1. QualityControl QualityManagement Before even today Standard: CSA Z Examples Petrobrás Dow Química Beginning: October 1992 ISO 9001 BVQI.
Configuration Management (CM)
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Important informations
Georgia Institute of Technology CS 4320 Fall 2003.
11 FSO Assessment of Fermilab QA Program Status September 14 – 18, 2009.
© 2001 Change Function Ltd USER ACCEPTANCE TESTING Is user acceptance testing of technology and / or processes a task within the project? If ‘Yes’: Will.
BGRI Face-to-Face Meeting 11 March 2012 San Jose, Costa Rica.
The MIT/QA Plan Issue W. Reiersen. Terminology 1 Product specification: A document generated by the customer identifying requirements and the inspections.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
Systems Accreditation Berkeley County School District School Facilitator Training October 7, 2014 Dr. Rodney Thompson Superintendent.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
ESTABLISHMENT OF THE CLEAN DEVELOPMENT MECHANISM (CDM) NATIONAL AUTHORITY, OPERATIONAL FRAMEWORK AND SUPPORT SYSTEMS FOR THE PHILIPPINES Establishment.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 J. Clinton 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument.
1 Overview of the NF 1680 Evaluation of Performance Process Overview/Training Charts April 7, 2008.
Linda Bagby - SBN Program Electrical Coordinator ICARUS Electronics Meeting 27 January 2016 SBN Program Operational Readiness Clearance.
Linda Bagby - SBN Program Electrical Coordinator T600 Installation 8 February 2016 SBN Program Operational Readiness Clearance.
Thomas Jefferson National Accelerator Facility Page 1 FNAL/JLab weekly meeting, April 23, 2014 Agenda  Path Forward  Status at FNAL  Status at JLab.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
JLab SRF Operations Staffing and Training T.Reilly JLab.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
LCLS-II Cryomodule Interconnect Camille M Ginsburg (FNAL) FNAL LCLS-II Deputy Team Lead – Cryomodules Cryomodule Control Account Manager 29 July 2015 Project.
Engineering Documentation
Fermilab LCLS-II Cryomodule QA/QC Model and Software Tools ESS Cryomodule Workshop, 16-Oct-2014 Jamie Blowers Head of Machine Shop and Quality & Materials.
LCLS-II Prototype Cryomodule FDR J. Blowers, C.M. Ginsburg, T. Peterson, R. Stanek, J. Theilacker (FNAL) 21 – 22 January 2015 Homework Responses.
S. Barbanotti - DESY Requirements Conformance for SRF Cryomodules Workshop 16/10/2014 – ESS, Lund XFEL cryostat main components: Quality Assurance and.
LCLS II FNAL Niobium Pre- Procurement Review - Overview Camille M. Ginsburg, FNAL April 17, 2014.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Prof. Shrikant M. Harle.  The Project Life Cycle refers to a logical sequence of activities to accomplish the project’s goals or objectives.  Regardless.
LCLS-II Prototype Cryomodule Darryl Orris 21 January 2015 Final Design Review: Instrumentation.
CONFIGURATION MANAGEMENT AND CONTROL PLAN ESS Quality Assurance and Control workshop (30June) V. HENNION.
QUALITY ASSURANCE MODULE 3. Definitions Quality Assurance - A process/effort that ensures that processes are followed, that the processes of doing right.
Accelerator Readiness Review October 31, 2006
Accelerator Operations Department Readiness (Part 2)
Enterprise Content Management Owners Representative Contract Approval
2K CB FDR Overview:  Agenda, Charge, Review Process
Standards and Certification Training
GLAST Large Area Telescope:
MODULE B - PROCESS SUBMODULES B1. Organizational Structure
ESS approach and support for Declaration of Conformity (CE-marking) Fredrik Håkansson ESS Accelerator Collaboration Board Meeting Trieste
DOE Review of the LCLS Project October 2006
Presentation transcript:

Production CM QA/QC Plans and Systems Production Cryomodule Final Design Review Jamie Blowers 12-May-2015

2 LCLS-II Production Cryomodule FDR, May 2015 Outline My background “Big Picture” (FNAL, JLAB, SLAC) Procurement strategy Internal and external quality-related systems Design Controls Incoming Inspection Production control, Travelers, and NCRs Summary

3 My background LCLS-II Production Cryomodule FDR, May 2015 Engineering Physicist by title Department Head (Quality & Materials, Machine Shop) and Technical Division QA Manager by role BS Physics, coursework towards MS in Accelerator Physics Been with Fermilab 16 years Implemented QA and QE programs prior to Fermilab Started my quality career in the automotive industry ASQ certifications: CQE, CQA, CQM

4 “Big Picture” LCLS-II Production Cryomodule FDR, May 2015 QA staff from SLAC, Jefferson Lab, and Fermilab have been working closely to coordinate quality efforts related to LCLS-II Cryomodule work All three have formal QA programs, and LCLS-II-specific QA Plans have been put in place FNAL and JLab QA have frequent telecon’s (currently every three weeks or so), to work on coordination; SLAC participates as necessary SLAC LCLS-II QA Manager has assessed the QA programs at JLab and FNAL-TD (so-called “crosswalk”), and gave them both passing marks (Nov/Dec 2014) Both JLab and Fermilab are including SLAC-specific QA requirements into their plans (e.g. Acceptance Criteria Strategies) FNAL ACS forms:

5 “Big Picture” (con’t) LCLS-II Production Cryomodule FDR, May 2015 Cryomodules at both labs are being built to the same design using identical components end result will be CM’s which are mechanically identical, and that all meet the functional requirements We recognize that staff, tooling, and processes will not be identical working on a set of common parameters that both labs will include in their production processes; will report and compare them (electronic) travelers will be used in both Labs, and as they are being developed we are sharing and comparing

6 Procurement Strategy LCLS-II Production Cryomodule FDR, May 2015 Procurements split between the two labs For any given procurement, a “Lead Lab” has been identified As the name implies, they lead and make the procurement The other Lab is involved in a supporting role Each Lab performs their own receiving inspections Allows for each Lab to work in their preferred way (to a common set of requirements) Eliminates the natural tendency to reproduce/redo work Each Lab has named an technical person to work on each procurement (for both lead and supporting); “SOTR”

7 LCLS-II Production Cryomodule FDR, May 2015 Sub-Contracting Officer’s Technical Representative (SOTR) Important Role / Responsibility “Glue” between design, prototyping, procurement and assembly phases Technical expertise for sub-system components Design Phase Develops technical specifications from higher level requirements Prepares drawings and supporting technical documents Prototyping Phase Works with Acquisition/Procurement to procure prototypes from industry/partner labs Participates in prototype development and testing Feeds forward experience into production process Production Procurement Phase Provides technical leadership and point of contact with suppliers Inspection/Assembly/Integration Provides sustaining engineering during receiving inspection & manufacturing Technical judgment to resolve non-conformances (Ed Daly)

8 LCLS-II Production Cryomodule FDR, May 2015 FNAL, TD, and SLAC Quality Systems

9 LCLS-II Production Cryomodule FDR, May 2015 JLab Quality Systems (Johnny Leung)

10 Design Controls LCLS-II Production Cryomodule FDR, May 2015 The outputs of all engineering work are managed in Teamcenter Requests for design work are formalized Design releases are reviewed and approved using a Teamcenter workflow Design changes that affect the functional requirements will be brought to the attention of the SLAC Change Control Board for review and approval To ensure that consideration is given to the effects of “smaller” design changes, they will be discussed during weekly Fermilab/JLab coordination meetings and communicated to the appropriate SOTRs Parts and material are not procured without approved drawings Both Labs pull final (approved) drawings from Teamcenter

11 Incoming Inspection LCLS-II Production Cryomodule FDR, May 2015 All parts and materials are inspected upon receipt SOTRs are working with QC folks to define inspection drawings/plans The two Labs are comparing inspection plans and data, along with ACSs

12 LCLS-II Production Cryomodule FDR, May 2015 Incoming Inspection example (Fermilab)

13 LCLS-II Production Cryomodule FDR, May 2015 Incoming Inspection example (JLab) (Frank Marhauser)

14 LCLS-II Production Cryomodule FDR, May 2015 Production control The LCLS-II Project has committed to using travelers Provide detailed step-by-step instructions covering whole process

15 LCLS-II Production Cryomodule FDR, May 2015 Process Control System: Vector (Fermilab) All travelers are fully electronic; System is currently read-only to the world, so easy data sharing is in place As much as we could, we replicated the functionality and flexibility of a paper traveler:

16 Process Control System: Pansophy (JLab) LCLS-II Production Cryomodule FDR, May 2015 (Valerie Bookwalter)

17 LCLS-II Production Cryomodule FDR, May 2015 Document Control All Travelers and Operating Procedures are under version control and any changes to those documents need to be reviewed and approved by Responsible Authorities JLab Fermilab

18 LCLS-II Production Cryomodule FDR, May 2015 Nonconformance handling (Vector) All non-conformances will be recorded using built-in Discrepancy Report System and have to be resolved by the Lead Engineer before proceeding to next step Rework Steps will be issued if process repeat is needed

19 LCLS-II Production Cryomodule FDR, May 2015 Nonconformance handling (Pansophy) (Valerie Bookwalter)

20 Summary LCLS-II Production Cryomodule FDR, May 2015 Quality systems are in place at both Labs, and have proven effective in numerous past projects SLAC-specific requirements have been incorporated Completed QA Cross-Walk exercises in Nov/Dec 2014 On-going regular QA discussions between JLab and FermiLab on project QA. Both Labs are using electronic travelers, and will be collecting a common set of parameters Designs are controlled through Teamcenter Both SLAC and JLab have access Our quality systems are in use now for the pre-production Cryomodule work Thanks to Anne McEwen, Johnny Leung and Valerie Bookwalter for their help