Alignment & Vibration Issues for SuperB M. Esposito, S. Tomassini, INFN-LNF SuperB Workshop – SLAC – October 7th, 2009.

Slides:



Advertisements
Similar presentations
The Preassembling Installation Survey & Alignment Accelerator Center of IHEP Qu Huamin 2006 / 4 / 27.
Advertisements

Progress of the sub-harmonic bunching system (i.e. upgrading progress of BEPCII present bunching system) Pei Shilun for the SHBS team Accelerator center,
April 27th, 2006 Paola Puppo – INFN Roma ILIAS Cryogenic payloads and cooling systems (towards a third generation interferometer) part II: the Vibration.
Survey of KEKB magnets and monuments for SuperKEKB Mika Masuzawa(KEK) Yasunobu Ohsawa(KEK) Naohiro Abe, Kenji Mishima (PASCO) Survey of KEKB Magnets and.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Zachary Wolf Undulator Tuning June 17, 2008 Undulator Tuning Status Z. Wolf, S. Anderson, R. Colon, S. Jansson, S.Kaplunenko,
MICE Target Status Chris Booth Sheffield 10 th May 2006.
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Physics.
Bob Lill Undulator Systems – BPM April 20, 2006 Undulator Cavity BPM Status and Plans.
Pre-alignment solutions applied to girders 1/19 Sylvain GRIFFET, 06/07/2010.
Metrology for NCSX Steve Raftopoulos and the NCSX Metrology Team.
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
1 ATF2 project: Investigation on the honeycomb table vibrations Benoit BOLZON 33rd ATF2 meeting, 24th January 2007 Laboratories in Annecy working on Vibration.
Alignment and Beam Stability
STRIPLINE KICKER STATUS. PRESENTATION OUTLINE 1.Design of a stripline kicker for beam injection in DAFNE storage rings. 2.HV tests and RF measurements.
ALIGNMENT DESIGN AND STATUS OF TAIWAN PHOTON SOURCE WEI-YANG LAI October,
Tilt meter fiducial Guide rail Abstract This poster covers the survey and alignment techniques selected for installation of the SPIRAL2 accelerator devices.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
Orbit Control For Diamond Light Source Ian Martin Joint Accelerator Workshop Rutherford Appleton Laboratory28 th -29 th April 2004.
BEPCII Prealignment Installation Survey and Alignment Accelerator Center of IHEP Xiaolong Wang
CLIC survey and alignment 1 CLIC CES meeting STARTSLIDE CLIC SURVEY AND ALIGNMENT Hélène MAINAUD DURAND.
Optimization of Field Error Tolerances for Triplet Quadrupoles of the HL-LHC Lattice V3.01 Option 4444 Yuri Nosochkov Y. Cai, M-H. Wang (SLAC) S. Fartoukh,
Fast feedback, studies and possible collaborations Alessandro Drago INFN-LNF ILCDR07 Damping Rings R&D Meeting 5-7 March 2007.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Meeting of the European Global Design Effort Report from INFN non EU-funded R&D Carlo Pagani University of Milano and INFN DESY, 10 May 2006.
Survey, Alignment and Metrology Fiducials Requirements Fabien Rey ESS Survey, Alignment and Metrology Group ACCELERATOR TECHNICAL BOARD 23/09/2015.
Survey, Alignment and Metrology Fabien Rey Pawel Garsztka ESS Survey, Alignment and Metrology Group.
Survey, Alignment and Metrology Fabien Rey Pawel Garsztka ESS Survey, Alignment and Metrology Group Interface Workshops for ESS Warm-Linac: ISrc - LEBT.
BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.
GM sensor tests and installation A.Jeremie K.Artoos, D. Kudryavtsev, Y.Renier, R.Tomas-Garcia, D.Schulte.
Fiducialisation and initial alignment of components for CLIC Mateusz Sosin on behalf of the CLIC active pre-alignment team CLIC Workshop 2015.
ATF status M. Ross October 15, 2004 The ATF is the largest test facility built exclusively for linear collider RD –Utility not reduced by the selection.
Ground motion studies at ATF2 June 11, 2014 Orbit jitter source identification via ground motion studies at ATF2 (Results of the June run) Marcin Patecki,
WP8-HGA High Gradient Acceleration M. Biagini (INFN-LNF) WP8 coordinator Tiara Kickoff Meeting, CERN, Feb , 2011.
Catherine LeCocq, SLAC Alignment Plan for the LCLS Undulator IWAA 2006,1 Alignment Plan for the LCLS Undulator Catherine.
ATF2: final doublet support Andrea JEREMIE B.Bolzon, N.Geffroy, G.Gaillard, J.P.Baud, F.Peltier With constant interaction with colleagues from KEK, SLAC.
S UPER B site status report S. Tomassini INFN-LNF On behalf of SuperB Collaboration SuperB general meeting– Frascati – December 1-5, 2009.
Company LOGO Technology and Application of Laser Tracker in Large Space Measurement Yang Fan, Li Guangyun, Fan Baixing IWAA2014 in Beijing, China Zhengzhou.
1 BROOKHAVEN SCIENCE ASSOCIATES 12th International Workshop on Accelerator Alignment September 10-14, 2012 Fermilab, Batavia, Illinois, U.S.A NSLS-II Girder.
Midterm Review 28-29/05/2015 Progress on wire-based accelerating structure alignment Natalia Galindo Munoz RF-structure development meeting 13/04/2016.
1 st TIARA Steering Committee A. Gallo – INFN Frascati deputy of TIARA WP8 leader STATUS OF TIARA WP8.
TDR and R&D Plans J. Seeman and M. Biagini For Super-B Staff.
1 BROOKHAVEN SCIENCE ASSOCIATES 13th International Workshop on Accelerator Alignment October 13-17, 2014, IHEP, Beijing, China Smoothing Based on Best-fit.
Calva update Nicolas Leroy for the CALVA group (LAL, ESPCI, LAPP, LMA) Main Laser Cavity 1Cavity 2 Aux. Laser L1 L2 M1M2M3.
Survey for SPL Dominique Missiaen BE-ABP/SU. Outline 12/11/2008 Dominique Missiaen BE-ABP-SU, Survey for SPL 2  Scope & Main Parameters  Technical Description.
S UPER B SITE OVERVIEW S. Tomassini, INFN-LNF On behalf of SuperB Collaboration.
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November.
Alignment and stability session
Tutorial On Fiducialization Of Accelerator Magnets And Undulators
Phase Feed-Forward Piotr Skowroński (CERN)
SUPERB site status report
SUPERB SITE OVERVIEW C. Sanelli, F. Sgamma, S. Tomassini, INFN-LNF
SUPERB site status report for layout v12
WP9-SuperB in TIARA M. Biagini, INFN-LNF.
Workshop on Tau-Charm at High Luminosity
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
by P. Musumeci and F.Tazzioli
(Potential) Site and Utilities
SuperB Injection, RF stations, Vibration and Operations
Optimization of Triplet Field Quality in Collision
SPARC RF gun status by P. Musumeci Review committee
Superattenuator for LF and HF interferometers
Installation status and planning
3rd Workshop on SuperB SLAC June , 2006
Advanced Research Electron Accelerator Laboratory
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Summary of Washington DOE Review
Super-B Accelerator Overview
as a prototype for Super c-tau factory
M. E. Biagini, LNF-INFN SuperB IRC Meeting Frascati, Nov , 2007
Presentation transcript:

Alignment & Vibration Issues for SuperB M. Esposito, S. Tomassini, INFN-LNF SuperB Workshop – SLAC – October 7th, 2009

Outline LNF Alignment Group ( what we have done and what we can do) Requirements and Tolerances for SuperB Alignment Update on Vibration Studies Conclusions

LNF ALIGNMENT GROUP Hall Probe & Rotating Coil Magnetic measurements for component fiducialization Part of the LNF Mechanical Engineering Service 2 expert technicians and 1 engineer under the responsibility of Eng. F. Sgamma Laser Trackers Leica LTD 840 ( ±15µm+6µm/m) Leica LT 500 (±10µm/m) Optical Instruments 2 Leica T3000 theodolites 2 Leica N3 levels

DA  NE Upgrade Upgrade of the layout based on the Crab waist collision scheme with large Piwinsky angle Fast kickers New bellows IR2 parassitic collisions removal And also

Network completely remeasured in 2007 for the upgrade of the accelerator: -10 free standing LT stations -15m max acceptable measuring distance -0.03mm max RMS value of residuals accepted DAFNE -The 2 IRs have been changed and realigned - The alignment of most part of the rest of the 2 rings was checked and modified only if necessary. We have been able to store the beams in the rings without any vertical correction with a max distorsion of the orbit of ±3mm ( → 0.1mm RMS vertical alignment error)

SPARC 6 module undulator SLAC type acc. sections Seeding laser 1.6 cells RF gun

SPARC magnetic measurements using a Hall Probe machine [4] ACCELERATING SECTION SECTION STEERING MAGNETS SEEDING CHAMBER RF DEFLECTOR construction of specifically designed alignment tools fiducialization with a tactile probe 3D measuring machine. FOCUSING SOLENOIDS FIDUCIALIZATION OF COMPONENTS. GUN AND GUN SOLENOID DIPOLES QUADRUPOLES Laser Tracker capabilities and Leica Axyz software [3] versatility were exploited for fiducialization it represents the reference frame for all alignment and surveying operations. REFERENCE NETWORK for target and optical instrument positioning it is the reference frame for all alignment and surveying operations … addition of “secondary” nodes and realization of Laser Tracker measuring campaigns specifically designed and installed for LT measurements PILLAR SOCKETS BRACKET SOCKETS GROUND SOCKETS it was initially designed for the use of optical instruments [2] SECONDARY SOCKETS

SPARX Project of a different scale Same tolerances or even tighter Asked CERN alignment group (J.P. Queznel) for some suggestions based on their experience on accelerators of bigger size

Streched wire as a reference for an LT measured reference network SPARX CERN built instruments to measure offsets from streched wires EARTH CURVATURE EFFECT h≈D 2 /2R

SUPERB Tolerances? network measurement error propagation along the tunnel (how to estimate it and how to keep it low) reusability of component supports, adjustment systems, fiducials and tools Interference of vibration active damping (where and if necessary) with alignment

Vibration survey (what we did) In order to characterize the site, vibration measurements are foreseen: on ground surface underground The surface measurements were made in a single point very near the railway station and Highway by the Pisa INFN VIRGO group (Dr. Braccini and Eng. Gennai). They made a preliminary measurements on June 8 th and the results were shone at the Perugia meeting. U. Rotundo from the LNF was involved too, but his instrumentations didn’t have enough sensitivity to perform this kind of measurement.

Vibration survey cont’ In order to give an answer to the question from the Perugia meeting: “make coherence measurement”, we have bought six accelerometers (Virgo like) (we are waiting for the devices delivery). In the meantime G. Di Pirro is working on the measurement setup timing: the system is based on GPS synchronization. 100μs of synchronization can be easily achieved and this is enough for measurements on 1000Hz frequency span,. The setup will be ready by the end of November, hopefully. We have decided to buy the hardware in order to have an in house working group with the right expertise even in the future.

Synchronization and acquisition system CPU 1.9 GHz, 2 Gbytes RAM, HD 250 Gbytes Operating System Windows XP Software environment Labview NI PXI-6682 GPS, IRIG-B, IEEE 1588 Sync and Time Module with TCXO NI PXI-4462, 24 Bit, kS/s, 4 Inputs, 118 dB Dynamic Range Trimble Thunderbolt E a GPS receiver that provides a 10MHz GPS disciplined clock GPS splitter GPS antenna G. Di Pirro

Synchronization and acquisition system GPS antenna GPS disciplined clock PXI System GPS splitter G. Di Pirro

Synchronization and acquisition system Modular System A single acquisition system More acquisition system G. Di Pirro

Vibration survey (what we are going to do) The preliminary geological survey finished last week. Thanks to Andrea Jeremy we have organized the next campaign of vibration measurements for next week. The plan is: 1. Make measurements in more surface points at LNF site 2. Make coherence measurements on surface 3. Make coherence measurements between surface and underground On October 13 th, Andrea Jeremy will start the next campaign of vibration measurements at LNF

Underground Measurements On September 14 th the first campaign of geological tests started at LNF site: 4 holes of different depth have been bored in the points shown below. Each hole was tubed with a plastic pipe with an inner bore of about 70mm. A second campaign of other four-five holes is foreseen soon These holes will also be used for underground vibration measurements 50m 40m 30m

Underground Measurements We have two types of vibration sensors: - 2 geophones which can measure ground motion from 0.1Hz to 50Hz but with a diameter of 16.8cm (does not fit in the holes). However, we will bring the geophones which can be used to measure ground motion on surface. - 2 accelerometers which can measure ground motion from 1Hz-10Hz (depending on the level of ground motion: Signal to Noise Ratio) up to 100Hz with a diameter of 6.48cm. So this last one can be put in the holes although it is tight (hole diameter: 7.0cm). Our accelerometer supports will be too large to be put in the holes, but we can fix the sensors to a heavy metal cylinder (we have some at LAPP). Cheers, Benoît

Conclusions LNF alignment group has a good expertise on standard alignment procedures. Their expertise and their instrumentation is available for SuperB collaboration Tolerances for the mechanical alignment of the SuperB components have to be established. Solutions on how to obtain them have to be established and optimized Preliminary single-point vibration measurements for the Frascati site have been performed in June Correlation and (hopefully) underground measurements will be performed very soon LNF are creating a group with the right expertise and the appropriate instrumentation to perform vibration measurements in house in the next future