 Add potential impacts for a 53/135 interchange  Meeting with FHWA to resolve issues  Do not have a plan/timetable from FHWA for review.  Submit to.

Slides:



Advertisements
Similar presentations
Planning and Development Committee West Corridor Update May 10, 2007.
Advertisements

Metro Muncipal Agreement Program
Agreement between the Village of Owego and Inflection Energy.
Meadowbank Gold Project Cumberland Resources Ltd. Nunavut Impact Review Board Public Hearing Chesterfield Inlet, Nunavut March 30, 2006.
CMGC Contracting at UDOT Program, Projects & Lessons Learned
Introduction to EIS/EA Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation.
Year End Review January, 2015.
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
ROUTE 27 (PARK STREET) CORRIDOR SEWER EVALUATION Mark J. Thompson, P.E. Gus O’Leary Kleinfelder / S E A Consultants Inc.
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Managing and Negotiating Change Orders Presented by Daniel Williams, P.E. May 1, 2008.
May 13, TSX-V:OCO, Frankfurt:OR6, US OTC: ORRCF.
Highway 1/169 Improvements Six Mile Lake Road to Bradach Road “Eagles Nest” October 10, 2014 Project Update Meeting Eagles Nest Town Hall.
LANE CLOSURE CHARTS CHART DEVELOPMENT AND DELAY DAMAGES (District 3) OBJECTIVE To become familiar with the lane closure chart development process.
Rivanna Water & Sewer Authority Community Water Supply Mitigation Plan Public Meeting November 2, 2006.
Lake Columbia Water Supply Reservoir Project TWCA March 4, 2010.
Determining Innovative Contracting Methods to Reduce User Costs Stuart Thompson Utah Technology Transfer Center.
OSU Airport – Overview of Master Plan and Draft Environmental Assessment Purpose of an Airport Environmental Assessment (EA) Identify environmental impacts.
Other Construction Projects
On Target Group Coaching
January 30, 2014 Kurt Parkan, External Affairs Manager Industry Outlook Forum Kenai Peninsula Economic Development District.
Columbia River Water Management Program (CRWMP) Review of Year One Upper Crab Creek Planning Unit Meeting April 17, 2007.
Calvert Cliffs Unit 3 Status Summary for PPRAC Meeting 26 August 2008.
WRRDA and WRDA: How are they different, and does it make any difference? Inland Rivers, Ports and Terminals, Inc. Tuesday, April 29, 2014 James A. Kearns.
Utah Transit Authority Proposed Changes to ADA Paratransit Services October 5, 2015 John M. Inglish, CEO/General Manager.
Week 3 Sr. Design. Important Things we Know You will be doing heavy haulage by Barge on the Yukon River for $5 per tonne to Nennana – There will be no.
1 Public Hearing to Consider Proposed Amendments to the Emission Inventory Criteria and Guidelines Regulation for the AB 2588 Air Toxics “Hot Spots” Program.
FERC Relicensing of the Toledo Bend Project – Hydroelectric Power Generation Drought Hydroelectric vs. Water Supply Sabine River Authority Issues.
Assessing Effects on Human Health Meadowbank Gold Project Margaux Brisco Nunavut Impact Review Board Final Hearings, Baker Lake, Nunavut March 27 to 31,
Title 5 Emissions Quantification © Dr. B. C. Paul.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
Rivanna Water & Sewer Authority Community Water Supply Mitigation Plan Public Meeting November 2, 2006.
World Leader in Platinum Expansion : November 2002 PRODUCTION PROFILE Anglo Platinum 28 November 2002.
September 25, Who is Brushy Creek Regional Utility Authority? Local government corporation formed by Cedar Park, Leander and Round Rock to access,
Fred Luna, SBCAG Paul Martinez, Caltrans District 5 April 3, 2013 SBCAG North County Subregional Committee State Route 246 Passing Lanes.
Millbrook Dam Environmental Assessment Study Dan Marinigh CAO/Secretary-Treasurer Otonabee Region Conservation Authority October 20, 2015 Otonabee Conservation.
US 36 Commuting Solutions Northwest Rail Westminster Segment/Eagle P3 Oct. 14, 2014.
Jericho Project Air Quality Assessment. TOPICS METHODOLOGY EMISSION SOURCES RESULTS AND ASSESSMENT MITIGATION AND MONITORING CONCLUSION.
Tempe Town Lake Downstream Dam Replacement NEW DAM ALTERNATIVES SELECTION January 5, 2012.
The Role of NEPA Leasing and Mineral Rights Sales Subject to Environmental Use and Planning Provisions –The National Environmetal Policy Act of 1969 requires.
SP (TH 53) Relocation Project Preferred Alignment Selection Process for FHWA December 1, 2014 Patrick Huston, P.E.
ECNM Meeting October 1, Project Purpose The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects.
 Working with FHWA on review.  Submit to Cooperating Agencies (EPA and Corp of Engineers)  45 day review May  Respond to agency comments  Publish.
FHWA CMGC Workshop October 23, Project Purpose The purpose of the US 53 project is to address the termination of the 1960 easement agreement that.
1% Sales Tax Commission Board Meeting June 3, 2015.
December 2,  Introductions  Disclaimers  Ground Rules  Project Overview  CMGC RFP Overview  CMGC Process  ICE/EE Procurement  Design Consultant.
December 17,  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low.
The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects the current highway location in order to continue.
Available at: hwy53relocation/sco ping.html hwy53relocation/sco ping.html.
 HDR, Ott Constructability, Dan Brown  Visit and boat tour of Rouchleau pit ◦ Access better than potrayed ◦ Challenging geotechnically 
 HDR, Ott Constructability, Dan Brown  Visit and boat tour of Rouchleau pit ◦ Access better than potrayed ◦ Challenging geotechnically 
Iron Range Tourism Bureau April 25, 2013 Hwy 53 Update.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
Richland Creek Water Supply Program Status Update Paulding County, Georgia Board of Commissioners Work Session January 26, 2016.
Richland Creek Water Supply Program Update Paulding County, Georgia Board of Commissioners Work Session March 08, 2016.
Technical Issues Design Status Due Diligence Materials Tony DeVito, Project Director Jan. 28, 2016 I-70 East Project.
Proven Management – Proven Gold Districts – Safe Jurisdictions Symbol:PG Exchange:TSX Hardrock Project Environmental.
Feasibility of Bass Lake Wastewater Treatment
Englewood Mews HOA May 23, 2017 Michelle Holland, Megaprojects Communication Manager Virginia Department of Transportation John Morse, I-66 Project.
Adams County Oil & Gas Traffic Impact Study
Upland Landfill Waste Discharge Application 7295 Gold River Highway
Contractor Submissions
Sully District Council of Citizens Associations January 25, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation.
Eagle P3 Project Update RTD Board of Directors Sept. 2, 2014.
Ohio’s Research Initiative for Locals
Issaquah-Fall City Road
Transportation Improvement Program and Air Quality Conformity Analysis
Walker Street Reconstruction Project 25% Design Public Hearing
A Test Application of the WRAP Economic Analysis Framework
Presentation transcript:

 Add potential impacts for a 53/135 interchange  Meeting with FHWA to resolve issues  Do not have a plan/timetable from FHWA for review.  Submit to Cooperating Agencies (EPA and Corp of Engineers)  45 day review -April ?  Publish in May  45 day public review  Public hearing in 45 day period in Virginia area  Preferred Alternatives Selection  July 2014

- Contractors -3 grading -2 bridge -2 large firms -I JV - General Comments -Get a ROD as early as possible -Time = cost -Material delivery (ste el or geo grid) not an issue -Winter a huge risk -No consensus on flyrock - M-1 -Easiest to build – access and dry

- E-1a -Don’t dewater- many issues -Multiple crews needed – 24/7 construction -Access from both ends - E-2 -Use barges and traditional cranes -4- span Steel bridge is appropriate -Use drilled shafts -Candidate for launching girders (haunch issue) -Precast hollow bridge piers appropriate

 25% of water to the Enterprise pit and local lakes  West Two Rivers Reservoir ◦ 5.5 miles ◦ $13.7 million  Minntac Cell 2 Tailings Pond  6 miles  $21.6  3 month pumping + set up time  Costs not in E-1a estimate

- Ongoing this week - Emphasis on constructability & geotech - Ott Construction Consultants - Geo Tech -Nick LaFronz – Geo tech from the “Hoover Dam” bridge -Options instead of dewatering -Ideas for testing underwater - Report on Friday 10-noon -Smart Board – CO G22

Proposed TH 53 & TH 135 Interchange -Only E-1a & E-2 -M-1 major impacts -Cost (not included) -E-1a $ 4 million (reduces cut) -E-2 $7 million

Elements No Build Alternative Existing US 53 Alternative Alternative M‑1 (2 bridges) Alternative E-1A (w/out future bridge) B Alternative E-2 (1 bridge) Construction$1 to $2N/A$153 to 211$74 to 106$120 to 150 ROW/Land/ Mitigation N/A $400 to $600 $96 to 108$ 7 to 11$ 87 to 104 Total Capital Cost for Construction $1 to $2 $400 to $600 $248 to 319$81 to 117 B $207 to 254 B-C Ratio

 Existing Roadway  $400- $600 million per initial estimate  Does not include loss of revenue, jobs etc if mine cannot expand.  Flawed methodology per mine geologists  Rough calculations by geologists concur with range  Need full depth cores and assay to validate  Few cores done by MnDOT in 2001 in mine’s possession  Will allow to view, but not test.  Anecdotal information indicates high quality material with low silica  Require condemnation and possible Loss of Going Concern

 M-1 $95.5 million estimated  $75 million in AQ mitigation (model non-compliance)  $10 million in Minerals (Mine says too low)  $10 million in mine operating costs  $0.5 million for other properties  Mine has stated that they will not cooperate.  Will require condemnation- possible Loss of Going Concern claim  Cliffs Natural Resources & RGGS  Delay of 6 months +

 E-1a $6.8 million  $4.7 million estimated in ferrous minerals (assay results due end of March)  No gold costs, but low risk of gold.  Gold assay results due in May  If gold, 3 D easement  $500,000 in mine operating costs  Remainder in other properties/agreement with other parties.  Major agreement issues /risks  Air and Water Quality  No costs included.

 E-2 $87.4 million  $87 million in minerals discounted to present day  Not in operating mine or under lease  RGGS and School Trust  Both open to sale “if the price is right”  $0.4 million for other properties  Outside any leased or permit to mine area  No gold costs included  Awaiting assay results – due in June (both gold and ferrous)

 Changing EPA standards- re-evaluated every 5 years (NAAQS)  Two years behind schedule  May be new evaluation system with new standards  Must meet at mine boundary or at public receptors  Modeled or monitored non-compliance permitted by MPCA.  Mine could lose AQ permit (closure)  Existing T.H. 53 an exception to the permit to mine.  New rules for changing permit to mine boundaries.

 M-1 has modeled non-compliance over NW ¼ in mine  PM 10 (dust from trucks) passing under road  Southerly portion high – disperses dust  E-1a has modeled compliance with a margin of safety  Requires mine to relocate stock piles.  All mining on one side of the road.  Modeled at 4% grade – high above operation  Several low volume roads in Permit to mine areas with monitors.

 Mine  Fewer trucks –large cost, need to retrofit crusher  Alternate conveyance system in pit (rail, conveyor belts)  More watering/dust control –winter issues  Pave in-pit roads – continually changing routes  State  Cover and possible fans - $40-75 million  Change permit to mine boundary –  EPA variance – no process

 All road run off must be captured or will re-open mine NPDES permit  If mine NPDES re-opened must meet standards for entire mine ($$)  M-1 – storm sewer and ponds on north end  E-1a - sag in middle of pit  Additional concern for drinking water supply.  Series of ponds (need MPCA concurrence)  Storm sewer- possible pumping  Need agreement on storm/BMP’s to mitigate.

 How do we transfer risk to mine?  Agreement on issues and standards  Possible payment  Negotiate Permit to Mine Boundary with DNR  Mining Commissioners Board  Will mine need an EAW to expand boundary?  Appropriate parties for negotiation.  Next steps - Nex

May 5, 2017