LIU-SPS T. Kramer, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 20 th November 2015 20/11/2015 LIU-ABT Review - SPS2.

Slides:



Advertisements
Similar presentations
Multi-Turn Extraction / L.Ducimetière / Kicker options for MTE Prepared by L.Ducimetière, L.Sermeus Outline: Reminder : Present MTE dedicated.
Advertisements

PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
1/10/2014 LIU-PS ABT review1 T. Kramer, L. Ducimetiere, L. Sermeus.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
4 November 2014 Mike Hourican TE/ABT1 LIU-SPS Injection Upgrade With input from Jan Borburgh, Bruno Balhan.
PXI-Kicker Generator Control Jan Schipper TE-ABT-EC.
Semiconductor Switch Designs M.J. Barnes Acknowledgements W. Bartmann, L. Ducimetière, B. Goddard, J. Holma, A. Lechner, T. Fowler, T. Kramer, M. Meddahi,
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
LIU-IONS Linac3 meeting LIU Project – Planning and Installation Julie Coupard EN/MEF-OSS.
MKI Erratics: Hardware and Electronics Related Aspects M.J. Barnes Acknowledgements: A.Antoine, R.A. Barlow, P. Burkel, E. Carlier, N. Magnin, V. Mertens.
Plan. 12/05/ Who are we? PM (Project Management and Resource Planning) – APT – IMPACT – PPTEU2 – Plan LS1 – 2012 –…–… Plan V2 – From LS1 to LS2.
STATUS OF THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team March 6, 2012CERN.
Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
R. Rosol, LIU-PSB review, 10 September BI.DIS Pulse generators R. Rosol, LIU-PSB review, 10 September Luc SERMEUS, Rodolphe ROSOL Laurent.
LIU external beam dump review External beam dump option A: branching off from LSS6 J.L. Abelleira Thanks to: F. Velotti, B. Goddard, M. Meddahi, H. Vincke,
ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT.
Replacement of Obsolete/Old Hardware L. Ducimetière SPS Consolidation Review Luc Sermeus, Mike Barnes, Viliam Senaj, Thomas Kramer, Luis Feliciano, Vasco.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
SBDS – MKDV/H: The new MKDV Generator and additional Magnet for BA5 installation V. Senaj, L. Ducimetière November 20 th 2015.
Extraction and beamline progress B.Goddard TE/ABT.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
LIU-ABT systems: SPS T. Kramer, E. Carlier, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 4 th November /11/2014 SPS LIU-ABT Systems Review2.
LIU budget cuts – SPS savings? First brainstorming discussions!!! BG 30/4/14.
POTENTIAL EN-MME DESIGN JOBS IDENTIFIED BUT CURRENTLY NO REQUEST FROM EQUIPMENT OWNERS TO EN-MME EDMS B.RIFFAUD On behalf of EN-MME design team.
MKP-I Kicker System Design and Feasibility M. Barnes, L. Ducimetiere, T. Kramer, L. Sermeus E. Carlier, B. Goddard, W. Höfle, R. Noulibos, G. Kotzian,
The way to fast and "loss-free" SPS kickers E. Gaxiola With contributions from AB-BT-KSL section and F. Caspers, T. Kroyer, M. Timmins, J. Uythoven.
Technology Department MKP status L. Sermeus, L. Ducimetière TCM 18 November 2014.
MTE: Statistics of kickers faults Etienne Carlier, Luis Feliciano, Laurent Ducimetière, Brennan Goddard, Luc Sermeus 1 19 October 2015 MTE internal review.
ELENA KICKERS AND SEPTA ELENA Meeting, Prepared by J. Borburgh, E. Carlier, A. Fowler, L. Sermeus TE/ABT.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
SPS BEAM DUMP UPGRADE FUTURE CABLING CAMPAIGNS Georgi Minchev Georgiev EN-EL-FC.
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Udo Blell - Synchrotrons 1 Udo Blell GSI, Darmstadt MAC – 7 April 2 th - 3 th, 2012 FZ - Jülich SIS 100 Injection / Extraction systems.
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
2 BT.KFAs kicker rise time measurements (December 2015) L. Sermeus TE/ABT/FPS LIU-PSB meeting, 19 th January 2016.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
PSB extraction and transfer kickers LIU TE-ABT review, 20 November L. Sermeus.
LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.
MKDV upgrade LIU-SPS ABT meeting V. Senaj, L. Ducimetiere, P. Faure November 4 th 2014.
Wim Weterings Remy Noulibos
S A Griffiths CM42 June 2015 Electrical & Control.
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
ABT-EC EYETS Activities 2nd reports
CT Hardware Overview and Issues
Brief Status SPS Prototype PSB Prototype Installed in LS1
PS-CT: ERD-2 switch tank harmonization
HV-Cables Current standard product is RG-220/U like cables from Draka. Limited to max. 40kV Not compatible for CPS SF6 gas filled PFL.
LIU – EVM status and next steps
Future Kicker Generator strategy
EC Activities Status for the LIU
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Status of the BI Work Package in the LIU-PSB frame
prepared by R.A.Barlow 30/056/2016
Acknowledgments: LIU-PT members and deputies, H. Bartosik
LIU and TE/ABT/PPE activities
Status with crucial LSS5 kicker transmission line cables
MKI Operational Experience and Future Plans
LIU-SPS review for BI (no BWS)
Status of the BI Work Package in the LIU-PSB frame
SPS Injection BIS - Draft requirements
KFA10 status 03/06/2019 Currently:
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

LIU-SPS T. Kramer, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 20 th November /11/2015 LIU-ABT Review - SPS2

Status Functional specification available ( SPU-M-ES-0001 /EDMS ). 2 nd iteration submitted to LIU-ION management. Established 100ns test stand in 867 in February/March. 1 st measurements with diode configuration performed (>200ns tr / not optimized). 2 nd thyratron configuration still to be done. Mid 2015: decision to postpone project to after LS2 -> SPS ion inj. not LIU anymore! However: Feasibility study for 100 ns kicker shall be finished within LIU with reduced priority. Resources: Received 1 FTEC. LIU-ABT Review - SPS 3 20/11/2015

Budget 20/11/2015 LIU-ABT Review - SPS4 Year PV EV 150 AC 18 Covers only inj. kicker WU (as only WU with remaining activities)

Conclusions Functional Specification Functional Specification for SPS ion inj. available (v2.0, not approved). Decision taken to postpone project: Decision taken to postpone project: Budget Budget cut (saved 1.92M on kickers) <100k requested in 2016 (50k in 2017). Test stand established reduced priority.. Test stand established but operated with reduced priority. Presently remains within LIU - work to be done in Feasibility study (LIU) Feasibility study (LIU) to be delivered in /11/2015 LIU-ABT Review - SPS5

THANK YOU FOR YOUR ATTENTION!

New SPS Injection Layout for Ions (100ns)  Use existing (fast) MKP-S kicker with additional PFL.  Additional septa (MSI-V) needed.  Requires ion injection dump upstream QD MKP-S MKP-L TBSJ MSI MSI-V SPS LSS1 7 MSI MSI-V MKP-S TDI Element Magnetic Length [m] Deflection [mrad] MSI-V (2)1 per mag.12.3 MSI (4)2.1 per mag.42.8 MKP-S (12)8.63 all2.07  17 GeV/c/u PB 82+  100 ns rise time  Q20 compatible  Low impedance impact FS chapter 3; page 6 f. LIU-ABT Review - SPS

HV-connection of PFL & PFN to Magnet (I) 20/11/2015 LIU-ABT Review - SPS8 2 x 3 RG-220U Transmission cables MS Thyratron PFN PFL 3 x 25Ω? 70m 2 x 3 RG-220U Transmission cables MS Thyratron (PFL) PFN PFL 3 x 25Ω? 70m MS Thyratron (PFN) Magnet Module n+1 Magnet module n Magnet Module n+1 Magnet module n 8.3 Ω 16.6 Ω Option 1Option 2

Initially Planned Schedule 20/11/2015 LIU-ABT Review - SPS9 SPS MKP 100ns PFL upgrade 2014LIU-SPS Ion Injection Functional Specification (Done, waiting for other WU and approval ) Early 2015Basic 100ns PFL test stand available (867). Mid 2015Basic 100ns PFL tests and analysis finished. Carry on with extended tests if necessary (see option1/2). Q4/2015Detailed system design & Technical Specification available. EOY 20151st drawings available. Q2/2016All Drawings available. Long lead items ordered. Production for “in-house” subcomponents started. 2017Production and preassembly. Q2/2018Preassembly finished – QA lab testing of produced components. Aug/2018Installation of PFL cables. Q4/2018Modification of PFN tank/ installation of PFL switch components. 2019Installation of RCS, connection of new components to controls system. EOY/2019All activities finished. Q1/2020HW/Beam commissioning. Activities in parallel with KFA-53(45?) development!

Budget (2014) 20/11/2015 LIU-ABT Review - SPS10 all in kCHF 100 ns Injection kicker Proto-type150 Design office150 6 PFLs300 6 switches420 6 connections PFN/PFL300 3 Resonnant Charging Systems (50% EC)150 BA1 modifications (40% EC)100 Cabling (50%EC)100 Slow controls90 Fast controls60 Interlocking30 FSU controls50 S 1900 FSU FPS200 Total2100