vacuum conditions in PANDA pbar-line Alexander Gruber, SMI, Vienna, Austria
A. Gruber XXVIII. PANDA meeting GSI PANDA layout status as of week 08/2009 extending dump pipes with additional 150 mm Ø tube, so that dump outside cut-out of yoke some changes in design vacuum system since Dec. 2008: extending vertical pipes of cross, so that gate valves outside of muon chambers opening Ø of tube inside FS to 180 mm luminosity monitor (placeholder) Ø 250 mm
A. Gruber XXVIII. PANDA meeting GSI PANDA vacuum system status as of week 09/2009 some changes in design since Dec (some of which will be discussed this week): opening angle 45° - to be discussed flange at z=-852 mm (outside of endcap EMC) – to be discussed luminosity monitor (placeholder) Ø 250 mm
A. Gruber XXVIII. PANDA meeting GSI calculations vacuum in pbar-line studies on effect of opening angle of big upstream conus on vacuum in the upstream section: pressure along 150 mm Ø pipe towards upstream TMPs only decreasing from to upper mbar alarm: many pbars destroyed before reaching IP (thickness of residual gas) again review of vacuum situation in pbar-line with current layout try putting cryopump inside beam pipe next to cone calculations with VAKLOOP: pressure profile for H 2 calculating thickness of residual H 2 -gas outgassing of air (N 2 ): pressure profile of air due to outgassing from walls only thickness of residual gas (N 2 )
A. Gruber XXVIII. PANDA meeting GSI geometry for calculations for H 2 leak rate from target: mbar*l/s mbar*l/s mbar*l/s leak rate from dump: mbar*l/s S H2 ~ 750 l/s S H2 ~ 480 l/s TMP S H2 ~ 750 l/s IGP S H2 ~ 800 l/s cryopump: 100 mm long 100 mm Ø (one cold facet) 50 mm Ø (2 cold facets) S = 10 l/s*cm² S = 3142 l/s
A. Gruber XXVIII. PANDA meeting GSI Schematics of PANDA for VAKLOOP … gate valve from HESR 3,4 … upstream TMPs 5 … end cone 4,5 … TMPs of collimator chamber 6 … IP 7 … “leak” from target 8 … “leak” from dump 9 … end of target cross (20 mm Ø ) 11,12 … TMPs behind TS 14 … TMP behind FS 15 … ion getter pump 16 … gate valve to HESR 7 8 9
A. Gruber XXVIII. PANDA meeting GSI pressure along pbar-line
A. Gruber XXVIII. PANDA meeting GSI sections 0 & 1
A. Gruber XXVIII. PANDA meeting GSI pressure in sections 0 & 1
A. Gruber XXVIII. PANDA meeting GSI sections 2 & 3
A. Gruber XXVIII. PANDA meeting GSI pressure in section 2
A. Gruber XXVIII. PANDA meeting GSI pressure in section 3
A. Gruber XXVIII. PANDA meeting GSI section 4
A. Gruber XXVIII. PANDA meeting GSI pressure in section 4
A. Gruber XXVIII. PANDA meeting GSI pressure along pbar-line
A. Gruber XXVIII. PANDA meeting GSI sections 5 & 6
A. Gruber XXVIII. PANDA meeting GSI pressure in sections 5 & 6
A. Gruber XXVIII. PANDA meeting GSI pressure along pbar-line
A. Gruber XXVIII. PANDA meeting GSI geometry for calculations for N 2 no leak rate from target no leak rate from dump S N2 ~ 1000 l/s S N2 ~ 500 l/s TMP S N2 ~ 1000 l/s IGP S N2 ~ 800 l/s cryopump: 100 mm long 100 mm Ø (one cold facet) 50 mm Ø (2 cold facets) S = 10 l/(s*cm²) S = 3142 l/s all surfaces outgassing with 1* mbar*l/(s*cm²) (stainless steel) 5* mbar*l/(s*cm²) (Ti) (values after pumping > 24 h) [J.F.O‘Hanlon: User guide to vacuum technology]
A. Gruber XXVIII. PANDA meeting GSI total pressure in pbar-line
A. Gruber XXVIII. PANDA meeting GSI total pressure in pbar-line
A. Gruber XXVIII. PANDA meeting GSI resulting thickness residual gas
A. Gruber XXVIII. PANDA meeting GSI conclusions Need concrete numbers of gas load into pbar-line from both targets (and dump) Since mbar*l/s is realistic influx resulting thickness residual gas almost in order of target thickness ! Could reduce thickness of residual gas in backstream section with a cryopump (enough space available) BUT: what about thickness in downstream part inside the TS ?