Ralph Assmann 1

Slides:



Advertisements
Similar presentations
Collimation with retracted TCSGs R. Bruce, R. Kwee, S. Redaelli.
Advertisements

Simulation priorities for 2015 R. Bruce for task 5.2.
Critical beam losses during Commissioning & Initial Operation Guillaume Robert-Demolaize (CERN and Univ. Joseph Fourier, Grenoble) with R. Assmann, S.
Collimation MDs LHC Study Working Group Daniel Wollmann for the Collimation-Team, BLM-Team, Impedance-Team, … LHC Study Working Group,
GRD - Collimation Simulation with SIXTRACK - MIB WG - October 2005 LHC COLLIMATION SYSTEM STUDIES USING SIXTRACK Ralph Assmann, Stefano Redaelli, Guillaume.
Loss maps of RHIC Guillaume Robert-Demolaize, BNL CERN-GSI Meeting on Collective Effects, 2-3 October 2007 Beam losses, halo generation, and Collimation.
6/14/11 Collimation Upgrade Plan & Questions R. Assmann, CERN for the collimation team 14/6/2011 LHC Collimation Project Review.
External Review on LHC Machine Protection, CERN, Collimation of encountered losses D. Wollmann, R.W. Assmann, F. Burkart, R. Bruce, M. Cauchi,
Ralph Assmann What Do We Want To Measure (in 2009) R. Assmann S. Redaelli, V. Previtali CERN/BE discussed with W. Scandale CERN/EN26/3/2009CC09  See also.
Concept of a Collimation System with Enhanced Operational Stability and Performance.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
CASA Collider Design Review Retreat HERA The Only Lepton-Hadron Collider Ever Been Built Worldwide Yuhong Zhang February 24, 2010.
ESGARD – OMIA 10 & 11/09/2007 JRA on Collimators and Materials for High Power Accelerators Motivation Work Packages Partners & resources R. Assmann.
Work required to have a proposal in June (for discussion) RA, CPM, 15/4/03.
IEFC WS March 2011 Middle-Long Term Needs for Ion Beams S. Maury 111 Middle-Long Term Needs for Ion Beams S.Maury Thanks to T. Bohl, C. Carli, D.
RA CPM 21/2/03 1 Present Approach and Status R. Assmann for the LHC Collimation Team Problem: Al/Cu system would not resist irregular dumps (pre-trigger.
Preparation of Review R. Assmann et al CWG, CWG R. Assmann.
Stefano Redaelli, CERN, BE-ABP on behalf of the LHC Collimation Project and HiLumi WP5 LHC Collimation Status and Plans 2 nd Joint HiLumi LHC-LARP Annual.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
CERN Phase II Collimation Conceptual Review Summary 09 April 2009 LARP CM12 Napa, CA Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research.
Updates on FLUKA simulations of TCDQ halo loads at IR6 FLUKA team & B. Goddard LHC Collimation Working Group March 5 th, 2007.
RWA, 4/11/2005 Review Movement & Motorization November 4 th, 2005 Program Introduction & Charge – R. Assmann Mechanical design & SPS results – O. Aberle.
Thursday 28 January 2010 Session 8 - LHC Upgrade Plans for the first long Shutdown (Convener: Oliver Bruning, Paolo Fessia )
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Heat Deposition Pre-Evaluation In the context of the new cryo-collimator and 11-T dipole projects we present a review of the power deposition studies on.
LHC off-momentum collimation simulation Hector Garcia Morales Royal Holloway University of London Roderik Bruce, Danielle Mirarchi, Belen Salvachua, Kyrre.
Case study: Energy deposition in superconducting magnets in IR7 AMT Workshop A.Ferrari, M.Magistris, M.Santana, V.Vlachoudis CERN Fri 4/3/2005.
Collimator settings for 2012 R. Bruce, R. Assmann for the collimation team
R. Assmann, June 2009 Operational Experience with the LHC Collimation System R. Assmann, CERN 8/6/2009 for the Collimation Project Team Visit TU Munich.
Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,
NM4SixTrack Implementation of new composite materials for HL-LHC collimator upgrades in SixTrack “Tracking for SixTrack” workshop – CERN, R.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Backgrounds at FP420 Henri Kowalski DESY 18 th of May 2006.
Summary Session 5 Chamonix 2011, 24. – Session 5: “High Intensity: Present and Future” R. Assmann & S. Redaelli Thanks to Frank Z. for his notes…
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
Ralph Assmann Performance of LHC Collimation R. Assmann, CERN 13/09/2010 ColMat Meeting, GSI … for the LHC Collimation Project CERN and EuCARD/ColMat Collaboration.
How low can we go? Getting below β*=3.5m R. Bruce, R.W. Assmann Acknowledgment: T. Baer, W. Bartmann, C. Bracco, S. Fartoukh, M. Giovannozzi, B. Goddard,W.
Ralph Assmann Collimation Project R. Assmann, CERN 26/4/2010 CERN Machine Advisory Committee.
29 October 2015 B. Di Girolamo. B. Di Girolamo – Collider-Experiments Day – 5 th HiLumi Annual Meeting 2 Collider-Experiments Interactions There is a.
News and Introduction from CERN June 15th, 2005
Ion Commissioning: Thursday & Friday
Tracking simulations of protons quench test
S. Roesler (on behalf of DGS-RP)
Machine-Experiment Interface
Scope of the Meeting: the Framework of the Collimation Project
Joint Meeting SPS Upgrade Study Group and SPS Task Force
Progress in Collimation study
Upgrade Strategy for the Experimental Vacuum Systems
Β*-reach in 2017 R. Bruce, S. Redaelli, R. De Maria, M. Giovannozzi, A. Mereghetti, D. Mirarchi Acknowledgement: collimation and optics teams, BE/ABP,
Energy deposition studies in IR7 for HL-LHC
Beam collimation for SPPC
Intensity Evolution Estimate for LHC
CERN, Geneva, Switzerland PAC 2003 – Portland, Oregon, USA
Proton Intensity Evolution Estimates for LHC
Introduction to dispersion suppressor collimation
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
LHC Collimation Requirements
HiRadMat Test Facility
Optic design and performance evaluation for SPPC collimation systems
Beam halo and beam losses in IR1 and IR5
Collimation after LS1: cleaning and β* reach
Collimation margins and *
Beam Loss Simulations LHC
Draft of Conceptual Phase 2 Collimation System Design
Introduction and Requirements
Collimators: Operations - Baseline Assumptions
LHC External Collimation Review
Another Immortal Fill….
IR/MDI requirements for the EIC
HI2011 Commissioning Status
Presentation transcript:

Ralph Assmann 1

Charge Review the overall priorities and the schedule defined in the LHC collimation project. Review the work in the dispersion suppressors, proposed for Take a decision on starting the work for a 2012 collimation upgrade in IR3. –Upgrade of DS. –Installation of vertical collimators into IR3 warm part. 2

Ralph Assmann Project Overview R. Assmann, CERN 8/7/2010 Review on 2012 DS Work

Acknowledgements I am very glad we are here and are having this review today (no matter what decision is taken in the end). This was made possible by the hard work of many colleagues: –Thanks to the project engineers A. Bertarelli and O. Aberle. –Thanks to V. Parma and J.P. Tock for giving crucial TE support. –Thanks to T. Weiler, A. Rossi, S. Redaelli, J. Jowett, D. Wollmann, G. Bellodi, F. Cerruti, V. Vlachoudis, V. Boccone, E. Metral, N. Mounet, … for studies –Thanks to all members of the technical WG led by V. Parma and A. Bertarelli: Delio Duarte Ramos, Thierry Renaglia, Rob Van Weelderen, Vincent Baglin, Alessandro Masi, Katy Foraz. –Thanks to group leaders involved: R. Folch, R. Losito, L. Rossi, O. Bruening, M. Lamont, M. Jimenez, … Ralph Assmann 4

Introduction Collimation project put in place by S. Myers and E. Chiaveri in 2002 to find & implement adequate solution for LHC collimation. Goal: “Best possible system for LHC startup, upgradeable to reach nominal and ultimate performance”  no change in SC areas allowed! Highest priority on system robustness and radiation hardness. Compromises on impedance, cleaning efficiency, remote handling, advanced operational diagnostics, air activation, … accepted. Collimation construction included tunnel preparations for advanced collimators (~5 MCHF investment). Collimation upgrade started as R&D project in 2008, supported by new initiative funds and EU grants. Decision on construction envisaged after first LHC beam experience. Now it is time to decide on construction if we want this upgrade in place for ~2015/6. Ralph Assmann 5

Collimation is Designed for Upgrades! EMPTY PHASE II TCSM SLOT (30 IN TOTAL) PHASE I TCSG SLOT

Overall Collimation Plan Ralph Assmann 7 Initial collimation system (2009 – 2011) Inefficiency: 0.02 %  * ~ 2 m R2E limits in IR7 > 4 days per setup Initial collimation system (2009 – 2011) Inefficiency: 0.02 %  * ~ 2 m R2E limits in IR7 > 4 days per setup Full collimation system (2016 onwards) Inefficiency: %  * ~ 0.55 m L not limited 30 s per setup Full collimation system (2016 onwards) Inefficiency: %  * ~ 0.55 m L not limited 30 s per setup Interim collimation system (2013 – 2015) Inefficiency: %  * ~ 1 – 2 m Gain ~100 in R2E (IR7  IR3) L ≤ 5 × cm -2 s -1 > 2 days per setup Interim collimation system (2013 – 2015) Inefficiency: %  * ~ 1 – 2 m Gain ~100 in R2E (IR7  IR3) L ≤ 5 × cm -2 s -1 > 2 days per setup 2012 shutdown 2015/16 shutdown Details presented in past LMC’s, Chamonix, external collimation reviews, CERN Machine Advisory Committee, … Not repeated here!

Interim Collimation Collimation upgrade in IR3 dispersion suppressors to capture p losses due to single-diffractive scattering and to capture ion losses (removes highest predicted and highest measured loss). 2.Collimation upgrade in IR3 warm insertion (10 vertical collimators added) to add flexibility for relocating losses from IR7 to IR3 (SEE limitations). 3.Prepare work for 2015/16 collimation upgrades. Gain: Hope to reach nominal intensity and up to half nominal luminosity. Lower complexity. Smaller horizontal impedance. Higher cleaning efficiency. Price to pay: Twice larger vertical impedance, additional loss spike in IR5 and higher losses at tertiary collimators. IR3 upgrade is an excellent step forward but no miracle solution. Ralph Assmann 8

Full Collimation Collimation upgrade in IR7 and IR2 dispersion suppressors to capture p losses due to SD scattering and to capture ion losses. 2.Installation of advanced collimators (mostly into prepared empty slots) to allow non-destructive and very fast collimator setup, compatible with LHC stability and small  * (0.55m). SLAC very motivated to participate to construction, “regardless of the technology chosen for the secondary collimators to be installed” ( associate lab director B. Hettel). 3.Collimation upgrade in IR1 and IR5 for luminosity-induced losses from collisions (install 4 already produced Cu collimators). 4.Collimation upgrade in IR2 for ZDC acceptance issue. EARLIER??? 5.Remote handling and air bypass operational in IR7. 6.Additional tungsten absorbers in IR6 dump protection system to improve local cleaning. Ralph Assmann 9 Not discussed today!

Dispersion Suppressor Work Addresses a very basic limitation of the LHC collimation system: protons loose energy when hitting matter, ions dissociate and fragment! Could not be addressed before: collimation started very late in the game and SC areas of LHC were frozen. Note that this is nothing exotic: other accelerators had this (e.g. LEP2 added collimators into dispersion suppressors). A solution without new SC magnets was proposed: allows collimation readiness for nominal and ultimate beams by 2015/6 at latest (if we start). Other solutions are nice but would come much later (e.g. shorter magnets with collimator in front).  What – Where – Why Ralph Assmann 10

-3 m shifted in s halo Halo Loss Map Upgrade Scenario +3 m shifted in s Downstream of IR7  -cleaning transversely shifted by 3 cm cryo-collimators NEW concept Losses of off-momentum protons from single-diffractive scattering in TCP without new magnets and civil engineering TCRYO

Is This a Real Problem? Look at Measurements! (Beam 1, Vertical Plane, 1.3s) LHC Collimation team 12 factor 5,000 cleaning to SC arc magnets TCT Dump TCT Off-momentum Betatron Highest SC losses all around the LHC ring Simulated ideal performance

Zoom into Betatron Cleaning Region (Beam 1, Vertical Plane, 1.3s) LHC Collimation team 13 TCT Dump SC magnets act as halo dumps  not good! Gain factor > 10 by catching losses with collimators! SC magnets act as halo dumps  not good! Gain factor > 10 by catching losses with collimators!

Is the LHC Cryo-Collimator Feasible? The technical WG has identified a cryo-collimator solution: –Fits into 4.5 m slots. –Has no visible show-stopper. –Four units can be built until November –Allows to close the cryostat by March 2013 (limited by resources). Accelerator physics and shower studies have been performed: –Optics has been matched for 4.5 m slots and aperture checked. –LHC performance (efficiency, impedance) has been simulated. –Feasibility and important gains have been verified (few drawbacks as well). The solution is technically feasible but time is very tight. Ralph Assmann 14

How Long Can We Live Without Cryo-Collimators? For sure not forever! Losses will always hit the same spots in the same magnets! SC magnets are very bad as collimators: quench, radiation damage, … Situation will be much worse at 7 TeV! Loose factor ~10. Ralph Assmann e e TeV quench level Ideal Inefficiency Quench Limit  Factor 3 higher leakage!  Factor 3 lower quench limit!

How Long Can We Live Without Cryo-Collimators? I did no answer yet. Depends all on assumptions on loss rates. Specified maximum loss rate is 0.1 %/s of total beam intensity (0.2 h beam lifetime for up to 10s). Drastic losses observed: up to 26 %/s. In every physics fill, that I looked at, we see losses above the specification during the cycle. Likely not better for more bunches: –Higher impedance. –Long-range beam-beam effects. I think nobody can predict the future losses in detail (also not me). Fact: Presently we profit from the high collimation efficiency as it allows us pushing intensity much more efficiently (no quenches). Ralph Assmann 16

Prediction: Intensity Limit with Initial Collimation vs Energy (LMC ) Ralph Assmann 17 LHC beam energy 2010/11 Limit intermediate settings Limit tight settings Significant uncertainties. Will improve as more parameters are verified in operation (e.g. quench limit, loss dilution, …)

Do We Need the Best Brakes? Good brakes allow you to go faster and safer! Do not assume you never must brake! If they work too well you will not complain but if they do not work well… Collimators are the brakes of the LHC except that they cost relatively less: so far 1% of the LHC! Ralph Assmann k€ 9 k€ 70 MCHF 3,000 MCHF

Can we do it? Possible but tight! Ralph Assmann 19

Risk Assessment In case we do not continue and LHC loss remains at/beyond specification: –Cryo-collimators will for sure not be ready for 2012/13 shutdown. –Risk to be limited in luminosity reach after 2012/13 shutdown: we could be ready for 7 TeV after heavy work and then deliver insufficient luminosity. –Risk to limit LHC discovery potential in 2013 – 2016 due to long known collimation features (DS collimators were installed for LEP2). –Risk from upgrading dispersion suppressors for 3 IR’s in parallel during 2015/16! –Risk to do a larger than required upgrade in 2015/6 without IR3 experience. In case we push forward now and LHC losses can be very much reduced: –Loss of resources for design and preparation of cryo-collimators. Installation plans can still be stopped in Summer 2011 (one year from now). Ralph Assmann 20

Possible Impact from IR3 Experience on Overall Collimation Plan Parts of the collimation upgrade plan must in any case be implemented: –IR collimation upgrades for high luminosity in 2015/6 –IR6 improvements in 2015/6 –IR2 dispersion suppressor upgrade in 2015/6 for ion luminosity –Advanced collimators for non-destructive and fast setup in 2015/6 However, the IR7 upgrade details might be strongly affected: –Maybe IR3 can take over parts of IR7 functionality permanently? –Less or no losses in IR7 could avoid need for remote handling, air duct, air conditioning, replacement of warm IR7 magnets, replacement of IR7 collimators (due to radiation damage), … The early 2012/13 implementation of an IR3 upgrade will give time to explore the performance reach with this system and to minimize IR7 work! Ralph Assmann 21

Our Proposal 1.Decide to move ahead for collimation upgrade in IR3 dispersion suppressors as fast as possible. Implement the warm collimator solution. 2.Decide to move ahead for upgrade of warm IR3 insertion with vertical collimators. 3.Decide to start designing, prototyping and building required hardware. 4.Agree on goal to achieve readiness for 2012/3 installation. There is hope but we cannot guarantee it. 5.Agree on decision date for actual installation in Summer This decision will take into account operational experience in Decide on ALICE request for 2012/3 upgrade of IR2 collimation (4 additional collimators).  Decisions are now required. No decision is the same as a no! Ralph Assmann 22

Ralph Assmann 23