US Belle II Project Overview Jim Fast Pacific Northwest National Laboratory.

Slides:



Advertisements
Similar presentations
Roadmap for Sourcing Decision Review Board (DRB)
Advertisements

PROJECT RISK MANAGEMENT
Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
1 Schedule Risk Assessment (SRA) Overview July 2013 NAVY CEVM.
Secure System Administration & Certification DITSCAP Manual (Chapter 6) Phase 4 Post Accreditation Stephen I. Khan Ted Chapman University of Tulsa Department.
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
NuMI Offaxis Costs and Whither Next Stanley Wojcicki Stanford University Cambridge Offaxis workshop January 12, 2004.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
Advanced Project Management Project Plan Templates
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
LCG Milestones for Deployment, Fabric, & Grid Technology Ian Bird LCG Deployment Area Manager PEB 3-Dec-2002.
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
OSF/ISD Project Portfolio Management Framework January 17, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
Project Initiation Document (PID) Strategic Plan PID Committee Meeting - November 5, 2012.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 Community-Based Care Readiness Assessment and Peer Review Team Procedures Overview Guide Department of Children and Families And Florida Mental Health.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
BSBPMG505A Manage Project Quality Manage Project Quality Project Quality Processes Diploma of Project Management Qualification Code BSB51507 Unit.
Project Overview How to get here…. Half Way to the Test Run October 18, 2012HPS Project Overview2 …starting from here? John Jaros HPS Collaboration Meeting.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Executive Session Director’s CD-1 Review of the LBNE Project September 25, 2012 Jim Yeck.
DOE Order 413.3A Program and Project Management for the Acquisition of Capital Assets Catherine Santana Deputy Director, Project Management Systems, OECM.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Apply Quality Management Techniques Project Quality Processes Certificate IV in Project Management Qualification Code BSB41507 Unit Code BSBPMG404A.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
Earned Value Management Update Nancy L. Spruill Director, Acquisition Resources and Analysis Office of the Under Secretary of Defense (Acquisition, Technology.
TGDC Meeting, July 2011 Voluntary Voting System Guidelines Roadmap Nelson Hastings, Ph.D. Technical Project Leader for Voting Standards, ITL
Project Initiation at The Regence Group 12/19/2015John Garrigues1.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
Evaluate Phase Pertemuan Matakuliah: A0774/Information Technology Capital Budgeting Tahun: 2009.
John J. LeRose 1.  Roles/Responsibilities/Organization  Approach  Goals and Objectives  Scope  WBS’s  WBS 1  Funding profile  Schedule  Critical.
John J. LeRose 1.  Roles/Responsibilities/Organization  Approach  Goals and Objectives  Scope  Schedule  Funding profile  Risk management  EH&S.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
Project X Working Group Meeting January 15, :00 PM Snake Pit.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
PDS4 Project Report PDS MC F2F University of Maryland Dan Crichton March 27,
European Spallation Source Overview and Status Technical Advisory Committee 1-2 April 2015 James H. Yeck ESS CEO & Director General
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
US Belle II Project Overview Jim Fast Pacific Northwest National Laboratory.
Project Overview James Fast Pacific Northwest National Laboratory.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
IV&V Facility 7/28/20041 IV&V in NASA Pre-Solicitation Conference/ Industry Day NASA IV&V FACILITY July 28, 2004.
US Belle II Project – Technical Elements David Asner Pacific Northwest National Laboratory.
ITOP Quartz Procurement Status James Fast Pacific Northwest National Laboratory PNNL-SA
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
WBS 1.04 KLM Leo Piilonen Virginia Tech. Talk Outline WBS Element Scope Performance Requirements Cost Summary Schedule Risks Summary January 2014Leo.
WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii.
Director’s Progress Review Closeout Meeting
Jim Fast Pacific Northwest National Laboratory
Jefferson Lab Overview
Project Management W. J. Foyt
WBS 1.03 Readout Systems Scope, Cost and Schedule
Preparations for a Lehman Review
Director’s Progress Review Closeout Meeting
Linac Coherent Light Source (LCLS)
Preliminary Project Execution Plan
Conventional Facilities
Presentation transcript:

US Belle II Project Overview Jim Fast Pacific Northwest National Laboratory

Outline Project Scope Key Performance Parameters Project Schedule Project Cost Project Management Project Risks Project Reviews and Responses CD-2/3 Requirements Checklist Summary January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)2

US Belle II project scope: delivering key systems to KEK US Belle II Project 1.1 Project Integration and Support 1.2 iTOP Optics 1.3 Readout Systems 1.4 KLM Systems 1.5 Commissioning Detector KLM (WBS 1.4, readout WBS 1.3) iTOP (WBS 1.2, readout WBS 1.3) Trigger and Data Acquisition (WBS 1.3) Commissioning Detector (WBS 1.5) January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)3

CD-4 Definition Scope chosen to meet available funding Scope completion must not be contingent on external factors such as Super-KEKB operation Leads to somewhat unusual choice of where we transition from construction project to post- project integration, installation and commissioning phase (operations funds) – Construction project delivers parts or sub-assemblies for Belle II and KPPs defined around pre-installation testing of these, not final in situ performance

Key performance parameters January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)5

US Belle II project schedule is driven by KEK Belle II/SuperKEKB schedule KLM module installation summer 2013 Commissioning detector for SuperKEKB runs in 2014 and 2015 iTOP module installation spring January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)6

US Belle II project funding sufficient to complete in-scope work Cost estimate including contingency in at-year M$ $1.6M spent & committed 14% contingency on remaining costs 30% contingency on remaining non-quartz costs* January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)7 *Further discussed in WBS1.02 breakout in context of scope contingency related to preproduction optics

Project Contingency Assume use of preproduction bars and mirrors in experiment and total fabrication of 18 sets of optics ( spares) TEC+OPC = 12.68M; contingency $2.31M – Contingency 18.2% of total Remaining costs = $11.76M – Contingency 20.9% of remaining costs Remaining non-quartz costs = $6.75M – Allow for $0.3M contingency for quartz (allows for all Zygo bars) – $2.0M is then 34.3% of non-quartz remaining costs Question: Should the project assume use of preproduction optics in baseline at CD-3? January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)8

Funding profile matches guidance from OHEP January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)9

Strong management team in place and working together US Belle II Project IPT Members Federal Program Manager (Helmut Marsiske OHEP) Federal Project Director (Jeff Day PNSO); Contracting Officer (Ryan Kilbury PNSO) Contractor Project Manager (Jim Fast PNNL) January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)10

Major risks identified and mitigation strategies being executed The major risks have been identified and mitigation strategies developed Handling actions and due dates have been identified and are monitored Risks and handling actions are reviewed and reassessed ~quarterly Key risks: – ASIC developer is overcommitted and cannot complete all assigned scope on schedule. Mitigation strategy: Offloading work to other institutions (IU, Pittsburgh, PNNL, VT, WSU) – Quartz vendors have production problems and delivery of quartz is delayed or vendors must be added. Mitigation strategy (schedule): Prototyping, use of multiple vendors, understanding implications of non-ideal articles Mitigation strategy (cost): Multiple vendors have been identified and developed; contracts (to) include clauses allowing quantities to be reduced to allow flexibility to move production to alternate vendors in case of quality or schedule issue; differential cost for bars is understood and has been used to develop baseline cost and contingency – ASICs (TARGET or IRS) require an additional design cycle, delaying production. Mitigation strategy: Advanced TARGET testing with off-project collaboration interested in chip for other uses; following lower- risk development of IRS chip with discrete RF amplifiers rather than BLAB with integrated RF amplifiers – Grant-funded tasks do not produce required project-related outcomes and funding must be supplemented by project. Mitigation strategy: Working closely with grant monitor so that required funding levels are understood. Project contingency in these areas is high to account for possible need to move to project-funded resources January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)11

Belle II and US Belle II have been reviewed thoroughly Technical Design Review (KLM/Com. Det.) 13 December 2013 Technical Design Review (iTOP)/BPAC iTOP Mini Review 6-7 December 2013 Belle II Focused Review (BPAC) 9-10 September th BPAC March 2013 DOE Mini Review 17 December 2012 Belle II Focused Review (BPAC) 1-2 October 2012 CD-1 Independent Project Review 26 June 2012 Peer Review March 2012 Conceptual Design Review March th BPAC February 2012 Directors Review December 2011 Belle II Focused Review (BPAC) November th BPAC February 2011 Black: US Belle II Project Reviews Blue: Belle II Project Reviews BPAC: Belle Physics Advisory Committee January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)12

DOE Mini Review Recommendations Technical: 1.(Unchanged from June 26, 2012 DOE/SC CD-1 Review) See subsequent slides 2.Explore with Belle II management the possibility of shifting the iTOP installation date later by up to six months. This should be done before the next CD review. After September, 2013 BPAC Focused Review, Belle II management decided on partial iTOP installation on original schedule (spring 2015), followed by complete installation in future shutdown (summer 2017). Cost and Schedule: None Management: 3.Optimize the number of prototype quartz bars required and determine the overall vendor production rate for these materials in support of the CD-2/3 decision. Revised prototyping plan to 4 full sets of optics to evaluate vendor quality and production rates Prototype bars ordered from two vendors to compare cost/quality/production 4.Re-evaluate the current plan of requesting CD-3b in April 2013 and focus on a CD- 2/3 review request in July Eliminated CD-3b in light of technical readiness and continuing resolution January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)13

CD-1 IPR Recommendations Technical: 1.WBS 1.02 (iTOP) – Further work is needed to demonstrate the performance of the counter, both in Monte Carlo and prototypes. We recommend: a.The existing prototype should be tested with a particle beam and/or Cosmic Rays over the entire phase space (azimuth, track position, and polar angle) in the presence of backgrounds similar to what is expected in Belle II. The MC should also explore performance across the phase space of tracks in the bars of Belle II. b.The prototype results should be compared to a detailed Monte Carlo simulation to ensure that all features of the counter’s performance are adequate and well simulated. 2.WBS 1.05 (Commissioning Detectors) – Redundant neutron detector systems should be considered to back-up the “Micro TPCs” See subsequent slides Cost and Schedule: None Management: 3.Evaluate the potential of increasing the upper limit of the TPC TPC raised from $14M to $15M 4.Prepare for another mini-review in September Mini Review conducted December January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)14

Mini Review and CD-1 Recommendation 1a. The existing prototype should be tested with a particle beam and/or Cosmic Rays over the entire phase space (azimuth, track position, and polar angle) in the presence of backgrounds similar to what is expected in Belle II. The MC should also explore performance across the phase space of tracks in the bars of Belle II. Beam test was conducted the first week of June 2013 Full-size bars, spherical mirror, prism, IRS and CFD readouts Data taken at [cos  =0, x=0], [cos  =0.4, x=0], [cos  =0.4, x=200mm] Cosmic Ray Test stand established at KEK Fuji hall Prototype from beam test with CFD readout installed 1b. The prototype results should be compared to a detailed Monte Carlo simulation to ensure that all features of the counter’s performance are adequate and well simulated Significant simulation progress reported at BPAC Beam test conditions simulated for comparison with data details in next presentation and breakout sessions January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)15

CD-1 IPR Recommendation 2. WBS 1.05 (Commissioning Detectors) – Redundant neutron detector systems should be considered to back-up the “Micro TPCs” Alternatives reviewed and documented – most systems detect thermal neutrons Proton recoil only direct fast neutron technique Liquid scintillator counters are best alternative (gamma discrimination) Source direction possible using multiple cells (neutron scatter camera) however, there is not sufficient space in Belle to accommodate this He-3 thermal neutron detectors added to suite of instruments for commissioning System will be provided by new Canadian collaborators January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)16

BCR-01 Project is utilizing baseline change request process to track changes BCR-01 captures comprehensive set of changes after CD-1 IPR Need to add summaries of each BCR January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)17

CD-2/3 requirements on track RequirementDocumentationStatus Approve Updated Acquisition StrategyBelle-II Acquisition Strategy Updated. Approval at CD-2/3 Establish a Performance Baseline Belle-II Preliminary Project Execution Plan ✔ Approve Updated Project Execution Plan (PEP) Belle-II Preliminary Project Execution Plan Updated. Approval at CD-2/3 Complete a Final Design Belle-II Technical Design Report ✔ Conduct a Final Design Review Held 6-7 December 2013 at U. Tokyo and 13 December 2013 at SLAC ✔ Complete a Final Design Report Technical Design Report Completed December 2013 ✔ Employ a certified EVMS systemN/A RequirementDocumentationStatus Perform Baseline Validation (CD- 2) and Execution Readiness (CD-3) Review Planned for March/April 2013 – pending SC-28 guidance Prepare (CD-2) and Update (CD-3) Hazard Analysis Report Belle-II Hazards Analysis Report ✔ Continue with (CD-2) and Update (CD-3) Quality Assurance Program (QAP) Belle-II Project-Specific Quality Assurance Program ✔ Conduct Preliminary Security Vulnerability Assessment, if necessary (CD-2) and finalize SVA report (CD-3) Belle-II Preliminary Project Execution Plan, Section 8.8N/A Complete National Environmental Policy Act Strategy by issuing a Final Determination (i.e., EA). Categorical Exclusion (B3.6) for the US Belle-II Project ✔ January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)18

Summary The project management team is organized, capable and ready to proceed The Technical Design has been reviewed The recommendations from previous reviews have been addressed All of the CD-2/3 requirements have been met We are excited to execute the project and access the science that it will enable! January 2013James Fast, US Belle II Directors Review (Pre CD-2/3)19