Grid maintenance expenses Commerce Commission Workshop 2 March 2010.

Slides:



Advertisements
Similar presentations
Managing the Health and Safety of Contractors
Advertisements

Facilities Capital Planning and Management A program management overview prepared for Ferndale School Districts Facilities Planning Committee.
Demand Response: The Challenges of Integration in a Total Resource Plan Demand Response: The Challenges of Integration in a Total Resource Plan Howard.
PERFORMING EFFECTIVE BUILDING SYSTEM RECOMMISSIONING STUDIES Joseph J. Watson, P.E. Booth # 312.
Offshore Wind 2004 From Vindeby to Nysted A Manufacturer’s Experience Henrik Stiesdal Bonus Energy A/S.
Rate Plan. Value Story When asked, our customers identify the following topics as ways MidAmerican Energy provides value – Emergency Response.
FOG Guidance Document Launch Seminar 26th January 2012 Water Services Training Group Guidance Document Control of Fat Oil and Grease Launch Seminar 26.
TNSP Outputs for Use in Economic Benchmarking AER Economic Benchmarking Workshop #2 14 March 2013 Denis Lawrence and John Kain.
Contractor Safety Management
Frankfurt (Germany), 6-9 June 2011 Coordination between TSOs and DSOs – a necessity for system planning and operation Dr. Ralph Pfeiffer Amprion GmbH 1.
Seismic code and design standard for transmission line and substation in Japan September 3, 2003 Hajime Imura The Kansai Electric Power Co.,Inc.
RPI-X: Forecasting costs Regulation and Competition John Cubbin.
SUBSTATION HIGH VOLTAGE COMPONENTS
Substations. Substations Chapter 4 Substations Major types of equipment found in most transmission and distribution substations with their purpose,
ABS Ennin, George Coleman, David Dadson & Anthony Ansah
1 Introduction to Power Systems Expensive! Influential!Intrusive! Source: Riadh W. Y. Habash, Electromagnetic Fields and Radiation, Marcel Dekker, New.
Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP.
OCCUPATIONAL SAFETY AND HEALTH IN GHANA Ghana has a mixed economy dominated by agriculture, commerce, service and industry.
An Overview of Our Regulatory Proposal
Increasing the life cycle of existing grids to avoid high replacement costs of new systems By S.R.Sethi Member Delhi Electricity Regulatory Commission.
REGULATORY LEGAL AND CONTRACTUAL ASPECTS OF PPP IN WATER AJAY RAGHAVAN Counsel Training Workshop, Bhopal, February 2009.
Experience you can trust. Hurricane Hardening Commission Staff Workshop on Electric Utility Infrastructure Richard E. Brown, PhD, PE Tallahassee,
ELG4125 Transmission and Distribution Systems
APPLIED ELECTRICITY SS3
Office of Facilities Deferred Maintenance UTSA Strategic Resource Planning Council Deferred Maintenance UTSA Strategic Resource Planning Council March.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
Module 5, Unit A Vocabulary Review Game. 2 pt 3 pt 4 pt 5pt 1 pt 2 pt 3 pt 4 pt 5 pt 1 pt 2pt 3 pt 4pt 5 pt 1pt 2pt 3 pt 4 pt 5 pt 1 pt 2 pt 3 pt 4pt.
North Island Grid Upgrade Proposal Presentation to the Electricity Commission Conference 22 May 2007.
Barcelona, May 13, 2003 ASSET MANAGEMENT Development of new approaches Gerd Balzer Darmstadt University of Technology TU Darmstadt Institute of Electrical.
Care Act Presented by Simon Cheverst of RadcliffesLeBrasseur May 2015.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Digital recordkeeping strategy for mobile work processes Joel Smith HPRM System Administrator.
A Presentation On 132 KV GSS BEHROR
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
132KV GSS PIPAR CITY JODHPUR
Public Forum 10 December 2014 SAPN Regulatory Proposal Bev Hughson Consumer Challenge Panel Member.
A PRESENTATION On 400KV GSS SURPURA JODHPUR
2014 Hurricane Season Preparedness Briefing Jorge Puentes Technical Projects Manager – Northeast and Northwest Divisions March 26, 2014.
Craig T. Riesen Energy Workshop II 1 Electricity & Generation Basics of Electricity and Electrical Transmission Transmission Generation electrons.
1 Managing Distribution System Reliability at Southern California Edison Robert Tucker Thach “Nicholas” Duong Roger Lee OIR R Workshop May 26.
Presentation Topic: Circuit Breakers Represented to: Dr. M. Riaz Khan Represented by: M. Mujahid.
Default price-quality paths for gas pipeline services Briefing on the Commission’s final decision for financial market analysts 28 February 2013.
Energy Coal, HSEC, September 2009 ICAM : Oil Circuit Breaker Explosion Incident date: Saturday 5 th September, 2009 Before After.
ENERGY, PERFORMANCE & VALUE Dr Neil Blake, Head of EMEA Research & Rebecca Pearce, EMEA Head of Sustainability 30 th June 2015.
Capex Regulation in Australian NEM NZ Commerce Commission workshop – March 2010.
One Nottingham Lunchtime Learning Public Spending Cuts.
Identifying drivers of expenditure. Reasons for spending money 2 Effective regulation requires an understanding of why a business spends money Many different.
Top-down models of operating and capital expenditure.
Contestability in Connections Contestability Working Group Meeting NIE/SONI Joint Presentation 9 September
Initial observations on the Initial Observations Nathan Strong Chair, ENA Default Price Path Working Group.
AMEU QUARTERLY REPORT February 2017
Comparison of AIS and GIS Grid Station Muhammad Ali Ashraf Management Associate (Electrical) CPP Project.
Long-Term Planning Presented by: APP Site Visit Don Untch
Sub Station.
Agenda TSOG 8th November
SUB-STATIONS.
MAINTENANCE ENGINEERING
Chapter # 25 Sub-Stations risemark.pbworks.com.
Financial performance Update as at 4 August 2016
Work experience presentation
Emergency Lighting Design, Inspection and Maintenance Requirements
OSHA’s Final Rule: Electric Power Generation, Transmission, and Distribution Electrical Protective Equipment Presented to: RESAP Area Administrators Presented.
Mid-Continent Area Power Pool
Components of Substation
EHV Transmission Equipments
TxMAG presentation
Presentation to the Portfolio Committee - Labour
Substation Equipment's
Management of Change GROUP HSE RULE (CR-GR-HSE-302)
Presentation transcript:

Grid maintenance expenses Commerce Commission Workshop 2 March 2010

2 Overview Maintenance expenditure on the grid has increased significantly above CPI during the period of the Settlement There is a need for further increased maintenance expenditure Forecasts for next two years are $115.7 M and $119.8 M respectively (cf 2009/10 draft forecast outturn of $104.7 M) The main drivers for increased maintenance expenditure are: –Increased scope of work on ageing assets particularly the replacement of components of transmission line conductors and towers (lines projects have increased from $6.4M in 2006/07 to $19.1M in 09/10) –Accumulation of work deferred from previous years that cannot be delayed further without significant risk –Increased complexity of undertaking work Trees Regulations, Resource Management Act requirements, Landowner relationships –Limited availability of skilled labour and increased input costs –Growth in the number of substation assets to be maintained

3 Background Allowances for grid maintenance within the Settlement were based on historic levels adjusted only for CPI. An increasing quantity of grid assets (particularly transmission line components) is now reaching condition criteria where maintenance replacement is required This “wave of work” is expected to continue for several years Maintenance has increased above CPI during the period of the Settlement Some non-critical maintenance has been deferred in previous years to keep total operating expenditure within acceptable limits

4 Maintenance and total OPEX

5 Classification of maintenance Maintenance expenditure is categorised as follows: Transmission lines Routine maintenance Maintenance projects Substations Routine maintenance Maintenance projects

6 Grid Maintenance Summary2006/072007/082008/092009/102010/112011/12 Act $m Fcst $m Routine Transmission AC Stations HVDC Projects Transmission AC Stations HVDC Subtotal cf Settlement Allowance Pass Throughs Rates Total cf Business Plan

7

8 Transmission Lines Maintenance expenditure has increased over the period of the Settlement by approx 15 % p.a. Routine maintenance cost drivers: –Increased scope of work as a result of changes in risk management stance in accordance with Good Electricity Industry Practice: increased frequency of condition assessment (particularly following Otahuhu earthwire incident in 2006) pro-active management of access roads and bridges (particularly following Berryman case) more conservative management of trees close to lines (following serious safety incidents and actual tree strikes) –Increasing complexity of work (Trees Regulations, Resource Management Act requirements), and increasing landowner engagement –Increased input costs (contract hourly rates have increased above CPI, despite focus on cost-effective procurement)

9

10 Transmission lines Maintenance projects have increased from $6.4 M in 2006/07 to $19.1 M forecast in 09/10 Further increase forecast to $24 M in 2010/11 and 2011/12 Drivers include: –Increasing quantity of aged components on conductors and towers reaching condition criteria where replacement is required: Conductor components – joints, vibration dampers, conductor spacers Tower components - insulator attachment points, bolts, steelwork, foundation components, baseplates and stubs Note: replacement of these components is treated as expense because they are small parts of assets, rather than assets in their own right –Increased scope of work in testing of aged conductor to determine remaining life before re-conductoring is required –Accumulation of work resulting from maintenance deferred from previous years that cannot be further delayed without significant risk

11

12 Structural steelwork replacement Insulator attachment points

13 Conductor component replacements Mid span compression jointSub-conductor spacer Vibration damper

14 Substations Maintenance expenditure on substations and operations has not increased significantly over the period of the Settlement to date Routine maintenance cost drivers: –Increased scope of work to address poor asset performance (particularly disconnectors) –Increased scope of stations inspections for compliance with resource consent and HSNO regulations requirements –Increased costs of service charges (incl access charges for cable route across Auckland Harbour Bridge) –Increased input costs (contract hourly rates have increased above CPI) –Increased costs related to contractor training –For 2011/12, new maintenance requirements will arise from growth in assets: Otahuhu GIS substation, Drury and Whakamaru North substations, and new Static Var Compensator systems HVDC Pole 1 will be decommissioned partway through 2011/2012, but new routine maintenance costs will arise for HVDC Pole 3 in the same period

15 Substations Maintenance projects are variable between years, typically $5 – 10 M p.a. Dominated by major planned and forced repairs of power transformers, and maintenance projects on buildings Forecast for 2010/11 includes provision for: –Further transformer repairs, including temporary arrangements to restore security Expect a small number of major failures to occur each year until the older transformers are retired over the next years –Emerging requirements for new project work to review seismic strength of existing substation buildings in response to new standard NZS 1170

OPEX efficiency initiatives OPEX savings will follow capital replacements: –Replacement of maintenance intensive types of circuit breakers: Air blast Minimum oil –Replacement of maintenance intensive outdoor 33 kV switchyards with indoor switchboards –Replacement of aged single phase transformer banks –Replacement of HVDC Pole 1 converter stations Review of outsourced contracting arrangements in progress: –Improve contractor performance –Simplify contract management –Achieve cost efficiencies 16