Logo area 11 T Wire: Procurement Strategy and QA/QC B. Bordini, A. Ballarino, M. Macchini Acknowledgments: thanks to E. Charifoullina for her contribution.

Slides:



Advertisements
Similar presentations
LARP MSM Conductor, Cable and Procurement - A. Ghosh1 Strand, Cable and Procurement BNL -FNAL - LBNL - SLAC Magnet Systems Meeting Jan 09, 2014.
Advertisements

Spectrometer Solenoid Procurement Update Steve VirostekWing Lau Mike GreenStephanie Yang Lawrence Berkeley National LabOxford Physics MICE Collaboration.
Outline: Goals for the cable development at CERN. Main parameters of the cable. Cable development work for a cable width of 15.1 mm and for a cable width.
Oct , 2013, CDP D.R. Dietderich LARP Conductor & Cable Review 1 Conductor Development Program Support for LARP and HiLumi LARP- HiLumi Conductor.
TASK Conductor Studies First Proposal CERN – 09 th July 2015 EuroCirCol Meeting – WP5.
Collaboration Mtg, St Charles, IL 10/5-6, 2005 A. Ghosh1 Conductor R&D Plan Arup K. Ghosh BNL.
MQXF RRP® Strand for Q1/Q3 A. K. Ghosh MQXF Conductor Review November 5-6, 2014 CERN.
Status of MQXF Conductor LARP Update
AARD Sub-panel at Fermilab Feb , 2006 LARP Magnet R&D Program - S. Gourlay1 BNL -FNAL - LBNL - SLAC LARP Magnet R&D Program Steve Gourlay AARD Sub-Panel.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
Daniel Schoerling TE-MSC-MNC 1 Magnets Daniel Schoerling on behalf of WP 2.2 and WP 2.16 ELENA Project Review 14 th – 15 th October IT.
MQXF Cable for Q1/Q3 D.R. Dietderich MQXF Conductor Review November 5-6, 2014 CERN.
Specification of niobium sheets 031/05/2010 O. Capatina G. Arnau Izquierdo W. Weingarten S. Atieh.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
Quality assurance of the QXF- Q2 Nb 3 Sn cable mass production C. Scheuerlein, 6 November 2014 HL-LHC/LARP International Review of the Superconducting.
15 Th November 2006 CARE06 1 Nb 3 Sn conductor development in Europe for high field accelerator magnets L. Oberli Thierry Boutboul, Christian Scheuerlein,
Outline: Main characteristics of the FRESCA2 cable Main characteristics of the strand Strand stability, an issue to avoid magnet quench at low field Procurement.
LARP Meeting April 2006LARP Magnet Program – D.R. Dietderich LARP Cable R&D D.R. Dietderich LBNL.
GROUP C – Case study no.4 Dr. Nadezda BAGRETS (Karlsruhe Institute of Technology) Dr. Andrea CORNACCHINI (CERN EN Dept.) Mr. Miguel FERNANDES (CERN BE.
Status of the PMT light detection system Gian Luca Raselli 20-AUG-2015 ICARUS executive meeting.
MQXF Q1/Q3 Conductor Procurement A. K. Ghosh MQXF Conductor Review November 5-6, 2014 CERN.
Magnet design, final parameters Paolo Ferracin and Attilio Milanese EuCARD ESAC review for the FRESCA2 dipole CERN March, 2012.
Conductor Review Oct 16-17, 2013LARP Strand :Specs. Procurement, Measurement- A. Ghosh1 LARP Strand: Specifications, Procurement and Measurement Plans.
1st FNAL-CERN Collaboration Meeting Fermilab, May 13, 2011
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
E. Todesco OUTPUT OF THE CABLE REVIEW E. Todesco and the QXF team CERN, Geneva Switzerland CERN, 10 th December 2014 QXF design review, CERN.
LARP Meeting, Oct. 6, 2005 D.R. Dietderich, LBNL1 LARP Cable R&D FY05 & FY-06 Plans D.R. Dietderich, LBNL Geneva, IL October 5-6, 2005 bnl – fnal – lbnl.
Outline: Strand R&D and strand procurement and inventory. Main parameters of the cable without a core. Results obtained during the cable development without.
24 Th January Status of the Conductor Development Status of the manufacturing for Alstom Status of the manufacturing for SMI L. Oberli.
Philip Schwarz TE-MSC-MNC 1 Engineering Specifications for ELENA ring and TL magnets Philip Schwarz on behalf of WP 2.2 ELENA IIC meeting 5 th December.
HL-LHC/LARP Cable Review, CERN, Nov Lessons Learnt in LARP- A. Ghosh 1 Lessons Learnt from LARP experience Arup. K. Ghosh HL-LHC/LARP International.
HL-LHC QXF Conductor/Cable Internal Review. Thank You First of all, let me thank everybody for accepting an extended work time and have this meeting over.
29 th September 2009 EuCARD-WP7 HFM Conductor specification and procurement Luc OBERLI CERN, TE-MSC-SCD.
CDR for the ESS Linac Magnets for LWUs (pulsed quadrupoles and DC correctors) Closeout May 4, 2016 J.G. Weisend II, Chairman CDR.
TQC03e Test Status  Magnetic measurements at 300 K  Z-scan at ±10 A  Magnetic measurements at 4.6 K (I max up to 6.5 kA)  Quench training and ramp.
Discussion about the technical specification of the Nb-Ti strand and Rutherford cable for the MCBXF corrector magnets.
Cold mass procurement, status and plan, QA-QC H. Prin With contribution from S. Becle, O. Housiaux, R. Principe, J.-L. Rudeiros Fernandez, F. Savary 3.
Answers to the review committee G. Ambrosio, B.Bordini, P. Ferracin MQXF Conductor Review November 5-6, 2014 CERN.
11T Quality Assurance O. Housiaux, R. Berthet, S. Menu, R. Principe 3rd International Review on the 11T dipoles at collimator Section for the HL-LHC 6-8.
LARP Collaboration Meeting 15 Nov 1-3, 2010 A2C- Materials Working Group Arup Ghosh (coordinator), Emanuela Barzi, Dan Cheng, Dan Dietderich, Soren Prestemon,
LARP Collaboration Meeting 15 Nov 1-3, 2010 Conductor Procurement and Qualification Arup K. Ghosh (BNL) bnl - fnal- lbnl - slac US LHC Accelerator Research.
CERN QXF Conductor Procurement and Cable R&D A.Ballarino, B. Bordini and L. Oberli CERN, TE-MSC-SCD LARP Meeting, Napa, 9 April 2013.
MQXF Cable for Q1/Q3 D.R. Dietderich MQXF Conductor Review November 5-6, 2014 CERN.
Procurement of Nb 3 Sn strand, cable fabrication, and quality control for the U.S. Hi-Lumi LHC Accelerator Upgrade Project Lance Cooley, Fermilab L3 manager.
Nb3Sn wiggler development
CERN Cabling Experience FRESCA 2, 11 T Dipole and MQXF A. Ballarino
FCC Conductor Development at KAT-Korea
Lessons learnt from CERN experience
MQXF cable with RRP wires for Q2
Niobium for Long-Length Fine-Filament Nb3Sn Conductors
Crab Cavities Contribution from the U.S.
Development of Nb3Sn (and Bi-2212) strands in preparation for the FCC
CSP 25th November 2010 Technical agreement number 3: overview
Cryostat procurement, status and plan, QA/QC
11 T cable development and procurement strategy at CERN
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
CERN Conductor and Cable Development for the 11T Dipole
MQXF Short Models Status and Plans
Procurement of Nb3Sn strand for coils assembled at CERN
Circuits description and requirements - Closed Session-
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
MQXF cable with RRP wires for Q2
Superconducting Links and Cold Powering components for HL-LHC
Status of the PANDA Solenoid Magnet Production in BINP
MQXF updates P. Ferracin October 9th, 2014.
Daniel Chávez A NbTi Cable-in-Conduit conductor for the
Status of SF Model Dipole Contract with TAMU
East Hall under construction
F.Pasdeloup, H.Prin, L. Williams
Presentation transcript:

logo area 11 T Wire: Procurement Strategy and QA/QC B. Bordini, A. Ballarino, M. Macchini Acknowledgments: thanks to E. Charifoullina for her contribution in the superconductor database development Review of the 11 T Dipoles at Collimator Section for the HL-LHC CERN – 7 th April 2016

logo area Outline  Wire Procurement  Quantities and Scheduling  Documentation from wire manufacturer  List of documents and measurements per shipment  Verification Measurements  Measurements carried out at CERN  Test load vs. laboratory capabilities  CERN Approval Procedure  Superconductor database  3 phases approval procedure  Tracing production  Conclusions 11 T Wire: Procurement Strategy and QA/QC – B. Bordini2

logo area Wire Procurement Number of Coils and Wire quantities  The total length is calculated with 10% margin  3 Unit lengths (86.6 km) for the LS2 prototype were produced with the 169 RRP  In total for LS2 we need 700 km of the RRP 108/127  The prototype for LS3 will use the PIT conductor  In total for LS3 about 1500 km of wire (RRP and PIT) 11 T Wire: Procurement Strategy and QA/QC – B. Bordini3 LS2 LS3

logo area Wire Procurement Schedule 11 T Wire: Procurement Strategy and QA/QC – B. Bordini4 F.C.  Financial Committee S.  Signed (contract) S.R.  Strand Received (first shipment) 500 km RRP 108/ km RRP 108/ km 5 RRP Cables for Prototype 15 RRP Cables for LS2 Series 5 RRP Cables for LS2 Series 7 PIT Cables for Prototype 38 Cables for LS3 Series 3 Cables from previous order

logo area Documentations List of Documents per Shipment  Certificate of Conformance for Delivery  List of spools (CERN and OST ID), Shipped Length, Order Length, Order Weight  Pedigree Report  Sub-Elements and ID of the raw material used in each billet  Raw Material Certificates  Production History  Pieces after intermediate draw (1.6 mm), pieces after final inspection, gross yield (km and %), phase when breakages or cuts occurred  QA Datasheets – Results of the measurements on the wire 11 T Wire: Procurement Strategy and QA/QC – B. Bordini5

logo area Documentations QA Datasheets – Meas. per Piece Length  Continuous measurements of the diameter, ovality and eddy current  At least * : 1 Copper to not-Copper, 1 Twist Pitch length and direction, I c and 1 RRR - (tail of the piece length) *Additional measurements: 1 Cu to not-Cu, 1 Twist Pitch, 1 I c and 1 RRR on the point of the piece length in the case of  the first delivered piece length of a billet  a piece length following a not delivered piece length 11 T Wire: Procurement Strategy and QA/QC – B. Bordini6 Each extremity of the delivered piece lengths are characterized ** XXXX X ** The X indicate the locations of the measured samples

logo area Documentations QA Datasheets – Meas. per Billet  2 micrographs (point and tail) with measurements of the minimum and maximum dimensions of the sub-elements  1 micrograph (tail) of the rolled wire  6 sharp bend tests (3 billet point, 3 billet tail)  6 spring back test (3 billet point, 3 billet tail)  1 I c of 15 % rolled sample (billet tail)  1 RRR of 15 % rolled sample (billet tail) 11 T Wire: Procurement Strategy and QA/QC – B. Bordini7

logo area Documentations CERN Measurements  1 micrographs x billet (tail)  6 sharp bend tests x billet (3 point, 3 tail)  6 spring back test x billet (3 point, 3 tail)  1 I c of 15 % rolled sample x billet (tail)  1 RRR of 15 % rolled sample x billet (tail)  1 magnetization sample x billet  1 diameter, 1 Copper to not-Copper, 1 Twist Pitch length and direction, I c and 1 RRR x piece length - (tail) 11 T Wire: Procurement Strategy and QA/QC – B. Bordini8

logo area Verification Measurements I c measurements per Quarter  200 km (about 50 % for 11 T and 50 % for MQXF) of wire and samples from 6 cables to be qualified per quarter  Verification samples (from the 200 km of wire):  Scenario I:  1 sample per piece length (+ 1 rolled per billet)  4.5 piece lengths per billet  132 measurements  yield equal to 80 %  Scenario II:  3 samples per billet (+ 1 rolled per billet)  96 measurements  yield equal to 80 %  Additional samples: 36 cable samples, 36 coil witness samples  In total 204 measurements in case of scenario I and 168 measurements in case of scenario II 11 T Wire: Procurement Strategy and QA/QC – B. Bordini9

logo area Verification Measurements Laboratory Capability per Quarter  Max I c test capability of the laboratory  6 samples per day (3 test stations)  Assuming 58 days per quarter (once having taken into account holidays and maintenance) 348 measurements  The laboratory would be occupied  58.6% of its capability in case of scenario I (204 I c measurements)  48.3% in case of scenario II (168 I c measurements) 11 T Wire: Procurement Strategy and QA/QC – B. Bordini10

logo area Approval Procedure Database: 3 phases approval procedure  The data from the manufacturer (QA datasheets) are in Excel format and are uploaded automatically in the CERN superconductor database  The results of the CERN verification measurements are also stored in the superconductor database  The approval procedure is managed via the superconductor database and it is divided in three phases: 1.Analysis of the manufacturer data: completeness and conformity. The manufacturer will obtain the green light for shipping the material only when this phase will be by approved 2.Analysis of the CERN Verification measurements: conformity with respect to the technical specification 3.Comparison between manufacturer and CERN data: the difference shall be limited 11 T Wire: Procurement Strategy and QA/QC – B. Bordini11

logo area Approval Procedure Tracing Production 11 T Wire: Procurement Strategy and QA/QC – B. Bordini12 Quantity [km] n° billets23 Average I c, RMS [A]461.4, 18 Average RRR, RMS293.6, 40.8

logo area Approval Procedure Tracing Production 11 T Wire: Procurement Strategy and QA/QC – B. Bordini13

logo area Conclusions  The procurement strategy and the wire measurement capability of the laboratory satisfy the needs of the project  To guarantee the quality of the received wire, CERN requires for each billet  A comprehensive documentation that describes the production process and the used raw material  A detailed measurement campaign from the manufacturer  Extensive verification measurements that cross-check the manufacturer data  All the data are stored (electronically) in the superconductor database and an extract of these results is sent to the WP11 QA team  The material approval procedure is managed via the superconductor database  Matlab routines, which extract the data from the superconductor database, trace the evolution of the wire production 11 T Wire: Procurement Strategy and QA/QC – B. Bordini14

logo area Thank You For Your Attention ! 11 T Conductor Performance – B. Bordini15  The procurement strategy and the wire measurement capability of the laboratory satisfy the needs of the project  To guarantee the quality of the received wire, CERN requires for each billet  A comprehensive documentation that describes the production process and the used raw material  A detailed measurement campaign from the manufacturer  Extensive verification measurements that cross-check the manufacturer data  All the data are stored (electronically) in the superconductor database and an extract of these results is sent to the WP11 QA team  The material approval procedure is managed via the superconductor database  Matlab routines, which extract the data from the superconductor database, trace the evolution of the wire production