February 13, 2007C.M. Ginsburg (Fermilab-TD)1 Fermilab Vertical Test Facility for ILC cavities Vertical Cavity Test Facility (VCTF) IB1 infrastructure.

Slides:



Advertisements
Similar presentations
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Advertisements

SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
ESS Cryogenic System Design
Current status Arkadiy Klebaner November 21, 2012
ESS Cryogenic System Process Design Philipp Arnold Section Leader Cryogenics CEC – ICMC 2015 June 29, 2015.
Engineering and Design Group Fermi National Accelerator Laboratory Cryogenic Department AAC Review, May , 2005 Jay Theilacker HPTFCRYOGENICS.
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
US Cavities Status and Plan Mark Champion 01 October 2009.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Shekhar Mishra, Fermilab Mark J. Oreglia, Univ. of Chicago
Overview of the ILC and SRF Program (With an emphasis on Px) Shekhar Mishra ILC & SRF Program Fermilab.
LARP LQX and MQX Magnets Cryogenic Testing at Fermilab’s Industrial Building 1 Roger Rabehl Technical Division/Test & Instrumentation Department.
Vertical Test Stand Update C.M. Ginsburg (Fermilab) For the VTS group: C.Sylvester, Y.Huang, R.Nehring, J.Ozelis, T.Peterson, V.Poloubotko, R.Rabehl, I.Rakhno,
Fermilab Vertical Cavity Test Facility (VCTF) VTS2&3 Project Status Ruben Carcagno, Camille Ginsburg, and Cosmore Sylvester On behalf of the VTS Group.
F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Vertical Test Stand in IB1 C.M. Ginsburg (Fermilab) for the IB1 VTS Group SRF R&D Meeting 6.July 2006.
M. Ross, N. Walker, A. Yamamoto ILC Cost Review, (updated for TB) and Cost Drivers  Future R & D ILC Cost Review (M. Ross,
ILCTA_IB1_VTS An in-ground vertical test facility for ILC SRF cavities at Fermilab Camille M. Ginsburg ILC SRF Technical Status Meeting 5.May 2006 for.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal Shekhar Mishra (Hasan Padamsee, John Mammosser, Mike Kelly) For the WBS 9 Collaboration.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal.
Horizontal Test Stands and CC2 Results Andy Hocker Testing an alternative ILC cavity design at USPAS (Q 0 =2.23E+02)
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Project X RD&D Plan Cryogenics Arkadiy Klebaner AAC Meeting February 3, 2009.
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
NML Cryogenic System Arkadiy Klebaner Cryomodule One Commissioning June 3, 2011.
17-18 December 2013 LARP VTF Workshop BNL Proposal 1 A.Marone
CMTF Cryogenics (status and plans) SRF program and AD/Cryogenics work presented by Arkadiy Klebaner May 21, 2013.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
MICE Coupling Coil Test Proposal Ruben Carcagno Fermilab July 9, MICE CC Test Proposal7/11/2011.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
CMTF Cryogenics Arkadiy Klebaner May 6, Outline CMTF cryogenic system scope Goals Key functional requirements Conceptual layout Cryoplant Current.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
SRF Collaboration Shekhar Mishra Fermilab. Overview Charge: Does the laboratory make effective use of collaboration and existing SRF capabilities at other.
Status of Vertical Test Stand at RRCAT P Shrivastava, P Mohania,D.Baxy, Vikas Rajput S C Joshi, S Raghavendra,S K Suhane RRCAT, Indore November 26, 2012.
Cryogenics for SuperB IR Magnets J. G. Weisend II SLAC National Accelerator Lab.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
SRF Test Facilities – Functions and Costs Alexander Romanenko Test Facilities Review 17 Mar 2015.
Chapter Editor: John Weisend TDR Chapter 6 Cryogenic System, Vacuum System & Test Stands.
Preliminary Review of LERF as Cryomodule Testing Facility for LCLS-II
Mike Anerella December 17, 2013
Ti/SS transitions A.Basti INFN-PISA*
for the FNAL/ANL, JLab, and Cornell cavity teams
Progress and Issues with VTS Upgrade
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
LARP Vertical Test Facility
ESS RF Development at Uppsala University
Accelerator Module Test Facility
Horizontal Tests in a Vertical Cryostat
Presented by: Ruben Carcagno
CTF Users’ Perspective
Conceptual design of the Cryogenic System of Comprehensive Research Facility for Key Fusion Reactor Core Systems Liangbing Hu Sep.4.
Presentation transcript:

February 13, 2007C.M. Ginsburg (Fermilab-TD)1 Fermilab Vertical Test Facility for ILC cavities Vertical Cavity Test Facility (VCTF) IB1 infrastructure Future upgrades

February 13, 2007C.M. Ginsburg (Fermilab-TD)2 Purpose of VCTF Test cavity quality (Q, Eacc) –Study cavity production and processing (i.e., S0 goals) –Cavity acceptance test prior to cryomodule assembly Develop Fermilab SCRF expertise –Contribute to world effort –Apply to new projects Technology transfer to university groups, other labs, industry Validate ILC project costs & technical performance

February 13, 2007C.M. Ginsburg (Fermilab-TD)3 VCTF Initial Project Scope One Vertical Test Stand (VTS) in Industrial Building 1 Single, bare 1.3 GHz 9-cell Tesla-style cavities Measure Q vs. T (T min ~1.5 K) Measure Q vs. E acc at 2 K 250 W (CW) max RF power required Q>5x10 9 and Eacc<35 MV/m or P d = (1.04 x )* E acc 2 /Q 0 < 250 W Use existing IB1 cryogenic capacity ~125 W at 2 K –250 W for short periods without excessive bath temp increase Maintain “Controlled Area” status in IB1 < 5 mrem/hr immediately outside the shielding <0.25 mrem/hr in normal working areas

February 13, 2007C.M. Ginsburg (Fermilab-TD)4 VCTF in Industrial Bldg 1 Significant cost savings and faster implementation Capable of delivering LHe to the test stand at a peak rate of 700 liters/hr and Maintaining a bath temperature of 2K with up to 125 W of continuous power dissipation (250 W for short periods w/o excessive bath temp increase) Knowledgeable technical staff VTS pit Existing IB1 cryoplant/infrastructure for Magnet Test Facility (MTF) Existing cryogenic utilities & vacuum lines

February 13, 2007C.M. Ginsburg (Fermilab-TD)5 VTS Cryostat/Insert Design 16’ heat exchanger phase separator radiation shielding vacuum vessel  =42” Helium vessel 26.5” cavity Based on Fermilab design of DESY/TTF/VTS Added phase separator for better quality He Cryostat under construction at PHPK Technologies, Columbus OH Current schedule – complete end February 2007 Top plate insert

February 13, 2007C.M. Ginsburg (Fermilab-TD)6 Magnetic Shielding Surface resistance increases due to trapped magnetic flux in localized normal-conducting surface impurities Magnetic field at IB1 floor in pit region measured to be consistent with Earth’s magnetic field (~0.5 G) Two-layer design: –Outer RT cylindrical shield, attached to pressure vessel OD Amumetal ( 80% Ni alloy) 0.040” thick –Inner 2K cylindrical shield, attached to helium vessel ID, with perforated (for LHe flow) endcap Cryoperm 0.040” thick –<0.01 G at cavity, with significant safety margin –Both “permanently” installed in/on cryostat to avoid damage Under construction at Amuneal Manufacturing Corp., Philadelphia, PA Current schedule – complete end February 2007

February 13, 2007C.M. Ginsburg (Fermilab-TD)7 Radiation Shielding 6” steel 18” normal concrete X-rays estimated from DESY data Thanks DESY staff! Design from MARS15 simulation approved by ES&H (Fermilab-TM-2350-AD) Tritium production negligible “Controlled area” satisfied Parts being ordered normal concrete lead borated polyethylene, steel Additional borated poly at instrumentation trench opening (not shown)

February 13, 2007C.M. Ginsburg (Fermilab-TD)8 RF System Based on proven Jefferson Lab VTS RF system with technology advances Proven JLab LabView-based data acquisition system –Very user friendly – useful when we have visitors at test stand Collaboration with Jefferson Lab established (T. Powers, C. Grenoble) added to Jefferson Lab MOU Internal Fermilab review August 24, 2006 – all reviewers’ recommendations incorporated RF personnel safety interlocks design approved by ES&H All parts received – in an advanced assembly stage

February 13, 2007C.M. Ginsburg (Fermilab-TD)9 Control room and instrumentation Under preliminary assembly Cryostat Instrumentation trench Cable trays Control room

February 13, 2007C.M. Ginsburg (Fermilab-TD)10 Parasitic research goals Anticipate having a “diagnostic” top plate insert, ready to go when high-throughput cavity tests are paused Program will evolve depending on outcome of ongoing R&D. Current proposals: –Thermometry for quench location in 9-cells –Field emission studies with x-ray detectors –Systematic study of magnetic field on cavity performance –Single-cell studies (processing techniques, large grain Nb, other materials, other cavity shapes) –“Collaboration” established and developing with Fermilab PPD scientists with instrumentation experience. Anticipate involving others.

February 13, 2007C.M. Ginsburg (Fermilab-TD)11 Single VTS Throughput TaskDuration (hours) Receive cavity and cage0 Mount cages to insert1 Connect cables and TDR test1 Install insert in dewar1 Perform Dewar seal check0.5 Perform Dewar leak check1 Backfill Dewar, helium contamination check0.5 Cooldown to 100K, 8 g/sec0.5 Wait at 100K for 8 hours (for Q-disease study)8 Cooldown to 4K1 4K2 Pump to 2K3 RF Test at 2K4 Boil off LHe4 Warmup Dewar17 Remove insert1 Remove cavity cage from insert1 Total single-cavity test cycle duration hours becomes 5 days with current infrastructure, primarily from waiting for people to become available

February 13, 2007C.M. Ginsburg (Fermilab-TD)12 Single VTS Throughput (cont.) IB1 Cryogenic System Downtime60days IB1 Vacuum Pumps Unavailable24days LHe Inventory Unavailable12days VCTF Unavailable15days TOTAL EQUIPMENT UNAVAILABILITY111days HOLIDAYS10days VTS Test Cycle (incl. shift operations)5days Number of Test Cycles in a Year48

February 13, 2007C.M. Ginsburg (Fermilab-TD)13 Projected Annual # Cavity Tests for S0 (from S. Mishra, ART FY08-09 Planning Meeting at SLAC 9/13/06) 48/year Required capacity exceeded in first couple of years

February 13, 2007C.M. Ginsburg (Fermilab-TD)14 Add vertical test throughput Upgrade VTS for two-cavity operation Add two more vertical test stands to VCTF Upgrade cryogenic infrastructure

February 13, 2007C.M. Ginsburg (Fermilab-TD)15 Two-cavities in VTS Single most effective way to increase throughput RF test one cavity at a time RF portion of cavity test <10% of test duration, can substantially increase throughput by cooling/warming two cavities simultaneously 5 days -> 6 days total test cycle duration VTS spatially accommodates two cavities Radiation shielding sufficiency to be determined, but should be possible with minimal upgrades Increases to 80 test cycles/year (almost factor 2)

February 13, 2007C.M. Ginsburg (Fermilab-TD)16 Two add’l VTSs and staging area

February 13, 2007C.M. Ginsburg (Fermilab-TD)17 Two add’l VTSs and staging area RF testing still one cavity at a time (not strong constraint) Common RF/DAQ system (except RF amplifier) Staging area to accommodate 6 top plates, each supporting two cavities As similar as possible to first VTS to minimize civil/mechanical/radiation shielding design and procurement costs ~180 tests/year (cryo system risk limited…)

February 13, 2007C.M. Ginsburg (Fermilab-TD)18 VCTF Cryogenic Infrastructure Upgrades Reduce schedule risk by adding safeguards to reduce downtime –Add compressor and full-flow purifier skid at vacuum pump outlet to eliminate contamination from sub-atmospheric operation (primarily air-leaks) Decouple vertical cavity testing from superconducting magnet tests. –Install dedicated vacuum pump for cavity vertical tests to de- couple from superfluid magnet tests –Add dedicated 10-ton crane Add helium gas storage capacity and staff to accommodate three VTS cryostats All upgrades require additional transformer ~264 cavity tests/year

February 13, 2007C.M. Ginsburg (Fermilab-TD)19 Proposed VCTF Cryosystem Upgrade

February 13, 2007C.M. Ginsburg (Fermilab-TD)20 Scenario IB1 Cryo system statusas-isupgrade #VTS cryostats1313 #cavities in all available VTS cryostats Downtime cause Cryo down Pumps unavailable LHe supply unavailable VTS unavailable holidays10 Total down days VTS test cycle # tests [1 ] [1 ] [1] [1] Scenario carries considerable risk because lack of purification system to remove contamination introduced by three sub-atmospheric test stands could significantly increase cryogenic system downtime. Infrastructure Scenarios

February 13, 2007C.M. Ginsburg (Fermilab-TD)21 Cost Summary Infrastructure M&S ($) SWF (FTEs) SWF ($k) Total with Indirect ($k) VTS-1 (FY07 to complete) VTS-1 (w/ 2 cavities) VTS-2 and Cryogenic system upgrade

February 13, 2007C.M. Ginsburg (Fermilab-TD)22 Conclusions Vertical Cavity Test Facility with one Vertical Test Stand well underway, to be operational in FY07 –Will establish Fermilab as an ILC cavity testing facility Infrastructure upgrades required to –accommodate more cavities to maximize cavity throughput, and –advance SCRF technology Develop Fermilab SCRF expertise –Develop collaborations on cavity diagnostic instrumentation for SCRD R&D –Apply advances to new projects Technology transfer to university groups, other labs, industry –SCRF R&D effort –Accommodate visitors with user-friendly facility