Remedial Measures Plans Response to EQC Questions June 21, 2011 Presentation to Lexington-Fayette Urban County Government Environmental Quality Committee.

Slides:



Advertisements
Similar presentations
Wakulla County Sewer Project Eutaw Utilities Presentation April 7, 2011.
Advertisements

Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
Stave Lake Water Supply & Treatment Project. Existing Water Supply System Norrish Creek Cannell Lake 19 Groundwater Wells.
City of Clinton Fiscal Year 2013 Sewer Rate Recommendations Committee of the Whole April 24, 2012.
Wastewater Collection Options for Lakota Beach Area Sub-Basin Special Meeting June 27, 2001 John Bowman Lakehaven Utility District (253)
Evaluation of Private Property I/I Sources for Sanitary Sewer Evaluation Study City of Grand Rapids – E. Leonard Heights Area Presenter: Jay Zawacki, CDM.
South Maple Street Sanitary & Storm Sewer System Improvements Project October 14, 2014.
STATUS OF CARLSBORG SEWER PROJECT Carlsborg Community Advisory Council Bob Martin June 6, 2013.
ROUTE 27 (PARK STREET) CORRIDOR SEWER EVALUATION Mark J. Thompson, P.E. Gus O’Leary Kleinfelder / S E A Consultants Inc.
City of Farmersville, Texas Water and Wastewater Rate Study February 2011.
Charlie Lake Sewer Collection System & Lagoon Upgrades Thursday June 20 th, 2013.
Water Rates Utility Rates & SDCs Presentation to the West Linn City Council October 5, 2009.
Community Water Supply Resources Implementation Strategy Lane Auditorium Albemarle County Office Building September 13, 2007.
Photos by Susie Fitzhugh Building Excellence Presentation Community Engagement April 2012.
Presentation to CITY OF PALM COAST, FLORIDA WATER AND WASTEWATER RATE STUDY AND BOND FEASBILITY REPORT Prepared in Conjunction with the Issuance of Utility.
City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010.
STORMWATER MANAGEMENT PROGRAM UPDATE July 23, 2014.
1 Manassas Park Town Meeting 29 October Welcome This is the first Manassas Park Town Meeting Governing Body implemented this as a way to improve.
Tysons 1 Operational Analysis of Dulles Toll Road Ramps to Tysons Board Transportation Committee Meeting September 17, 2013 Seyed Nabavi Fairfax County.
Utility Extension Project
Considering Tax-Supported Debt May 10, 2004 Presentation to City Council Roger Rosychuk Corporate Services Department.
Wastewater Collection System Optimization An Innovative Approach to Capital Improvement Planning COPYRIGHT – OPTIMATICS PTY LTD
Imagine the result Impact Study on MSD Rate Payers of Proposed Consolidation/Merger Phase II – Towns of Biltmore Forest, Montreat and Weaverville Presentation.
 Prepared for  City of Palm Coast, Florida  June 24, 2014 Drummond Property Acquisition in Connection With The Land Donation of 70 Laramie Drive From.
SSES and GIS, A Great Partnership Cindy Fort, PE Technical Director Environmental Engineering and Jeff McCann GIS Coordinator.
Special Order by Consent Wastewater Collection Improvement Projects Mark Fisher and Dennis Asbury Final Report to City of Eden October 20, 2009.
Water Supply Planning Initiative State Water Commission November 22, 2004.
Metropolitan Council Environmental Services A Clean Water Agency Presented to the Environment Committee February 9, 2010 Legislative Update: Inflow & Infiltration,
Waste Water Facilities Plan Update November 2, 2009 Palmer Engineering Company / Hazen & Sawyer / CDP Public Hearing Presentation.
3TB Project Review Tax Increment Financing (“TIF”) Overview January 25, 2013.
Debt Strategy Presentation to City Council May 10, 2004 Click to edit Master title style.
Financial Impact of Drought March 5, 2008 Updated 3/17/08.
Facilities Plan Update July 2, 2009 Palmer Engineering Company / Hazen & Sawyer / CDP.
TENTATIVE BUDGET PRESENTATION CITY COUNCIL PUBLIC HEARING SEPTEMBER 8, 2010.
PROPOSED BUDGET PRESENTATION CITY COUNCIL WORKSHOP AUGUST 23, 2011.
1 Public Hearing User Rate Adjustments April 8, 2008.
1 1 City Commission Workshop for the DRAFT Basis of Design Report December 14, 2015 CRAVEN THOMPSON & ASSOCIATES, INC.
Road Map to the Future: The Consolidation of Sewer Infrastructure in Rutherford County, NC November 16 th, 2015.
Ordinance Amending Chapter 37 Orange County Code Utilities Department October 21,
Western Hills Water DistrictWater Rate Update Board Meeting HF&H Consultants, LLC 0November 4, 2015 HF&H Consultants, LLC Western Hills Water District.
I-35W/Highway 62 Crosstown Commons Reconstruction Nathan Aul, Bob Krussow, and Michael Martin.
PECO Smart Ideas for Your Business Greater Philadelphia Association of Energy Engineers Mike O’Leary, PECO April 20, 2016.
Hernando County’s Utilities Infrastructure Opportunity through the American Recovery and Reinvestment Act of 2009 (the Federal Stimulus Package)
CITY OF ARCATA -WATER AND WASTEWATER CAPITAL IMPROVEMENT PROGRAM: RATE SETTING.
City of McCall Sanitary Sewer I&I Study Community Stewardship for Economic Benefits Nathan Stewart, PE, City Engineer Matt Neukom, PE, Project Manager.
Heritage Park Area Mandatory Connection Final Information Meeting March 14, 2016.
Effectiveness of Private Property Infiltration and Inflow Reduction efforts in East Tosa October 14, 2014: Wauwatosa Budget and Finance Committee Meeting.
1% Sales Tax Commission Board Meeting June 3, 2015.
LFUCG Group 1 Remedial Measures Plans September, 2011 Presentation to Lexington-Fayette Urban County Residents.
Town Branch Wet Weather Storage Public Information Meeting February 19, 2014 Lexington Fayette Urban County Government Division of Water Quality.
CITY OF PORT ARTHUR, TEXAS BUDGET WORKSHOP July 12, 2005.
What are they and how are they calculated? May 2015.
Operating Efficiencies Costs to operate and maintain the water and sewer system have not varied significantly during the first 5 years of operation.
MWRA WATER SOURCE TOWN MEETING OCTOBER 05, :30 PM NR HIGH SCHOOL PERFORMING ART CENTER.
Status Update on USEPA Compliance Sausalito City Council February 26, 2013 SMCSD Directors Raymond Gergus, President Bill Ring, Vice President Ann Arnott.
County Road 19(Manning Road) & County Road 22 Improvements Environmental Study/ Preliminary Design Report November 2008.
CONGAMOND ROAD ROADWAY IMPROVEMENT INFORMATIONAL MEETING
Stage 2 Light Rail Transit Program “In the ground ready”
Marquis Hills Area Information Meeting December 7, 2016
Welcome to the Libertyville Stormwater Master Plan Open House
Regional Roads Committee
Marquis Hills Area Information Meeting December 7, 2016
I-280 Corridor Study and I-280/Winchester Blvd Project
WEST & EAST DISTRICT PROJECTS PRESENTATION
Residential Sewer Lateral Maintenance Program Analysis
City of Rehoboth Beach Water and Wastewater Financial and Rates Review
Facilities Plan Update
Biltmore C Proposed Water & Sewer Improvement Project
2018 Water/Wastewater Rate Study and Financial Forecast
Space Coast TPO State Road (S.R.) 528 Update
Presentation transcript:

Remedial Measures Plans Response to EQC Questions June 21, 2011 Presentation to Lexington-Fayette Urban County Government Environmental Quality Committee

Agenda Preliminary cost estimate details Potential penalties for non-compliance and post-RMP SSOs Precedents from other communities Resolution of high-profile problem areas Construction management – internal vs. external Issues previously addressed Critical issues yet to be addressed

Background Information RMP being developed per CD requirements Group 1 RMP due October 2011 Critical Issue – selection of Level of Service (Design Storm) Potential costs - $500+ to $800+ million EPA likely to require at least a 2-yr design storm (matches Capacity Assurance criteria and precedents)

Monthly Rate Impacts (20-yr Loan) StormRainfallEstimated CostRate Impacts 2-Year3.2”$540 million$ Year3.8”$718 million$ Year4.3”$814 million$42.59 Potential monthly rate increases are based on financing capital improvements for 20 years at 3%, spread to 106,000 customer accounts. Rate increases would be implemented over 10 years.

Monthly Rate Impacts (30-yr Loan) StormRainfallEstimated CostRate Impacts 2-Year3.2”$540 million$ Year3.8”$718 million$ Year4.3”$814 million$32.38 Potential monthly rate increases are based on financing capital improvements for 30 years at 3%, spread to 106,000 customer accounts. Rate increases would be implemented over 10 years.

Cost Estimate Details Maps of 2-yr storm upgrades (7 watersheds) Map of 5-yr storm upgrades (for representative West Hickman watershed) Map of 10-yr storm upgrades (for representative West Hickman watershed) Table of 2-yr, 5-yr, 10-yr system costs (pipes, EQ, WWTPs) Initial estimates assume no I&I reduction Improvements shown are for initial concept – final solutions will vary (i.e. including rehab, etc.)

Wolf Run Improvements: 2-Year LOS

Cane Run Improvements: 2-Year LOS

Town Branch Improvements: 2-Year LOS

South Elkhorn Improvements: 2-Year LOS

North Elkhorn Improvements: 2-Year LOS

East Hickman Improvements: 2-Year LOS

West Hickman Improvements: 2-Year LOS

West Hickman Improvements: 5-Year LOS

West Hickman Improvements: 10-Year LOS

Table of 2, 5, 10-yr Storm Costs

Potential Regulatory Penalties Fines –Any SSO after its elimination deadline –$1000 to $5000 depending on volume Frame of reference: –Average 480 SSOs per year –Financial penalties would have ranged from $480,000 to $2,400,000 per year

Related Design Storm Issues 2-year storm is likely the smallest storm EPA would consider Selection of 2-year storm would result in lowest cost and lowest rate increases Selection of larger storm event would have higher costs, but would have less SSOs, less residential impacts, and less regulatory fines –Building improvements for the 2-year storm would result in an estimated 13 SSOs during a 5-year storm, and 53 SSOs during a 10-year storm

Precedents – Design Storm Louisville MSD: 2-year Knoxville: 2-year Nashville: 2-year Northern KY SD1: 2-year Atlanta, GA: 2-year Greenville, NC: 2-year Winchester: 5-year Birmingham, AL:10-year Richmond, VA:2- and 10-year (TBD) Pittsburgh, PA:2- and 10-year (TBD)

Precedents – Cost Recovery Louisville MSD: Water usage + surcharge Northern KY SD1 : Water usage Knoxville: Water usage Nashville: Water usage Winchester: Water usage Richmond: Water usage Frankfort: Water usage

Other Current Sewer Rates - BGADD Based on 4000 gallons/month usage

Other Current Sewer Rates – Other Cities

High-profile Problem Areas to be Resolved (Group 1) Richmond Road / Idle Hour Neighborhood Woods Lane / Barrow Wood Lane Tates Creek Road at Malabu and Kirklevington Montavesta Dr / Lansdowne Merrick Park Bob O’ Link Road Valley Park near Deauville Drive Normandy Road / Gardenside Park East Hickman Pump Station Wolf Run Pump Station WWTP bypasses Other areas to be addressed through continued funding of major I&I reduction work

Issues Already Addressed North Elkhorn Pump Station & Force Main South Elkhorn PS Dixie and Deep Springs (current) Bluegrass Airport Pump Station (current) Four cross connection eliminations Numerous collection system repairs –Sump pump disconnections – voluntary –Downspout redirections

Near-Future Work Wolf Run Pump Station Expansion Area 2A Pump Station Blue Sky Parkway Town Branch Pump Station Pump station eliminations FY12 collection system rehab

Construction Management Options Status Quo: DWQ Construction Manager Current average: $12 million/yr (+/-) Potential projects: $54 million/yr (+/-) Potential CM costs are included in estimates (Inspection by design engineer); program management by RMP consultant Immediate Issue – streamlining procurement for design, property acquisition, and construction

Critical Decisions Needed Level of Service –Design Storm (2-year, 5-year, 10-year) Initiate Private Property Policy Task Force

Questions?