Review of 2014/15
Topographic surveys
Lidar surveys 2014/15 Partial areas only All signed off and loaded to website
Lidar surveys 2013/14 Complete coverage of SE, mostly to MLWS One area [Medmerry] completely signed off. Of remaining 11, 4 polygons recently re-issued by Geomatics
UKHO survey status (March 2015)
Dark green in 100% swath bathymetry (IHO Order 1/1a)
Swath bathymetry surveys - CHP
Northeast
Waves, tides and met New tide gauge on Arun Platform (some set-up problems)
Eastbourne Pier (REX)
Terrestrial ecological mapping Specification refined Specification refined Work to be commissioned for F/Y 2015/16, to map 2013 ortho- photography, and compare with 2008 results Work to be commissioned for F/Y 2015/16, to map 2013 ortho- photography, and compare with 2008 results
Monthly website hits
Quarterly downloads from website (SE)
Medmerry
Next year?
Phase IV STAR schedule ActivityTimeStart DateTarget DateStatus Coastal Group agreement to prepare STAR Apr-13 Complete Free availability of project data to all (EA board) Aug-13 Outstanding Formation project board Oct-13 Complete Establish current financial rules for FDGIA Oct-13 Complete Consultation with various EA tiers on programme content (EA) Oct-13Jan-14Ongoing Consultation with LA operating authorities Oct-13 Complete Programme design Mar-14Sep-14Complete New programme elements - design and consultation Aug-14Sep-14Complete Project Board and Steering Group Sep-14Complete Local Authorities democratic process for lead authorities Sep-14Dec-14Started Develop procurement/delivery strategy Aug-14Sep-14Ongoing STAR production May-14Dec-14Started Present to Coastal Groups Winter 14/15 Submit STAR to LPRG Feb-15 OJEU Procedure advertise for framework tenders 167 days Jan-15Jul-15 OJEU Contract Notice Period 30 days Feb-15Mar-15 LPRG recommendation Mar-15 Contract documentation & award for 2016 Feb-16Mar-16 Coastal Monitoring Programmes for (SE from 2017) 01 April March 2022
Phase IV STAR schedule ActivityTimeStart DateTarget DateStatus Coastal Group agreement to prepare STAR Apr-13 Complete Free availability of project data to all (EA board) Aug-13 Ongoing Formation project board Oct-13 Complete Establish current financial rules for FDGIA Oct-13 Complete Consultation with various EA tiers on programme content (EA) Oct-13Jan-14Complete Consultation with LA operating authorities Oct-13 Complete Programme design Mar-14Sep-14Complete New programme elements - design and consultation Aug-14Sep-14Complete Project Board and Steering Group Sep-14Complete Local Authorities democratic process for lead authorities Sep-14Dec-14Complete Develop procurement/delivery strategy Aug-14Sep-14Complete STAR production May-14Dec-14Complete Present to Coastal Groups Autumn/winter 2014/15 Complete Submit STAR to LPRG Feb-15 Complete OJEU Procedure advertise for framework tenders 167 days Jan-15Jul-15 OJEU Contract Notice Period 30 days Feb-15Mar-15 LPRG recommendation Mar-15 Aug-2015 Complete Contract documentation & award for 2016 Feb-16Mar-16 Coastal Monitoring Programmes for (SE from 2017) Apr-16Mar-22