LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the.

Slides:



Advertisements
Similar presentations
Improved anchoring of SSS with vacuum barrier to avoid displacement Ofelia Capatina (speaker), Katy Foraz (coordinates all the activities), Antonio Foreste,
Advertisements

A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
Vacuum, Surfaces & Coatings Group Technology Department Cleanness of the 3-4 cold beam lines Outline:  History: Status of 2009 cleaning  Foreseen and.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Quality control of LHC electrical interconnections to be produced during the 2009 shutdown Since the functional properties of the LHC electrical interconnections.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
Overview of SMACC-QA 1.Recall of SMACC-QA organization 2.Tuning the procedures 3.Main results from the QC teams 4.Auditors findings Ranko Ostojic 23 July.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Magnets repair for 3-4 sector Lucio Rossi Reinstallation and interconnections Francesco Bertinelli Vacuum system – How to get ready for beam ? Vincent.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
2 IMPACT - THE FIRE PERMIT = Hot Work Permit 3 Welcome ! This course is linked to the use of IMPACT, so it is assumed that: You know how to use IMPACT.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
MTF – Manufacturing and Test Folder Large Scale Deployment of MTF Sonia Mallón Amérigo Elena Manola-Poggioli on behalf of the EDMS Team, TS-CSE.
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project … Courtesy ….
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
RF power couplers vacuum issues J.M. Jimenez Vacuum, Surfaces and Coatings Group (TE-VSC)
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Logistics for DYPB activities Bruno PUCCIO (TE/MPE)
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
TE-CRG Activities D. Delikaris, TE-CRG.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
A. Perin, TE/CRG, DFBA LSC Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
MSC Technical Meeting 29 August 2013 Overheated QBBI.A21L6 F. Savary with contributions from N. Dalexandro, H. Prin, C. Scheuerlein, P. Voisin.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop ***********************************
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
First LHC Splice Review Introduction
SMACC Tenth report [15 min] 13/09/2013
BA6 – crab cavity activities in EYETS
Status of LHC installation & New Installation Schedule
SPS cryogenic proximity equipment and SM18 validation
Long Shutdown for the LHC: Vacuum Beam Pipes
Consequences of warming-up a sector above 80 K
Hollow e- lens, Cryogenic aspects
MPE main activities planned for LS2
Renovation of the 45-year old PS magnets
Cryogenic Risk Assessment in LHC
UK RFD Pre-Series cryomodule
K. Foraz on behalf of OSS members
On behalf of TE-VSC group
Q1-Q2, Q2-Q3 Interconnect Zone Disconnection Q1 Magnet Extraction
Presentation transcript:

LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the IC teams [Separate presentations: Magnet Situation, VAC, consolidations (QPS, DN200), QC splices]

5 March, 2009 Installation Progress - Francesco Bertinelli 2 Tunnel status of 3-4 in W10/2009

5 March, 2009 Installation Progress - Francesco Bertinelli Reinstalled magnets status Courtesy H. Gaillard

5 March, 2009 Installation Progress - Francesco Bertinelli 4 Shutdown / Consolidation activities  1-2 and 5-6: ongoing since warmup W02 and W03 RF ball test: 3 PIMs with buckled RF fingers in each sector  1-2: removed MB2334 (B16R1) 100 nΩ 50 nΩ Q31R1–Q31L2 (4 IC checked US yesterday OK!)  6-7: warmed up to remove MB2303 (B32R6) 50 nΩ  5-6: 3 connection cryostats He level guards in arc SSS  Stand Alone helium level gauges (3 week window for PIMs)  1R and 5L: triplets copper braid  Pressure relief nozzles (arc and LSS)

5 March, 2009 Installation Progress - Francesco Bertinelli 5 QRL service modules: jumpers Courtesy O. Pirotte  First diagnostic: Q23, Q27 & Q31 bellows deformed from displacement Q25 collapsed bellows from inner pressure  Second diagnostic, more detailed: Some internal bellows damaged some 80K vacuum barriers collapsed due to external over pressure Some soot in QRL piping  In situ repair ongoing: W06: Q23, W07: Q27, W08: Q25, W09: Q31

5 March, 2009 Installation Progress - Francesco Bertinelli 6 IC work: a complex chain of activities Courtesy P. Fessia Some key issues:  ~40 inter-related activities to close an IC  requires several adjacent IC available  several different intervenants  overall duration driven by time between activities (i.e. coordination and quality more important)  cannot all work on the same IC at once  for 3-4: keep same sequence as series activities (important assumption, e.g. avoid AIV2 tests? …)

5 March, 2009 Installation Progress - Francesco Bertinelli 7 Example: electrical connections Courtesy CERN photo  Bus bars  Spools  N-line

5 March, 2009 Installation Progress - Francesco Bertinelli 8 IC sequence & terminology  W15 to W23, with no slack

5 March, 2009 Installation Progress - Francesco Bertinelli 9 IC 3-4 Detailed Planning  Based on detailed surface planning  regular delivery of half cells Courtesy A. Musso

5 March, 2009 Installation Progress - Francesco Bertinelli 10 IC 3-4 Detailed Planning: assumptions  Sequence defined: MEB and chain of surface activities last magnets «ready for installation» W15 sequence and timing to be respected  resources (production and QC) from surface move to tunnel by W15 (i.e. momentarily stop/slow down surface activity)  avoid coactivity conflicts (shutdown, transport, AUG, lifts, Flohe..)  no holidays (Easter, May …): is this realistic?  ignore experience on delays (e.g. humidity for PAQs, Cu/Sn/Ag pollution of some TIG welds, leaks with W closing …)  no (more) extra work (… additional sectors …)  Closing of W bellows: earliest plan for W23  but no vacuum subsectors made available earlier

5 March, 2009 Installation Progress - Francesco Bertinelli 11 Updated IC 3-4 situation W10 magnets are not readily interchangeable (different types, field quality) small improvements through slot changes have been discussed

5 March, 2009 Installation Progress - Francesco Bertinelli 12 IC Resources for series production Over 200 people (Dec – June 2007) IEG (Main Contractor) ~100 people: finished June 2008  now TE-MSC

5 March, 2009 Installation Progress - Francesco Bertinelli 13 IC Resources today  EN-HE & EN-MME: transport and installation  BE-ABP-SU: Survey  TE-MSC: all dedicated sections and ~50% from other sections  TE-MPE: ELQA  TE-VSC: leak testing  TE-CRG: QRL repair  EN-MME: special welding  Collaboration TE-MSC-Krakow: ICIT & ELQA  Collaboration PH-ATLAS-Dubna (for DN200 pressure relief nozzles)  FSUs « Can you use/integrate more new resources? »  we already have

5 March, 2009 Installation Progress - Francesco Bertinelli 14 FSU resources increase  very reactive but …  need to be integrated (e.g. minimum 1 week for access authorisations)

5 March, 2009 Installation Progress - Francesco Bertinelli 15 IC Quality Control  Many new intervenants collaborating (and of course many left...), organisational changes etc. Please accept and help towards this  Quality-Quality-Quality: no paranoia, but need to at least do “as good as before” and better where we know what to improve: let’s not be complacent (“it has always been done like this...”) From first TE-MSC Group Meeting 15 Jan 2009, F. Bertinelli

5 March, 2009 Installation Progress - Francesco Bertinelli 16 Organisation of IC Quality Control Courtesy JP. Tock

5 March, 2009 Installation Progress - Francesco Bertinelli 17 Organisation of IC work, coordination and QC Quality Control Responsible: - qualifies operators/workers, equipment and tooling; - organises/performs pre-inspections before work start; - organises/collects/analyses production data; - organises/performs quality inspections (visual, NDT etc.) of work done; - organises/performs weekly audits to ensure that correct procedures, qualified tooling and operators are used; - organises and analyses qualification and production samples; - ensures traceability of his work (e.g. photos); - is attentive to the general environment constraints around his specific work; - can close NC on delegation of the QCC - shall stop the activity in case of Quality issue Worksite Manager (Engineer in Charge): ensures safety of work conditions, specifically to allow start of work (cryogenics, vacuum, electrical, RP, procedures, work conditions); ensures coordination with other groups and other Worksite Managers; checks qualification of operators, tooling with the QC responsible for each technology before allowing work to start; prepares and follows planning; triggers quality inspections; collects/provides data for traceability (who, when, what, tooling, components, pictures); is particularly attentive to the general environment constraints around specific work tasks (e.g. fragile items); manages NC but do not close them shall stop activity in case of quality issues. Quality Control Coordinator: - organises traveller on worksites - organises traceability (who, when, what, tooling, components) - organises common data collection, storage in MTF of work and components, NC - organises hotline for Management of NC - is attentive to the general environment constraints around his specific work; - allows closure of NC / Closes NC - prepare tools for work within the ALARA principles Operators/workers and their supervision: - Before starting work, requests authorisation from Worksite Manager; - Informs himself of the general environment constraints of the work to be done; - Performs visual control before starting work: in case of NC informs Worksite Manager immediately; - Ensures traceability of work done (when, where, equipment, tooling) and reports on it regularly; - performs first visual control of work done: in case of NC informs Worksite Manager immediately

5 March, 2009 Installation Progress - Francesco Bertinelli 18 IC QC extending to surface Courtesy C. Scheurlein 13 kA cable stabilisation: avoid twisting of strands  standardise tooling, procedures, cleaning Cable straightness: check with dedicated gauge  merge surface and IC activities, production and QC: a healthy effect

5 March, 2009 Installation Progress - Francesco Bertinelli 19 Conclusions on 3-4 i/ii Where do you stand today? IC work starting W07 (next week) main current effort: to finish qualifying machines and people, organising coordination while satisfying shutdown requests in other sectors Is quality under control? Yes, technique is sound (no showstoppers), but … still risky/weak (organisation and routine not smooth, e.g W04 and W05 for surface activities) … but why did 19 September incident happen? so no paranoia, but keep this in mind

5 March, 2009 Installation Progress - Francesco Bertinelli 20 Conclusions on 3-4 ii/ii When do you finish? Plan for W23 (close W bellows), but … are we comfortable? No, see quality, no slack, holidays 4 extra weeks more realistic (more will create further complications with Summer months …) (How) can you go faster? No, see quality above, don’t take chances can extra resources help? Difficult, little time for integration: possibly yes in few special cases (ad-hoc needs e.g. QC and specific individual profiles) flexibility measures will help (coactivity, holidays, longer hours, …)

5 March, 2009 Installation Progress - Francesco Bertinelli 21 Thanks for your attention

5 March, 2009 Installation Progress - Francesco Bertinelli 22 Surface magnet planning  critical path  already balanced activities