Equipment Safety Buy-off g-Comply Tool
Power On Ready In Full Production Mode Deliver and set in place Turnover to Production Power On Time Ready Usage Mode Red Green Equipment Safety Buy-Off Procedure Green Check Point B Deliver and set in place Initial Test Turnover to Production Try-Out Without & With part(s) Red System complexity determines number of Checklist items Check Point A Check Point C Commissioning
Begin Buy-Off (Do-Not Use) Equipment Equipment Safety Buy-Off Overview Power-On & Initial Test Try-Out (with & without parts) Buy-Off Checklist Prepare for Production
Schedule Rate Chart Foot Print Master Listing Checklist Red/Yellow/Green Tags g-Comply
Power On Ready In Full Production Mode Equipment Safety Buy-Off Procedure Green Check Point B Deliver and set in place Initial Test Turnover to Production Try-Out Without & With part(s) Red System complexity determines number of Checklist items Check Point A Check Point C Commissioning
A look at the Modified g-Comply Tool based on your feedback since Black Lake
Procedure Reference Feature Demo
A look at the Modified g-Comply Tool based on your feedback since Black Lake
Highlights of Full Feature Mode Print Red, Yellow, Green Tags
A look at the Modified g-Comply Tool based on your feedback since Black Lake
Highlights of Full Feature Mode Print Red, Yellow, Green Tags Safety Buy-Off Checklist –Red Tag Items –Yellow Tag Items –Green Tag Items
g-Comply Checklist Questions by Category
Total Checklist Questions = 188 How the Checklist Questions are Distributed
X X Power On Ready In Full Production Mode Deliver and set in place Turnover to Production Power On Time Ready Usage Mode Red Green Equipment Safety Buy-Off Procedure Green Check Point B Deliver and set in place Initial Test Turnover to Production Try-Out Without & With part(s) Red System complexity determines number of Checklist items Check Point A Check Point C Commissioning
Laser Example
Adding Lasers from the Specific equipment Laser
How Checklist Question Distribution looks on the tool
Checklist Selection Feature Demo
A look at the Modified g-Comply Tool based on your feedback since Black Lake
Highlights of Full Feature Mode Print Red, Yellow, Green Tags Buy-Off Checklist –Red Tag Items –Yellow Tag Items –Green Tag Items Master Listing Sheet
Allows Program/Project engineers to enter or update their System/Equipment Details Provides 2-way Link to the Schedule Provides Password Protection for Status Updates Coordinates Red / Yellow / Green Tagging (Commissioning) Activities Creates Leadership Status Reports (Foot Print & Rate Chart) g-Comply Master Listing
Master Listing Feature Demo
A look at the Modified g-Comply Tool based on your feedback since Black Lake
Highlights of Full Feature Mode Print Red, Yellow, Green Tags Buy-Off Checklist –Red Tag Items –Yellow Tag Items –Green Tag Items Master Listing Sheet Schedule Safety Resources
g-Comply Scheduling Allows Plant Safety to Plan & Agree to a Schedule –Provides Weekly (7-Day) Calendar for Buy-Off Scheduling, –Provides Black-out dates for health & safety resources –Allows Commissioning Activities to be scheduled in Hourly Segments (from 7 am to 5 pm)
Schedule Feature Demo
A look at the Modified g-Comply Tool based on your feedback since Black Lake
Highlights of Full Feature Mode Print Red, Yellow, Green Tags Buy-Off Checklist –Red Tag Items –Yellow Tag Items –Green Tag Items Master Listing Sheet Schedule Safety Resources Foot Print (Visual Status)
g-Comply Foot Print Provides Status at a Glance for Review with Plant and Launch Leadership Tracks number of Attempts made per cell (min. 3, typ. 5) Displays System Complexity LA103R01; LA103 SCA Unit #2
Foot Print Feature Demo
A look at the Modified g-Comply Tool based on your feedback since Black Lake
Highlights of Full Feature Mode Print Red, Yellow, Green Tags Buy-Off Checklist –Red Tag Items –Yellow Tag Items –Green Tag Items Master Listing Sheet Schedule Safety Resources Foot Print (Visual Status) Rate Chart (Visual Status)
Rate Chart Feature Demo
Equipment Safety Buy-off g-Comply Tool Thank you Questions